Challenges loom in connecting southern Vietnam hub HCMC to mega-airport Long Thanh
The need of establishing optimal connectivity between Ho Chi Minh City and Long Thanh International Airport in the neighboring province of Dong Nai has become increasingly urgent. While rail projects have yet to take shape, road travel from the city's center to the planned mega-airport remains time-consuming.
According to HCMC’s Department of Construction, the city has been working closely with neighbouring localities, particularly Dong Nai, to roll out a series of coordinated measures aimed at accelerating investment in key transport infrastructure projects. These efforts are intended to ensure a modern and efficient connectivity network to support the effective operation of Long Thanh airport, a nationally significant project.
On the road front, six projects are currently being implemented to serve airport connectivity. These include the Ring Road 4 project, spanning 206 km with four lanes, under the authority of HCMC, Dong Nai and Tay Ninh provinces. The project is scheduled to break ground in June 2026 and be completed in 2028.
The Bien Hoa-Vung Tau Expressway, overseen by the Ministry of Construction, HCMC and Dong Nai, is targeted for completion by December 2025. The Ben Luc-Long Thanh Expressway, developed by Vietnam Expressway Corporation (VEC), is expected to be completed by September 2026.
VEC is also the investor in the expansion of the HCMC-Long Thanh Expressway, which is slated for basic completion in 2026, except for the Long Thanh Bridge, scheduled for completion in Q1/2027.
A section of the Ho Chi Minh City-Long Thanh Expressway. Photo by The Investor/Vu Pham.
Another key project is Ring Road 3, jointly managed by HCMC, Dong Nai and Tay Ninh provinces. This year, 30.5 km of the route is expected to be technically opened to traffic, with the remaining 39.5 km scheduled for technical opening by April 30, 2026, and full completion by June 30, 2026.
Meanwhile, the expansion of provincial Road TL25C, under the authority of Dong Nai province, has seen 7.6 km completed, with around 6.4 km currently under construction and targeted for completion in 2025. A further 2.65 km has yet to be implemented due to land clearance issues.
In the rail sector, the municipal construction department said the construction ministry is preparing investment for the North-South high-speed railway, which is expected to start construction by the end of 2026 and be completed by 2035, along with the Bien Hoa-Vung Tau railway.
For its part, HCMC has assigned Becamex Corporation to study investment in a combined freight and passenger railway linking Bau Bang to Cai Mep. The project aims to break ground in 2027 and be completed before 2035, serving industrial development, logistics, and seaports across the region.
For urban rail, three corridors have been identified to connect HCMC with Long Thanh airport.
The first involves Metro Line No. 2 (Ben Thanh-Tham Luong; Ben Thanh-Thu Thiem) linked to the Thu Thiem-Long Thanh line. The Ben Thanh-Tham Luong section is being developed with public investment funds, with construction planned to start before the 14th Party Congress (scheduled for January 19-25, 2026) and completion targeted for 2030.
The Ben Thanh-Thu Thiem section and the Thu Thiem-Long Thanh line are being proposed by Truong Hai Group under a public-private partnership (PPP) model, with construction targeted to begin in 2026 and completion in 2030.
The urban railway connecting Ho Chi Minh City to Long Thanh airport. Illustration by Gemini.
The second corridor centers on Metro Line No. 6, which HCMC plans to develop using public investment, prioritizing an early start on the Tan Son Nhat-Phu Huu section to connect with the Thu Thiem-Long Thanh line. Construction is targeted for 2026, with completion in 2030.
The third corridor would link Metro Line No. 6 with Metro Line No. 1 (Ben Thanh-Suoi Tien), extending Line No. 1 to Dong Nai province’s new administrative center and Long Thanh airport.
Under this plan, HCMC will oversee the development of Metro Line No. 6, while Dong Nai province will be responsible for the extension of Metro Line No. 1. Completion is targeted for 2030.
Three major hurdles
Despite the ambitious plans, the construction department identified several key challenges, including land clearance, mobilizing financial resources, and issues related to technology transfer and the development of a domestic railway industry.
Many of the rail routes pass through densely populated and central areas, posing significant impacts on existing structures such as high-rise buildings and technical infrastructure. For underground metro lines, technical complexity and high investment costs could delay progress if legal procedures and funding mechanisms are not synchronized.
In addition, implementing transit-oriented development (TOD) in HCMC will require close coordination among urban management, transport and financial authorities, as well as investors, to ensure integrated development of urban areas along metro corridors while improving public transport usage.
As this is a relatively new model, the city lacks extensive implementation experience and must both pilot projects and draw on international best practices.
The urban railway line No. 1 (Ben Thanh-Suoi Tien). Photo by The Investor/Pham Nguyen.
To accelerate progress, HCMC is focusing on several key measures.
First, it plans to maximize the use of special mechanisms provided under the parliament Resolution 188 on piloting special mechanisms for developing urban railway systems (metro) in Hanoi and HCMC and the Railway Law to shorten investment preparation and project implementation procedures.
Second, the city will review and adjust urban development planning around metro stations and depots in line with TOD principles, particularly for Metro Line No. 1 (Ben Thanh-Suoi Tien) and Metro Line No. 2 (Ben Thanh-Tham Luong). It also aims to complete a capital mobilization plan for the urban rail network.
Third, the city will issue plans and roadmaps for developing the railway industry, alongside training programs to build the necessary human resources.
Fourth, authorities will review land funds and submit to the city council a list of land parcels to be used as counterpart funding for railway projects developed under PPP arrangements using build-transfer (BT) contracts.
Finally, HCMC will develop resettlement plans aligned with investment schedules to support land clearance for railway projects.
“With these solutions, Ho Chi Minh City believes it can significantly shorten implementation timelines, ensure progress and quality, and establish a modern public transport system that is effectively connected with the city and neighboring regions, meeting the growing travel demand of residents,” the construction department said.
- Read More
UOB Vietnam appoints Pham Hong Hai as deputy country CEO
Singapore's United Overseas Bank (Vietnam) Limited on Monday appointed Pham Hong Hai, former CEO of HSBC Vietnam and later Vietnamese bank OCB, as deputy country CEO, effective immediately.
Banking - Mon, June 15, 2026 | 2:26 pm GMT+7
Shinhan Bank Vietnam launches AI translation desk, strengthening customer experience, digital innovation
Shinhan Bank Vietnam has officially launched AI Translation Desk, an AI-powered interpretation solution designed to help foreign customers communicate more easily while using banking services in Vietnam.
Banking - Mon, June 15, 2026 | 12:03 pm GMT+7
FDI listings a missing piece in Vietnam's stock market development
As Vietnam's stock market moves closer to its long-awaited upgrade to secondary emerging market status and seeks to attract higher-quality capital, allowing more foreign-invested companies to list on domestic exchanges could broaden the pool of investable assets and support the next phase of capital market development.
Finance - Mon, June 15, 2026 | 11:14 am GMT+7
Chinese robot 'eyes' manufacturer builds 10-hectare factory in northern Vietnam
Orbbec Inc., a Chinese company specializing in 3D vision sensors and robotic hardware, is building an over-10-hectare manufacturing center in the northern province of Bac Ninh to serve international markets.
Industries - Mon, June 15, 2026 | 8:00 am GMT+7
Long Thanh airport project faces shortage of 2,000 workers
The Long Thanh International Airport project in the southern province of Dong Nai is still short nearly 2,000 workers compared to actual requirements during its final acceleration phase.
Infrastructure - Sun, June 14, 2026 | 6:08 pm GMT+7
Nghi Son Refinery and Petrochemical Complex turns profitable in Q1 on full-capacity operations
Operating at full capacity, the Nghi Son Refinery and Petrochemical Complex in Vietnam's central province of Thanh Hoa reported its first profit in Q1/2026, marking a significant turnaround after years of losses.
Economy - Sun, June 14, 2026 | 2:45 pm GMT+7
50 years of Gamuda Berhad and its urban development journey in Vietnam
Celebrating 50 years of establishment and growth, Gamuda Berhad – one of Malaysia’s leading infrastructure and urban development groups – has evolved from an infrastructure specialist into an integrated urban developer with a growing presence across Asia.
Real Estate - Sun, June 14, 2026 | 11:21 am GMT+7
Industrials, technology top Vietnamese sectors in M&A transaction volume
Vietnam’s M&A market recorded 24 transactions in May, with industrials, technology and healthcare sectors being the most active sectors in terms of transaction volume, writes Grant Thornton analysts.
Consulting - Sun, June 14, 2026 | 9:00 am GMT+7
Top Vietnamese garment maker Vinatex's H1 profit rises 14%, weak order visibility clouds outlook
Vietnam National Textile and Garment Group (UPCoM: VGT) reported consolidated profit growth of 14.4% in the first half of 2026, driven by a strong recovery in its yarn business, even as weakening global demand and uncertainty over U.S. trade policy cast a shadow over the sector’s outlook.
Companies - Sun, June 14, 2026 | 8:00 am GMT+7
Gamuda Land Vietnam recognized among Top 10 Enterprises Pioneering Green Transformation 2025-2026
Gamuda Land Vietnam has been recognized as one of the “Top 10 Enterprises Pioneering Green Transformation 2025-2026” at the 25th Golden Dragon Awards.
Companies - Sat, June 13, 2026 | 7:45 pm GMT+7
T&T pushes ahead with $97 mln industrial park project, eyes new urban area projects in northern Vietnam
Vietnamese conglomerate T&T Group is seeking to accelerate five projects in Bac Ninh while proposing two new developments in this northern province.
Infrastructure - Sat, June 13, 2026 | 7:09 pm GMT+7
VinFast guns for 300,000 EV deliveries in 2026, spins off manufacturing operations
VinFast, the EV arm of Vietnamese conglomerate Vingroup (HoSE: VIC) targets at least 300,000 electric vehicle deliveries globally this year, up 52% year-on-year, while pursuing a restructuring plan aimed at improving capital efficiency, according to a report by Vietcap Securities.
Companies - Sat, June 13, 2026 | 3:07 pm GMT+7
Vietnam economy resilience amid cost pressures, external strains: UOB
The VND has stabilized in recent weeks, trading in a range of VND26,291-26,372 per U.S. dollars in April-May, well within the State Bank of Vietnam’s ±5% band. In a report released on Friday, UOB analysts say on balance, they retain a gradual depreciation bias for the USD/VND, with updated forecasts of 26,500 in Q3/2026, 26,400 in Q4/2026, 26,300 in Q1/2027, and 26,100 in Q2/2027.
Consulting - Sat, June 13, 2026 | 11:49 am GMT+7
Vietnam Politburo issues resolution on FDI sector development
The Politburo, Vietnam's highest decision-making body, has issued a resolution that establishes a new mindset in developing the FDI sector.
Economy - Sat, June 13, 2026 | 8:17 am GMT+7
Japan’s Meiko breaks ground on $500 mln electronic circuit plant in northern Vietnam
Japanese electronics manufacturer Meiko Group on Friday broke ground on a $500 million electronic circuit plant in northern Vietnam, underscoring the country’s growing role in global technology supply chains and advanced manufacturing.
Investing - Fri, June 12, 2026 | 4:06 pm GMT+7
Vietnam's EVN discusses energy investment opportunities with Thailand's Gulf Energy
Vietnam Electricity (EVN) chairman Dang Hoang An met executives from Thailand's Gulf Energy in Hanoi on Wednesday to discuss the company's investment plans and the development of energy projects in Vietnam.
Energy - Fri, June 12, 2026 | 3:59 pm GMT+7