EVNNPT strives to complete 220kV Vung Ang substation project and connection in July

By Nguyen Huong, Chau Anh
Mon, July 7, 2025 | 5:02 pm GMT+7

All available resources should be maximized to complete the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam within July, said Pham Le Phu, general director of state utility Vietnam Electricity's (EVN) National Power Transmission Corporation (EVNNPT) - the project investor.

Phu made the request last Thursday during a field trip to the project, whose construction is being accelerated under an emulation movement jointly launched by the Vietnam General Confederation of Labor (VGCL) and EVN.

Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.

Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.

The Central Power Projects Management Board (CPMB) acts on behalf of the investor to oversee and operate the project.

The joint venture between EVN International JSC and Energy JSC provides supervision consultancy services, while industrial engineering company Lilama serves as the main contractor.

The substation is located in Vung Ang ward, Ha Tinh province, with the grid connection line running through Vung Ang and Song Tri wards.

The substation is designed with three voltage levels - 220kV, 110kV, and 22kV. By 2030, it will be equipped with two 220/110/22kV transformers, each with a capacity of 250MVA. A third transformer of the same capacity is planned for installation after 2030 as a backup.

In the current phase, one transformer is being installed. The grid connection line spans a total length of 2 × 13.4 kilometers.

The construction has been basically completed, with only final tasks remaining, such as site finishing and asphalt paving inside and outside the station.

Electrical installation has been completed, including the connection of primary and secondary equipment and the transformer. Most of the commissioning work has been finalized, and the project team is currently reviewing and addressing remaining issues.

The 220kV grid connection line has been the most challenging project component in recent months, primarily due to obstacles in land clearance and compensation.

However, thanks to the strong involvement of local authorities, the province has so far handed over 45 out of 45 tower locations and 21 out of 25 right-of-way span anchor points along the transmission line corridor.

As for construction progress, 41 out of the 45 tower foundations have been erected, with work ongoing at the remaining four locations. The project has completed stringing for 15 out of 25 anchor spans and is currently working on three more.

At the field inspection, Phu emphasized that this is a critically important project to ensure power supply for Ha Tinh province and the region during this year’s peak summer demand.

Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.

Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.

For this reason, the VGCL and EVN have included the project in EVN’s list of urgent key works to be put into operation in 2025. EVNNPT and its trade union have launched an emulation campaign to accelerate construction and complete the project as early as possible.

Phu lauded the efforts of CPMB and the contractors involved, noting their strong commitment to delivering a substantial volume of work.

He also pointed out that some right-of-way clearance issues remain unresolved. Therefore, he called on CPMB to maintain close coordination with contractors and local authorities to conduct public outreach, helping residents better understand the project's importance and encouraging their support in handing over the remaining land.

Although the remaining workload is not extensive, it still requires the active engagement of the entire political system, Phu said.

He requested all units to maintain a high level of focus and closely coordinate with local authorities and communities to conduct outreach and address obstacles related to right-of-way clearance.

The July completion would be a meaningful achievement to mark the 4th EVN Party Congress for the 2025-2030 term and the 96th anniversary of the Vietnam Trade Union (July 28, 1929), he noted.

The units were also required to mobilize both manpower and equipment to simultaneously carry out foundation casting and tower erection across all remaining locations to ensure progress stays on schedule.

During construction, special attention must be paid to safety, with occupational safety for both workers and equipment placed as the top priority, Phu said.

As part of the working program, Phu held a meeting with the Party Committees and People’s Committees of Song Tri and Vung Ang wards to discuss solutions to site clearance obstacles at the remaining four anchor spans along the transmission line corridor.

He emphasized the project's urgency and strategic importance, saying once compensation for affected households is calculated accurately and fairly, if any households still deliberately refuse to cooperate, Song Tri and Vung Ang authorities should implement measures to ensure site access.

In response, Song Tri and Vung Ang leaders affirmed their clear understanding of the project's importance and pledged to take strong, proactive measures to promptly resolve outstanding issues, completing the project within this month.

Comments (0)
  • Read More
Vietnam’s finance ministry proposes raising personal deduction to $588 per month

Vietnam’s finance ministry proposes raising personal deduction to $588 per month

Vietnam’s Ministry of Finance has proposed raising the personal income tax deduction to VND15.5 million ($588) per month and the dependent deduction to VND6.2 million ($235).

Economy - Tue, September 9, 2025 | 4:09 pm GMT+7

PM urges prompt finalization of feasibility study for Lao Cai-Hanoi-Hai Phong railway project

PM urges prompt finalization of feasibility study for Lao Cai-Hanoi-Hai Phong railway project

Prime Minister Pham Minh Chinh on Sunday evening chaired a high-level meeting with key ministries and agencies to accelerate the implementation of the Lao Cai-Hanoi-Hai Phong railway project, during which he stressed the need for prompt completion of the project’s feasibility study.

Economy - Tue, September 9, 2025 | 3:06 pm GMT+7

WB, ADB to provide over $12 bln to green projects in ASEAN

WB, ADB to provide over $12 bln to green projects in ASEAN

The World Bank has allocated $2.5 billion, while the Asian Development Bank has set aside $10 billion to support green projects in ASEAN, said Malaysian Deputy Prime Minister Datuk Seri Fadillah Yusof.

Southeast Asia - Tue, September 9, 2025 | 3:01 pm GMT+7

Central Vietnam province seeks investors for $42 mln wind power project

Central Vietnam province seeks investors for $42 mln wind power project

Vietnam’s central province of Quang Tri is seeking investors for the Hung Bac wind power project, with total investment estimated at VND1.1 trillion ($41.69 million), according to the provincial People’s Committee.

Energy - Tue, September 9, 2025 | 2:56 pm GMT+7

Vietnam's leading conglomerate Vingroup sues 68 entities, individuals for false information

Vietnam's leading conglomerate Vingroup sues 68 entities, individuals for false information

Vingroup JSC (HoSE: VIC) on Monday reported to authorities, notified foreign embassies, and filed civil lawsuits against 68 organizations and individuals at home and abroad for spreading false information about the corporation online.

Companies - Tue, September 9, 2025 | 10:45 am GMT+7

Warburg Pincus unit, Masterise eye $739 mln expressway to Vietnam’s mega airport

Warburg Pincus unit, Masterise eye $739 mln expressway to Vietnam’s mega airport

A subsidiary of U.S. private equity firm Warburg Pincus and Vietnamese developer Masterise Group have separately proposed building an over VND19.52 trillion ($739 million) expressway connecting a major tourism area to the under-construction Long Thanh International Airport in the southern region.

Infrastructure - Tue, September 9, 2025 | 8:00 am GMT+7

Hoa Binh Construction wins $5 bln contract for mega urban project in southern Vietnam

Hoa Binh Construction wins $5 bln contract for mega urban project in southern Vietnam

Vietnam's leading contractor Hoa Binh Construction Group has secured a contract to build the first phase of a mega urban area project in Vietnam’s southern metropolis of Ho Chi Minh City.

Real Estate - Mon, September 8, 2025 | 9:22 pm GMT+7

Vietnam's monetary policy remains accommodative: WB

Vietnam's monetary policy remains accommodative: WB

Vietnam's monetary policy has remained accommodative, as State Bank of Vietnam (SBV) interventions contained foreign exchange pressures and increased credit growth, the World Bank Group said in its country economic update.

Economy - Mon, September 8, 2025 | 7:46 pm GMT+7

Property, technology, energy among sectors recording highest M&A activity in Vietnam

Property, technology, energy among sectors recording highest M&A activity in Vietnam

Vietnam’s M&A landscape in July recorded 34 completed transactions with the total disclosed and estimated deal value of $786 million, according to Grant Thornton Vietnam.

Economy - Mon, September 8, 2025 | 3:49 pm GMT+7

Vietnam's Van Thinh Phat-tied firm incurs $14 mln loss in H1 as legal woes persist

Vietnam's Van Thinh Phat-tied firm incurs $14 mln loss in H1 as legal woes persist

Bong Sen Corp, the hotel and property arm of troubled Van Thinh Phat Group, posted a net loss of nearly VND356 billion ($14 million) in the first half of 2025, its filing to the Hanoi Stock Exchange (HNX) showed.

Companies - Mon, September 8, 2025 | 3:24 pm GMT+7

Airport-centric urbanization - Vietnam’s new growth engine

Airport-centric urbanization - Vietnam’s new growth engine

In the past, cities in Vietnam would build airports to meet growing transportation needs, but today, airports themselves are becoming the nucleus around which new urban areas emerge.

Real Estate - Mon, September 8, 2025 | 1:36 pm GMT+7

Vietnam’s 8.3-8.5% growth target for 2025 ‘appropriate’: policy advisory council

Vietnam’s 8.3-8.5% growth target for 2025 ‘appropriate’: policy advisory council

The Vietnamese government’s GDP growth target of 8.3-8.5% for 2025 and double-digit expansion for 2026-2030 is "appropriate" in the context of favorable macroeconomic conditions and structural reforms, according to the Prime Minister’s Policy Advisory Council.

Economy - Mon, September 8, 2025 | 1:03 pm GMT+7

Enertrag SE proposes 55 MW wind power project in northern Vietnam

Enertrag SE proposes 55 MW wind power project in northern Vietnam

The Bac Ninh province People’s Committee is seeking public and ministerial feedback on a 55 MW wind power plant initiated by Enertrag Vietnam Co., Ltd, a subsidiary of German-based global renewables developer Enertrag SE.

Energy - Mon, September 8, 2025 | 11:29 am GMT+7

Southern Vietnam airport project Long Thanh on fast track, test flights set for December

Southern Vietnam airport project Long Thanh on fast track, test flights set for December

Construction of the Long Thanh International Airport in the southern province of Dong Nai is progressing on schedule, with calibration flights for Runway 1 planned for September 25 and a technical test flight expected on December 19.

Infrastructure - Mon, September 8, 2025 | 11:13 am GMT+7

Why Vietnamese agricultural machinery major VEAM shares on sidelines of market rally?

Why Vietnamese agricultural machinery major VEAM shares on sidelines of market rally?

While Vietnam’s stock market has surged in recent months, sending the benchmark VN-Index from around 1,090 points to nearly 1,700, state-controlled VEAM’s stock VEA has remained flat, trading sideways at around VND39,000 ($1.48) per share over the past year.

Companies - Mon, September 8, 2025 | 8:30 am GMT+7

New train helps tourists explore landmarks of Hanoi, Bac Ninh province

New train helps tourists explore landmarks of Hanoi, Bac Ninh province

The Hanoi Train officially began operation on Saturday, offering visitors a new way to explore the capital’s landmarks and travel to Tu Son in Bac Ninh province.

Travel - Sun, September 7, 2025 | 8:20 pm GMT+7