‘Environmental city' Danang struggles to untangle waste treatment plants from red tape

By Nguyen Tri, Minh Hue
Mon, November 6, 2023 | 5:44 pm GMT+7

Danang, dubbed central Vietnam's “environmental city”, has two waste-to-energy plants stagnating on paper because of procedural tangles.

The municipal Department of Planning and Investment recently granted an adjusted investment registration certificate to Vietnam Environment Joint Stock Company to invest in the Khanh Son-Danang waste-to-energy plant at the Khanh Son landfill in Hoa Khanh Nam ward, Lien Chieu district.

The plant will have a designed capacity of burning 650 tons of domestic solid waste per day; classify and burn 350 tonnes of common industrial waste per day; and produce 7,068 liters of finished petroleum oil (PO) per day or 11.78 liters of PO per ton of waste.

Khanh Son dump in Hoa Khanh Nam ward, Lien Chieu district, Danang city, central Vietnam. Photo by The Investor/Thanh Van.

Khanh Son dump in Hoa Khanh Nam ward, Lien Chieu district, Danang city, central Vietnam. Photo by The Investor/Thanh Van.

The plant will also produce 900 kilograms of finished recycled oil (RO) per day (1.5 kilograms per ton of waste). The project will include a hazardous waste storage and treatment facility with a capacity of 5,000 kilograms per hour.

The VND2.02 trillion ($87.78 million) project is expected to be put into operation in the third quarter of 2026.

At a recent press conference on the city’s socio-economic situation in Q3/2023, Vo Nguyen Chuong, deputy director of the municipal Department of Natural Resources and Environment, said the project will treat domestic solid waste with incineration technology from Germany.

Currently, Vietnam Environment JSC is implementing necessary procedures for the project to kick off on schedule.

The second project, also in the Khanh Son area, will be a public-private partnership (PPP) investment. Covering more than 29,000 square meters, the plant with an incineration capacity of 1,000 tons per day, will be built at a total cost of over VND823 billion ($33.73 million).

Danang authorities have selected the EcoPark Joint Venture – formed by TDH Ecoland Urban Development and Investment JSC, Huy Hoang Development Production and Import-Export JSC, and Huy Hoang Eco Environment JSC – as the project investor.

The planning department has informed the municipal People's Committee that the appraisal council has studied the project's feasibility study report and asked for some amendments and supplements.

Chuong said Danang will take the next steps in line with regulations. In case the PPP arrangement does not work out, the city will call for investment under other permitted modes to ensure that it continues to follow the approved waste treatment roadmap, he added.

Landfills not a priority

Le Cong Hung, a representative of TDH Ecoland, said that the joint venture has completed a feasibility study for the waste treatment plant and submitted related documents to the Ministry of Construction to get a license.

However, he noted that many localities were facing problems investing in waste treatment plants in the PPP form because of waste supply contracts, he said.

"Despite winning the bid, we cannot have the investment policy approved since approval requires a waste supply contract. Since the plant is yet to be built, we can’t sign a waste supply contract and set prices," Hung said.

He added that the project was facing difficulties with regulations on the “safe distance” mandated the Ministry of Natural Resources and Environment which requires a waste treatment plant to be at least 500 meters away from residents’ houses. However, more than 300 households live close to the site of both proposed plants.

Chuong with the municipal Department of Natural Resources and Environment said that city leaders have directed relevant units to ensure an environmentally safe distance from the Khanh Son solid waste treatment complex in line with regulations.

The municipal People's Committee has asked relevant departments and agencies to implement site clearance and compensation plans to create an environmentally safe distance.

Within the environmentally safe distance area, the city will call for investment in projects less affected by environmental factors like power stations, waste transfer stations, warehouses and logistics centers.

Le Quang Nam, Vice Chairman of the Danang People's Committee, said the Khanh Son solid waste treatment complex, covering an area of over 50 hectares, will also treat domestic, hazardous and medical waste, as well as recycle waste from construction materials.

"The city will choose appropriate technology, ensuring environmental protection with the most stringent standards," Nam asserted.

He said Danang has identified waste treatment as a vital issue and considers waste a resource. Therefore, the city will not prioritize landfills, he stressed.

Comments (0)
  • Read More
Vietnam parliament vice chairman assigned to run the legislative body

Vietnam parliament vice chairman assigned to run the legislative body

The National Assembly's standing Vice Chairman Tran Thanh Man has been assigned to run the country's highest legislative body after Chairman Vuong Dinh Hue was dismissed from the position.

Politics - Thu, May 2, 2024 | 7:37 pm GMT+7

Vietnam investment environment favorable for strategic M&A opportunities: KPMG

Vietnam investment environment favorable for strategic M&A opportunities: KPMG

With inflation under control, projected growth of 5.8% and public debt kept manageable this year, Vietnam’s investment environment offers strategic opportunities, especially in M&A, says audit and consulting firm KPMG.

Economy - Thu, May 2, 2024 | 4:59 pm GMT+7

PV Gas sees Q1 net profit go down 26% to $99 mln

PV Gas sees Q1 net profit go down 26% to $99 mln

PV Gas, Vietnam’s largest dry gas and LPG supplier, earned consolidated net profits of VND2,511.66 billion ($98.96 million) in Q1/2024, down 26.5% year-on-year.

Companies - Thu, May 2, 2024 | 3:38 pm GMT+7

Key infrastructure projects face site clearance issues, material shortages

Key infrastructure projects face site clearance issues, material shortages

Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.

Infrastructure - Thu, May 2, 2024 | 3:35 pm GMT+7

Ba Ria-Vung Tau province health department head in trouble for bidding rules violations

Ba Ria-Vung Tau province health department head in trouble for bidding rules violations

Legal proceedings have been initiated against Pham Minh An, director of Ba Ria-Vung Tau province's Department of Health for alleged bidding regulation violations related to equipment supply for a hospital.

Society - Thu, May 2, 2024 | 3:21 pm GMT+7

USD weakens slightly against VND after Fed holds rates steady

USD weakens slightly against VND after Fed holds rates steady

The U.S. dollar slid against the Vietnamese dong (VND) on Thursday morning hours after the U.S. Federal Reserve (Fed) kept its policy rate unchanged in the 5.25-5.50% range.

Banking - Thu, May 2, 2024 | 11:37 am GMT+7

PV Gas takes delivery of third LNG batch to meet rising power demand

PV Gas takes delivery of third LNG batch to meet rising power demand

PV Gas, the gas production arm of state-owned Petrovietnam, has taken delivery of its third batch of liquefied natural gas (LNG) to meet demand for power generation as the country battles to cope with a prolonged heat wave.

Energy - Thu, May 2, 2024 | 10:52 am GMT+7

Vietnam factory activity returns to growth on new orders: S&P

Vietnam factory activity returns to growth on new orders: S&P

The Vietnamese manufacturing sector returned to growth in April as a solid expansion of new orders fed through to a renewed increase in production, according to S&P Global.

Economy - Thu, May 2, 2024 | 9:25 am GMT+7

HCMC well off target of 8 metro lines by 2035

HCMC well off target of 8 metro lines by 2035

Vietnam’s southern economic hub Ho Chi Minh City seems to be falling well short of its goal of building eight metro lines totaling 200 kilometers by 2035 because none have been put into operation thus far.

Infrastructure - Thu, May 2, 2024 | 9:14 am GMT+7

Vietnam property market past most difficult period: expert

Vietnam property market past most difficult period: expert

The Vietnamese real estate market has gone through its most difficult period, and businesses or investors that have survived have done so through strong experience and resources, said Nguyen Van Dinh, chairman of the Vietnam Association of Realtors (VARS).

Real Estate - Thu, May 2, 2024 | 8:17 am GMT+7

Seven must-visit places in Dien Bien province

Seven must-visit places in Dien Bien province

The northwestern mountainous province of Dien Bien has many charming places to visit, in addition to historical relic sites related to the Dien Bien Phu Campaign.

Travel - Wed, May 1, 2024 | 10:42 pm GMT+7

Vietnam's economy: positive changes but concerns persist

Vietnam's economy: positive changes but concerns persist

Vietnam's economic picture is looking more positive with numerous bright spots, but many difficulties remain, especially market confidence, concerns about private investment, and social consumption, writes Dr. Vo Tri Thanh, director of the Institute for Brand and Competitiveness Strategy.

Opinion - Wed, May 1, 2024 | 6:32 pm GMT+7

Major industrial park developer Kinh Bac suffers setback with $3 mln Q1 loss

Major industrial park developer Kinh Bac suffers setback with $3 mln Q1 loss

Vietnamese industrial park developer Kinh Bac Urban Development Corporation recorded Q1/2024 losses of VND76.7 billion ($3 million), a setback considering its annual profit target of VND4,000 billion ($157.8 million).

Industrial real estate - Wed, May 1, 2024 | 3:51 pm GMT+7

Founder of Vietnam’s ACB bank passes away

Founder of Vietnam’s ACB bank passes away

Asia Commercial Bank founder Tran Mong Hung, father of the current chairman Tran Hung Huy, passed away Thursday. He was 72.

Banking - Wed, May 1, 2024 | 3:37 pm GMT+7

Singapore Management University opens office in HCMC

Singapore Management University opens office in HCMC

Singapore Management University (SMU) has chosen to open a representative office in Vietnam after Indonesia and Thailand as part of its vision to 2025.

Companies - Wed, May 1, 2024 | 3:18 pm GMT+7

Exhibition displays 300 artefacts of Dien Bien Phu Campaign

Exhibition displays 300 artefacts of Dien Bien Phu Campaign

The thematic exhibition named "Dien Bien Phu Victory - An Eternal Epic" showcases some documentaries and artefacts for the first time to the public about Dien Bien Phu Campaign.

Travel - Wed, May 1, 2024 | 3:02 pm GMT+7