Dau Giay-Phan Thiet expressway must be completed by April 30: minister
Newly-appointed Minister of Transport Nguyen Van Thang has asked the investor of the Dau Giay-Phan Thiet Expressway linking Dong Nai and Binh Thuan provinces to complete the project by April 30, or be penalized.
"The report of the project management unit (PMU) is very good but the real situation is not good at all. The project has been delayed once. If you do not complete it by April 30 (Reunification Day) next year, please write a resignation application," the minister told leaders of the Thang Long PMU - the investor of the expressway during his field trip to the construction site on Tuesday.
Construction of the Dau Giay-Phan Thiet Expressway. Photo courtesy of Youth newspaper
The 99-kilometer expressway, part of the North-South Expressway, has a surface of more than 32 meters with six lanes. It is projected to be built at a total investment exceeding VND12.5 trillion ($503 million).
Once completed, the travel time from the southern metropolis of Ho Chi Minh City to the central tourist hub of Phan Thiet-Mui Ne will be halved to 2-2.5 hours.
The project started in September 2020, and is expected to be completed by the end of this year. However, the construction progress has been very slow, with road foundations yet to be laid in many sections.
Minister Thang frankly pointed out that besides objective reasons like weather, lack of filling land and high material prices, the management unit must bear the main responsibility for this situation, calling Thang Long PMU incompetent and irresponsible.
"I don't need promises anymore. Any contractors that cannot meet the schedule and quality in this phase will not be allowed to do other works of the ministry in the near future. So are the supervision consultants," he said.
To ensure the expressway will be finished by April 30, the minister required all contractors to maximize human resources, machines and materials to speed up progress.
"The project management unit must report the progress of each day and each hour to the deputy minister in charge and will bear responsibility for any delay", Thang noted.
Later the same day, the transport minister inspected the construction site of the Vinh Hao-Phan Thiet Expressway project invested by PMU 7. The 100-kilometer expressway will have a total investment of nearly VND11 trillion ($442.7 million).
At the site, Thang said that the project has just completed 49% of its workload after two years, and that the investor and contractors must take the main responsibility for the delay.
He requested the investor to make regular contact with contractors to promptly solve difficulties during the implementation process as well as mobilize all possible human resources, machines and equipment for round-the-clock construction.
“Contractor first-phase performance is one of the criteria for the ministry to select them to complete the second,” he noted.
Earlier on November 17, during his trip to inspect the construction of the North-South Expressway’s section running through the north-central province of Thanh Hoa, Minister Thang ordered the contract with Hoang Long to be cancelled for failing to ensure the construction progress of the three-kilometer Mai Son-National Highway 45 section of the Ninh Binh-Thanh Hoa Expressway.
Thang, 49, was endorsed by the National Assembly to be Minister of Transport for the 2021-2026 term on October 21, replacing Nguyen Van The who resigned.
- Read More
Vietnam mulls opening door for private investment in small modular reactors
Vietnam’s Ministry of Industry and Trade has drafted a parliamentary resolution that, for the first time, would allow private companies to participate in the development of small modular nuclear reactors (SMRs).
Energy - Fri, October 17, 2025 | 4:37 pm GMT+7
Kido seeks buyer for remaining 49% stake in frozen food affiliate
Kido Group (HoSE: KDC), a leading food company in Vietnam, has approved a plan to divest the firm's remaining 49% stake in its affiliate Kido Frozen Food JSC (Kido Foods).
Companies - Fri, October 17, 2025 | 4:25 pm GMT+7
Le Ngoc Quang appointed Danang city's Party chief
Le Ngoc Quang, a Party Central Committee member and Party chief of Quang Tri province, has been appointed Party chief of Danang for the 2025-2030 term - the highest position in the city, central Vietnam's economic hub.
Politics - Fri, October 17, 2025 | 4:17 pm GMT+7
T&T Group seeks to reshape north-central Vietnam’s urban landscape with major projects
Multi-sector conglomerate T&T Group is developing a model eco-urban complex in Ha Tinh province and plans to build a massive 236-hectare urban area in neighboring Nghe An, with an aim to reshape north-central Vietnam's urban landscape.
Investing - Fri, October 17, 2025 | 2:44 pm GMT+7
Toyota plans $359 mln plant expansion in northern Vietnam
Toyota Motor Vietnam (TMV) plans to invest about VND9.46 trillion ($359.2 million) in the first phase of its plant expansion project in Phu Tho province.
Investing - Fri, October 17, 2025 | 2:09 pm GMT+7
PVI Insurance sees 9-month profit before tax more than doubling
PVI Insurance has reaffirmed its position as the No. 1 non-life insurer in Vietnam, with total revenue increasing nearly 1.4 times in the first nine months of 2025 and pre-tax profit more than doubling year-on-year - surpassing its full-year targets for both revenue and profit.
Companies - Fri, October 17, 2025 | 9:08 am GMT+7
Vingroup to develop 4,600ha coastal urban project in northern Vietnam
A consortium of Vingroup (HoSE: VIC) and its real estate arm Vinhomes (HoSE: VHM) will develop a 4,600-hectare coastal urban complex in Ha An ward, Quang Ninh province, following local authorities’ approval of a zoning plan.
Real Estate - Fri, October 17, 2025 | 8:30 am GMT+7
Indonesia resumes int’l carbon trading after 4-year hiatus
Indonesian President Prabowo Subianto has issued a new decree to restart international carbon emissions trading after a four-year hiatus.
Southeast Asia - Thu, October 16, 2025 | 9:23 pm GMT+7
Investors seek 2-year delay for $2.56 bln LNG power project in northern Vietnam, citing equipment hurdles
Investors of a $2.56 billion LNG-fired power plant in Hung Yen province have proposed delaying the project’s commercial operation schedule by two years due to difficulties securing key equipment.
Energy - Thu, October 16, 2025 | 9:04 pm GMT+7
Vietnam to soon raise taxpayers' personal deduction: official
The personal income tax deduction in Vietnam is "very likely" to increase to VND21.7 million ($823,940) per month, including VND15.5 million (588,530) for the taxpayer and VND6.2 million ($235,410) for each dependent.
Finance - Thu, October 16, 2025 | 6:25 pm GMT+7
Business confidence climbs as reforms gain traction amid global headwinds: EuroCham Vietnam
The index climbed to 66.5, surpassing pre-tariffs level and reaching its highest in three years – showcasing resilience and adaptability amid global headwinds and evolving U.S. tariff pressures.
Economy - Thu, October 16, 2025 | 4:36 pm GMT+7
Vietnam's stock market watchdog suspends two Grant Thornton auditors
Vietnam's State Securities Commission (SSC) has suspended two auditors from Grant Thornton Vietnam after determining that the 2024 audited financial statements of Saigon Water Infrastructure Corporation (HoSE: SII) failed to meet required standards.
Finance - Thu, October 16, 2025 | 3:35 pm GMT+7
Law No. 56 a major policy breakthrough for Vietnam's stock market development
The Law No. 56, effective January 1, 2025, is one of the major legal breakthroughs in recent years that will enhance the transparency and operational efficiency of the Vietnamese stock market.
Finance - Thu, October 16, 2025 | 2:30 pm GMT+7
WHA Group breaks ground on smart technology industrial zone in central Vietnam
Thailand's WHA Group on Tuesday broke ground on a world-class, modern, and environmentally friendly industrial zone in central Vietnam, namely the WHA Smart Technology Industrial Zone-Thanh Hoa.
Real Estate - Thu, October 16, 2025 | 2:00 pm GMT+7
Vietnam a key partner in Murphy Oil’s global strategy: exec
Vietnam remains a key partner in Murphy Oil’s global business strategy, said Eric Hambly, the U.S. corporation's president and CEO.
Companies - Thu, October 16, 2025 | 12:06 pm GMT+7
VNPT, Qualcomm debut Vietnam’s 1st original design-based excellence center
State-owned Vietnam Posts and Telecommunications Group (VNPT) and Qualcomm have officially launched the VNPT-Qualcomm Excellence Center (VQEC), the first facility in the country to operate under an original design co-development model using Qualcomm’s core technologies.
Companies - Thu, October 16, 2025 | 8:41 am GMT+7