EVNNPT strives to complete 220kV Vung Ang substation project and connection in July

By Nguyen Huong, Chau Anh
Mon, July 7, 2025 | 5:02 pm GMT+7

All available resources should be maximized to complete the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam within July, said Pham Le Phu, general director of state utility Vietnam Electricity's (EVN) National Power Transmission Corporation (EVNNPT) - the project investor.

Phu made the request last Thursday during a field trip to the project, whose construction is being accelerated under an emulation movement jointly launched by the Vietnam General Confederation of Labor (VGCL) and EVN.

Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.

Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.

The Central Power Projects Management Board (CPMB) acts on behalf of the investor to oversee and operate the project.

The joint venture between EVN International JSC and Energy JSC provides supervision consultancy services, while industrial engineering company Lilama serves as the main contractor.

The substation is located in Vung Ang ward, Ha Tinh province, with the grid connection line running through Vung Ang and Song Tri wards.

The substation is designed with three voltage levels - 220kV, 110kV, and 22kV. By 2030, it will be equipped with two 220/110/22kV transformers, each with a capacity of 250MVA. A third transformer of the same capacity is planned for installation after 2030 as a backup.

In the current phase, one transformer is being installed. The grid connection line spans a total length of 2 × 13.4 kilometers.

The construction has been basically completed, with only final tasks remaining, such as site finishing and asphalt paving inside and outside the station.

Electrical installation has been completed, including the connection of primary and secondary equipment and the transformer. Most of the commissioning work has been finalized, and the project team is currently reviewing and addressing remaining issues.

The 220kV grid connection line has been the most challenging project component in recent months, primarily due to obstacles in land clearance and compensation.

However, thanks to the strong involvement of local authorities, the province has so far handed over 45 out of 45 tower locations and 21 out of 25 right-of-way span anchor points along the transmission line corridor.

As for construction progress, 41 out of the 45 tower foundations have been erected, with work ongoing at the remaining four locations. The project has completed stringing for 15 out of 25 anchor spans and is currently working on three more.

At the field inspection, Phu emphasized that this is a critically important project to ensure power supply for Ha Tinh province and the region during this year’s peak summer demand.

Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.

Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.

For this reason, the VGCL and EVN have included the project in EVN’s list of urgent key works to be put into operation in 2025. EVNNPT and its trade union have launched an emulation campaign to accelerate construction and complete the project as early as possible.

Phu lauded the efforts of CPMB and the contractors involved, noting their strong commitment to delivering a substantial volume of work.

He also pointed out that some right-of-way clearance issues remain unresolved. Therefore, he called on CPMB to maintain close coordination with contractors and local authorities to conduct public outreach, helping residents better understand the project's importance and encouraging their support in handing over the remaining land.

Although the remaining workload is not extensive, it still requires the active engagement of the entire political system, Phu said.

He requested all units to maintain a high level of focus and closely coordinate with local authorities and communities to conduct outreach and address obstacles related to right-of-way clearance.

The July completion would be a meaningful achievement to mark the 4th EVN Party Congress for the 2025-2030 term and the 96th anniversary of the Vietnam Trade Union (July 28, 1929), he noted.

The units were also required to mobilize both manpower and equipment to simultaneously carry out foundation casting and tower erection across all remaining locations to ensure progress stays on schedule.

During construction, special attention must be paid to safety, with occupational safety for both workers and equipment placed as the top priority, Phu said.

As part of the working program, Phu held a meeting with the Party Committees and People’s Committees of Song Tri and Vung Ang wards to discuss solutions to site clearance obstacles at the remaining four anchor spans along the transmission line corridor.

He emphasized the project's urgency and strategic importance, saying once compensation for affected households is calculated accurately and fairly, if any households still deliberately refuse to cooperate, Song Tri and Vung Ang authorities should implement measures to ensure site access.

In response, Song Tri and Vung Ang leaders affirmed their clear understanding of the project's importance and pledged to take strong, proactive measures to promptly resolve outstanding issues, completing the project within this month.

Comments (0)
  • Read More
Vietnam mulls opening door for private investment in small modular reactors

Vietnam mulls opening door for private investment in small modular reactors

Vietnam’s Ministry of Industry and Trade has drafted a parliamentary resolution that, for the first time, would allow private companies to participate in the development of small modular nuclear reactors (SMRs).

Energy - Fri, October 17, 2025 | 4:37 pm GMT+7

Kido seeks buyer for remaining 49% stake in frozen food affiliate

Kido seeks buyer for remaining 49% stake in frozen food affiliate

Kido Group (HoSE: KDC), a leading food company in Vietnam, has approved a plan to divest the firm's remaining 49% stake in its affiliate Kido Frozen Food JSC (Kido Foods).

Companies - Fri, October 17, 2025 | 4:25 pm GMT+7

Le Ngoc Quang appointed Danang city's Party chief

Le Ngoc Quang appointed Danang city's Party chief

Le Ngoc Quang, a Party Central Committee member and Party chief of Quang Tri province, has been appointed Party chief of Danang for the 2025-2030 term - the highest position in the city, central Vietnam's economic hub.

Politics - Fri, October 17, 2025 | 4:17 pm GMT+7

T&T Group seeks to reshape north-central Vietnam’s urban landscape with major projects

T&T Group seeks to reshape north-central Vietnam’s urban landscape with major projects

Multi-sector conglomerate T&T Group is developing a model eco-urban complex in Ha Tinh province and plans to build a massive 236-hectare urban area in neighboring Nghe An, with an aim to reshape north-central Vietnam's urban landscape.

Investing - Fri, October 17, 2025 | 2:44 pm GMT+7

Toyota plans $359 mln plant expansion in northern Vietnam

Toyota plans $359 mln plant expansion in northern Vietnam

Toyota Motor Vietnam (TMV) plans to invest about VND9.46 trillion ($359.2 million) in the first phase of its plant expansion project in Phu Tho province.

Investing - Fri, October 17, 2025 | 2:09 pm GMT+7

PVI Insurance sees 9-month profit before tax more than doubling

PVI Insurance sees 9-month profit before tax more than doubling

PVI Insurance has reaffirmed its position as the No. 1 non-life insurer in Vietnam, with total revenue increasing nearly 1.4 times in the first nine months of 2025 and pre-tax profit more than doubling year-on-year - surpassing its full-year targets for both revenue and profit.

Companies - Fri, October 17, 2025 | 9:08 am GMT+7

Vingroup to develop 4,600ha coastal urban project in northern Vietnam

Vingroup to develop 4,600ha coastal urban project in northern Vietnam

A consortium of Vingroup (HoSE: VIC) and its real estate arm Vinhomes (HoSE: VHM) will develop a 4,600-hectare coastal urban complex in Ha An ward, Quang Ninh province, following local authorities’ approval of a zoning plan.

Real Estate - Fri, October 17, 2025 | 8:30 am GMT+7

Indonesia resumes int’l carbon trading after 4-year hiatus

Indonesia resumes int’l carbon trading after 4-year hiatus

Indonesian President Prabowo Subianto has issued a new decree to restart international carbon emissions trading after a four-year hiatus.

Southeast Asia - Thu, October 16, 2025 | 9:23 pm GMT+7

Investors seek 2-year delay for $2.56 bln LNG power project in northern Vietnam, citing equipment hurdles

Investors seek 2-year delay for $2.56 bln LNG power project in northern Vietnam, citing equipment hurdles

Investors of a $2.56 billion LNG-fired power plant in Hung Yen province have proposed delaying the project’s commercial operation schedule by two years due to difficulties securing key equipment.

Energy - Thu, October 16, 2025 | 9:04 pm GMT+7

Vietnam to soon raise taxpayers' personal deduction: official

Vietnam to soon raise taxpayers' personal deduction: official

The personal income tax deduction in Vietnam is "very likely" to increase to VND21.7 million ($823,940) per month, including VND15.5 million (588,530) for the taxpayer and VND6.2 million ($235,410) for each dependent.

Finance - Thu, October 16, 2025 | 6:25 pm GMT+7

Business confidence climbs as reforms gain traction amid global headwinds: EuroCham Vietnam

Business confidence climbs as reforms gain traction amid global headwinds: EuroCham Vietnam

The index climbed to 66.5, surpassing pre-tariffs level and reaching its highest in three years – showcasing resilience and adaptability amid global headwinds and evolving U.S. tariff pressures.

Economy - Thu, October 16, 2025 | 4:36 pm GMT+7

Vietnam's stock market watchdog suspends two Grant Thornton auditors

Vietnam's stock market watchdog suspends two Grant Thornton auditors

Vietnam's State Securities Commission (SSC) has suspended two auditors from Grant Thornton Vietnam after determining that the 2024 audited financial statements of Saigon Water Infrastructure Corporation (HoSE: SII) failed to meet required standards.

Finance - Thu, October 16, 2025 | 3:35 pm GMT+7

Law No. 56 a major policy breakthrough for Vietnam's stock market development

Law No. 56 a major policy breakthrough for Vietnam's stock market development

The Law No. 56, effective January 1, 2025, is one of the major legal breakthroughs in recent years that will enhance the transparency and operational efficiency of the Vietnamese stock market.

Finance - Thu, October 16, 2025 | 2:30 pm GMT+7

WHA Group breaks ground on smart technology industrial zone in central Vietnam

WHA Group breaks ground on smart technology industrial zone in central Vietnam

Thailand's WHA Group on Tuesday broke ground on a world-class, modern, and environmentally friendly industrial zone in central Vietnam, namely the WHA Smart Technology Industrial Zone-Thanh Hoa.

Real Estate - Thu, October 16, 2025 | 2:00 pm GMT+7

Vietnam a key partner in Murphy Oil’s global strategy: exec

Vietnam a key partner in Murphy Oil’s global strategy: exec

Vietnam remains a key partner in Murphy Oil’s global business strategy, said Eric Hambly, the U.S. corporation's president and CEO.

Companies - Thu, October 16, 2025 | 12:06 pm GMT+7

VNPT, Qualcomm debut Vietnam’s 1st original design-based excellence center

VNPT, Qualcomm debut Vietnam’s 1st original design-based excellence center

State-owned Vietnam Posts and Telecommunications Group (VNPT) and Qualcomm have officially launched the VNPT-Qualcomm Excellence Center (VQEC), the first facility in the country to operate under an original design co-development model using Qualcomm’s core technologies.

Companies - Thu, October 16, 2025 | 8:41 am GMT+7