$4 bln LNG-to-power Mekong Delta project targets 2029 completion
Project investor Delta Offshore Energy (DOE) plans to complete work on the $4 billion LNG-to-power plant in the Mekong Delta province of Bac Lieu in 2029.
An illustration of Bac Lieu LNG-to-power plant project in Bac Lieu province, Vietnam's Mekong Delta. Photo courtesy of the investor Delta Offshore Energy (DOE).
At a Wednesday meeting with Bac Lieu authorities, a DOE representative elaborated they aim to put the first 800-MW turbine into operation in June 2028.
The representative asked the province to support and fix hurdles that the mega project was facing, stressings problems related to power purchase agreement, currency exchange, government guarantee for capital arrangement and other issues.
Bac Lieu Chairman Pham Van Thieu responded that the province was willing to tackle problems within its jurisdiction and asked the firm to contact ministries, central agencies and the Prime Minister to fix issues beyond the province’s reach.
DOE, which has its head office in Hanoi and a branch office in the U.S., received its investment registration certificate in 2020. It set up a Vietnamese enterprise for project implementation in Q2/2021. The project secured environmental impact assessment approval in Q3/2021 and a feasibility study appraisal in Q4/2021.
The 3,200 MW project is slated for completion in December 2027, according to the investment registration certificate, but its progress has been sluggish.
Bac Lieu Chairman Pham Van Thieu speaks at a working session with executives of Delta Offshore Energy in the Mekong Delta province, July 12, 2023. Photo courtesy of Bac Lieu newspaper.
The project, set to begin construction in the second quarter of 2022, is entangled in procedural bottlenecks.
Without a signed power purchase agreement (PPA), the investor cannot negotiate with financial institutions to make capital arrangements, the company says.
Previously, Bac Lieu authorities had acknowledged that foreign currency conversion, government guarantee for EVN payment obligations and issues of compensation in case the PPA is terminated were hurdles for the giant project.
In May, DOE said it aims to reach a PPA with state utility Vietnam Electricity (EVN) in the last quarter of this year so that the project can break ground in 2024.
In May, Prime Minister Pham Minh Chinh issued Decision No. 500/QD-TTg, approving the much-awaited national Power Development Plan for 2021-2030 with vision to 2050 (PDP VIII). PDP VIII prioritizes maximizing the use of domestic gas for power generation. In case domestic gas production decreases, natural gas or LNG will be imported.
PDP VIII limits the development of power sources using LNG if there is an alternative to reducing dependence on imported fuels. By 2050, plants using LNG will gradually switch to hydrogen, the plan envisages.
The list of LNG projects of importance and priority for development until 2035 are prescribed under Table 1 of Appendix II: Quang Ninh (1,500 MW); Thai Binh (1,500 MW); Nghi Son (1,500 MW); Quang Trach II (1,500 MW); Quynh Lap/Nghi Son (1,500 MW); Hai Lang Phase 1 (1,500 MW); Ca Na (1,500 MW); Long Son (1,500 MW); Hiep Phuoc Phase 1 (1,200 MW); Long An I (1,500 MW); Long An II (1,500 MW); and Bac Lieu (3,200 MW).
In related news, Vietnam's first cargo of liquefied natural gas (LNG) was pumped into the Thi Vai LNG Terminal last Monday, marking a milestone in the country’s clean energy transition. Global oil giant Shell provided the first shipment and LNG carrier Maran Gas Achilles pumped it into the terminal located in the southern province of Ba Ria-Vung Tau. This first batch - almost 70,000 tons - will serve the LNG terminal’s test run before commercial operations begin.
- Read More
Vietnam, Finland firms sign multiple MoUs on satellite, cybersecurity, aviation partnerships
A series of cooperation agreements were signed between Vietnam and Finland on Tuesday, within the framework of Party chief To Lam's official visit to Helsinki, while bilateral relationship was lifted to a "strategic partnership".
Economy - Wed, October 22, 2025 | 12:43 pm GMT+7
Trung Nam Ca Na seeks to convert agri-forest land for $147 mln industrial park in central Vietnam
Industrial park developer Trung Nam Ca Na is seeking approval to convert about 170 hectares of agricultural and forest land for the construction of a VND3,875 billion ($147 million) project in Vietnam’s central coastal province of Khanh Hoa.
Industrial real estate - Wed, October 22, 2025 | 10:54 am GMT+7
PV Power's arm posts 5-fold jump in Q3 profit on margin recovery
PetroVietnam Power Nhon Trach 2 JSC (HoSE: NT2) reported a sharp rebound in third-quarter earnings as improved margins and higher revenue lifted profits nearly fivefold from a year earlier.
Companies - Wed, October 22, 2025 | 8:37 am GMT+7
TCBS overtakes SSI to become Vietnam’s largest securities company by market cap
Over 2.3 billion shares of Techcom Securities JSC (TCBS) debuted on the Ho Chi Minh City Stock Exchange (HoSE) on Tuesday. The stock, TCX, recorded the highest price and the largest market capitalization in the Vietnamese securities sector.
Finance - Tue, October 21, 2025 | 10:27 pm GMT+7
Indonesia’s palm oil industry becomes investment magnet
Indonesia’s palm oil sector attracted IDR52.7 trillion, or approximately $3.2 billion, in investment during the first nine months of this year, with the money going into enabling the country to capture more value out of its top commodity, the country’s Ministry of Investment reported.
Southeast Asia - Tue, October 21, 2025 | 9:34 pm GMT+7
Indonesia reports strong job, investment growth
The Indonesian Coordinating Ministry for Economic Affairs reported strong job and investment growth during the first year of President Prabowo Subianto’s administration, compared with the first year under his predecessor.
Southeast Asia - Tue, October 21, 2025 | 9:29 pm GMT+7
Singapore grants conditional approval for 1GW low-carbon power import from Malaysia
Singapore has granted conditional approval to import 1 GW of low-carbon electricity from the Malaysian state of Sarawak, marking a new phase in the energy partnership between the two countries.
Southeast Asia - Tue, October 21, 2025 | 9:26 pm GMT+7
Margin lending in Vietnam’s stock market hits record, but not worrisome
Despite margin debt in Vietnam’s stock market surging sharply, experts believe that current margin pressure is not yet a major concern as top securities firms have significantly strengthened their capital buffers.
Finance - Tue, October 21, 2025 | 4:23 pm GMT+7
Lenders in Vietnam now in low-rate lending race: ACB exec
The biggest “headache” for banks in Vietnam now is that profit margins are getting thinner, said CEO of Asia Commercial Bank (ACB) Tu Tien Phat.
Banking & Finance - Tue, October 21, 2025 | 4:00 pm GMT+7
PV Gas - 35 years of innovation and technological leadership in Vietnam’s gas industry
Over the past 35 years of establishment and development (1990-2025), PV Gas, a subsidiary of state-owned giant Petrovietnam, has affirmed its pioneering position in Vietnam’s gas industry, marked by a series of groundbreaking achievements in science and technology.
Companies - Tue, October 21, 2025 | 3:45 pm GMT+7
Vietnam's consumer finance major F88 achieves 90% of year's profit target after 9 months
F88 Investment JSC (F88), a leading consumer finance company in Vietnam, reported a cumulative pre-tax profit of VND603 billion ($22.88 million) in the first nine months of 2025, a 2.5-fold increase year-on-year, reaching 90% of its full-year target of VND673 billion.
Companies - Tue, October 21, 2025 | 3:15 pm GMT+7
Vietnam corporate earnings to be driven by credit expansion, trading activity, property recovery
With Q3 earnings season underway, results are expected to come in broadly in line with expectations. Financials should remain the largest contributors, benefiting from credit expansion and trading activity, while real estate continues to recover as project launches and sales rates improve, writes Tung Dang, associate director at Dragon Capital.
Economy - Tue, October 21, 2025 | 2:33 pm GMT+7
Inland port opens in southern Vietnam province Tay Ninh, set to become border logistics hub
The 16.5-hectare Tan Cang-Moc Bai inland port in Tay Ninh province, southern Vietnam has been opened, offering logistics services and handling customs clearance for imports and exports.
Infrastructure - Tue, October 21, 2025 | 12:03 pm GMT+7
State-managed property trading centers will help curb speculation, price manipulation: expert
Establishment of state-managed real estate trading centers is expected to create a transparent transaction channel, helping control and limit speculation and price manipulation in the Vietnamese market.
Real Estate - Tue, October 21, 2025 | 8:37 am GMT+7
Vietnam's benchmark VN-Index records sharpest drop in 25-year history
VN-Index, which represents the Ho Chi Minh Stock Exchange (HoSE), saw the sharpest decline in its 25-year history on Monday, down by 94.76 points, or 5.47%, to 1,636.43.
Finance - Mon, October 20, 2025 | 5:49 pm GMT+7
Construction contractor Coteccons sets record FY2026 targets, capital base hike via share issue
Coteccons Construction JSC (HoSE: CTD), one of Vietnam’s largest construction contractors, has set ambitious targets for its fiscal year 2026, driven by a record order backlog and its push into international markets.
Companies - Mon, October 20, 2025 | 4:50 pm GMT+7