Only 20 transitional renewable projects send power to national grid

Only 20 transitional renewable projects send power to national grid

Only 20 transitional renewable energy projects or project segments, or 20% of those that missed out on the Vietnamese government's preferential feed-in-tariffs (FiTs), have been put into commercial operation.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

14 solar power projects given unentitled preferential prices: inspectors

14 solar power projects given unentitled preferential prices: inspectors

Vietnam Electricity (EVN) has been tasked to deal with 14 solar power projects in Ninh Thuan province that have been given feed-in-tariff (FiT) rates that they are not entitled to.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Vietnam Electricity wants gas for power generation to minimize shortage

Vietnam Electricity wants gas for power generation to minimize shortage

State utility Vietnam Electricity (EVN) has asked Petrovietnam's two leading fertilizer subsidiaries, Phu My and Ca Mau, to provide gas for electricity generation instead of producing fertilizers and chemicals to minimize power shortage in May and June.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Vietnam ranks 10th on global renewables FDI league table

Vietnam ranks 10th on global renewables FDI league table

Vietnam was among the top 10 countries in terms of attracting foreign investment in green power technologies in 2022, fDi Intelligence said on Tuesday.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Vietnam renewable investors seek changes in power price policy

Vietnam renewable investors seek changes in power price policy

A letter signed by 36 companies developing wind and solar projects in Vietnam has been sent to Prime Minister Pham Minh Chinh to ask for changes in power price policies.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Bac Lieu wind power developers protest request to cut production

Bac Lieu wind power developers protest request to cut production

Wind power plant investors in Bac Lieu province are protesting the difficulties they have to endure because state utility Vietnam Electricity (EVN) has asked them to cut production.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Ministry figures way out for renewables projects missing feed-in-tariff deadline

Ministry figures way out for renewables projects missing feed-in-tariff deadline

Vietnam Electricity has been asked to set a price bracket, based on a newly issued circular, for renewable energy projects that have failed to meet the deadline for incentivized feed-in-tariff (FiT).

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

EVN responsible for price talks with renewables projects missing FiT deadline: regulators

EVN responsible for price talks with renewables projects missing FiT deadline: regulators

Vietnam Electricity (EVN) is responsible for negotiating prices and outputs with wind and solar power developers that have failed to meet the country’s feed-in-tariff deadline, says the Electricity Regulatory Authority.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

No price talks for renewables projects missing FiT deadline: EVN

No price talks for renewables projects missing FiT deadline: EVN

Vietnam Electricity (EVN) says it can’t negotiate prices with wind and solar power projects that have failed to meet the country’s feed-in-tariff (FiT) deadline of November 1, 2021.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Renewable power projects missing incentive deadline to negotiate purchase prices

Renewable power projects missing incentive deadline to negotiate purchase prices

The Ministry of Industry and Trade has proposed that solar and wind power project investors missing the incentivised feed-in-tariff deadline be allowed to negotiate purchase prices with Vietnam Electricity (EVN).

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Bidding to mature Vietnam renewables development: expert

Bidding to mature Vietnam renewables development: expert

A future bidding mechanism will help Vietnam avoid massive development of renewable energy like now as only the best investors can join the game, says Vietnam Energy Association’s chairman.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Quality, capacity hamper wind farms in Gia Lai

Quality, capacity hamper wind farms in Gia Lai

Five completed wind power projects in Gia Lai cannot start commercial operations due to some quality issues and lower-than-expected electricity transmission capacity in the Central Highland province.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7

Ministry mulls over auctions to replace FiTs for renewables projects

Ministry mulls over auctions to replace FiTs for renewables projects

Wind and solar power projects that miss the commercial operation deadline to enjoy feed-in-tariffs in Vietnam will shift to an auction system, the Ministry of Industry and Trade has proposed.

Energy - Mon, Dec 22, 2021 | 11:30 am GMT+7