EVNNPT strives to complete 220kV Vung Ang substation project and connection in July
All available resources should be maximized to complete the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam within July, said Pham Le Phu, general director of state utility Vietnam Electricity's (EVN) National Power Transmission Corporation (EVNNPT) - the project investor.
Phu made the request last Thursday during a field trip to the project, whose construction is being accelerated under an emulation movement jointly launched by the Vietnam General Confederation of Labor (VGCL) and EVN.
Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.
The Central Power Projects Management Board (CPMB) acts on behalf of the investor to oversee and operate the project.
The joint venture between EVN International JSC and Energy JSC provides supervision consultancy services, while industrial engineering company Lilama serves as the main contractor.
The substation is located in Vung Ang ward, Ha Tinh province, with the grid connection line running through Vung Ang and Song Tri wards.
The substation is designed with three voltage levels - 220kV, 110kV, and 22kV. By 2030, it will be equipped with two 220/110/22kV transformers, each with a capacity of 250MVA. A third transformer of the same capacity is planned for installation after 2030 as a backup.
In the current phase, one transformer is being installed. The grid connection line spans a total length of 2 × 13.4 kilometers.
The construction has been basically completed, with only final tasks remaining, such as site finishing and asphalt paving inside and outside the station.
Electrical installation has been completed, including the connection of primary and secondary equipment and the transformer. Most of the commissioning work has been finalized, and the project team is currently reviewing and addressing remaining issues.
The 220kV grid connection line has been the most challenging project component in recent months, primarily due to obstacles in land clearance and compensation.
However, thanks to the strong involvement of local authorities, the province has so far handed over 45 out of 45 tower locations and 21 out of 25 right-of-way span anchor points along the transmission line corridor.
As for construction progress, 41 out of the 45 tower foundations have been erected, with work ongoing at the remaining four locations. The project has completed stringing for 15 out of 25 anchor spans and is currently working on three more.
At the field inspection, Phu emphasized that this is a critically important project to ensure power supply for Ha Tinh province and the region during this year’s peak summer demand.
Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.
For this reason, the VGCL and EVN have included the project in EVN’s list of urgent key works to be put into operation in 2025. EVNNPT and its trade union have launched an emulation campaign to accelerate construction and complete the project as early as possible.
Phu lauded the efforts of CPMB and the contractors involved, noting their strong commitment to delivering a substantial volume of work.
He also pointed out that some right-of-way clearance issues remain unresolved. Therefore, he called on CPMB to maintain close coordination with contractors and local authorities to conduct public outreach, helping residents better understand the project's importance and encouraging their support in handing over the remaining land.
Although the remaining workload is not extensive, it still requires the active engagement of the entire political system, Phu said.
He requested all units to maintain a high level of focus and closely coordinate with local authorities and communities to conduct outreach and address obstacles related to right-of-way clearance.
The July completion would be a meaningful achievement to mark the 4th EVN Party Congress for the 2025-2030 term and the 96th anniversary of the Vietnam Trade Union (July 28, 1929), he noted.
The units were also required to mobilize both manpower and equipment to simultaneously carry out foundation casting and tower erection across all remaining locations to ensure progress stays on schedule.
During construction, special attention must be paid to safety, with occupational safety for both workers and equipment placed as the top priority, Phu said.
As part of the working program, Phu held a meeting with the Party Committees and People’s Committees of Song Tri and Vung Ang wards to discuss solutions to site clearance obstacles at the remaining four anchor spans along the transmission line corridor.
He emphasized the project's urgency and strategic importance, saying once compensation for affected households is calculated accurately and fairly, if any households still deliberately refuse to cooperate, Song Tri and Vung Ang authorities should implement measures to ensure site access.
In response, Song Tri and Vung Ang leaders affirmed their clear understanding of the project's importance and pledged to take strong, proactive measures to promptly resolve outstanding issues, completing the project within this month.
- Read More
Mega-airport Long Thanh in southern Vietnam welcomes first passenger flights
The first passenger flights touched down at Long Thanh International Airport in Dong Nai province on Friday morning, marking the inaugural civil aviation operation at Vietnam’s largest airport.
Economy - Fri, December 19, 2025 | 2:07 pm GMT+7
Vingroup starts work on $35.2 bln Olympic Sports Urban Area on Hanoi outskirts
Vingroup (HoSE: VIC), Vietnam's leading private conglomerate, on Friday broke ground on its 9,171-hectare Olympic Sports Urban Area project in Hanoi, which is expected to become a new growth engine for the southern part of the capital in the next decade.
Real Estate - Fri, December 19, 2025 | 1:59 pm GMT+7
Vietnam telecom giant VNPT establishes AI company
State-owned Vietnam Posts and Telecommunications Group (VNPT) on Thursday launched subsidiary VNPT AI, aiming to bring Vietnamese AI products to international markets.
Companies - Fri, December 19, 2025 | 11:50 am GMT+7
Quang Ngai Sugar develops sugar, biomass power projects worth $179 mln in central Vietnam
Quang Ngai Sugar JSC (UPCom: QNS), a top sugar producer in Vietnam, will simultaneously hold groundbreaking or inauguration ceremonies on Friday for three projects worth over VND4.7 trillion ($178.5 million) in Gia Lai province.
Companies - Fri, December 19, 2025 | 8:05 am GMT+7
Vietnam defeat Thailand to win men’s football gold at SEA Games 33
After conceding two goals in just over 30 minutes, Vietnam reversed the situation to finally beat host nation Thailand 3-2 in the men’s football final of the 33rd SEA Games.
Society - Thu, December 18, 2025 | 10:43 pm GMT+7
Sun Group to commence construction on 5 landmark projects worth $5.7 bln
Sun Group is scheduled to start construction of five large-scale projects across Vietnam’s three regions on Friday, with a total investment of nearly $5.7 billion.
Companies - Thu, December 18, 2025 | 8:39 pm GMT+7
Unpaid credit card balances in Singapore hit record high in 10 years
Singapore's credit card debt has exceeded SGD9.07 billion (about $7 billion) in 2025's third quarter, a 10-year high that was last seen in 2014.
Southeast Asia - Thu, December 18, 2025 | 7:54 pm GMT+7
Thailand, Japan deepen transport, infrastructure cooperation
Thai Deputy Prime Minister and Minister of Transport Phiphat Ratchakitprakarn has met with Japanese Ambassador Otaka Masato to advance cooperation in Thailand’s transportation and infrastructure projects.
Southeast Asia - Thu, December 18, 2025 | 7:50 pm GMT+7
Masan's FMCG arm MCH to list on HCMC bourse at $8 per share, valuation tops $8.6 bln
Masan Consumer Corporation (UpCoM: MCH), the fast-moving consumer goods arm of Vietnam’s Masan Group, will officially debut on the Ho Chi Minh City Stock Exchange (HoSE) on December 25, with a reference price set at VND212,800 ($8.08) per share.
Companies - Thu, December 18, 2025 | 4:57 pm GMT+7
Sun Group-led consortium to build $616 mln Red River bridge in Hanoi
Hanoi authorities have approved a consortium led by Sun Group as the investor for the Tran Hung Dao bridge project, with a total investment estimated at VND16.27 trillion ($616.14 million).
Infrastructure - Thu, December 18, 2025 | 3:26 pm GMT+7
Shinhan Bank Vietnam accompanies SMEs in promoting cashless payments
With modern, secure and convenient payment solutions designed to meet the specific needs of businesses, particularly the SME segment, Shinhan Bank Vietnam continues to accompany enterprises in building a modern corporate image and keeping pace with the digital economy.
Banking - Thu, December 18, 2025 | 2:10 pm GMT+7
JC&C to divest 4.6% stake at Vietnam's dairy giant Vinamilk to F&N for $228 mln
Singapore-listed Jardine Cycle & Carriage Limited (JC&C) has announced the sale of more than 96 million shares, or a 4.6% stake, in Vietnam’s dairy giant Vinamilk (HoSE: VNM) to F&N Dairy Investments Pte. Ltd., part of the Fraser and Neave (F&N) group controlled by Thai billionaire Charoen Sirivadhanabhakdi.
Companies - Thu, December 18, 2025 | 1:36 pm GMT+7
Siemens to supply high-speed trains, key railway systems to Vingroup's subsidiary VinSpeed
Siemens Mobility on Wednesday signed a comprehensive strategic cooperation and high-speed railway technology transfer agreement with VinSpeed, a unit of Vietnam’s Vingroup, to supply high-speed trains and key railway systems for planned rail projects in Vietnam.
Companies - Thu, December 18, 2025 | 1:24 pm GMT+7
Hanoi administration to raise over $52 mln from Thuong Dinh Footwear divestment
Hanoi’s municipal government is set to raise nearly VND1.38 trillion ($52.35 million) from the sale of its entire 68.67% stake in Thuong Dinh Footwear Company - a major footwear producer in Vietnam, after two individual investors agreed to buy all shares on offer at a price far above market levels.
Companies - Thu, December 18, 2025 | 10:01 am GMT+7
Sony Music to acquire 49% stake at Vietnam's YeaH1 subsidiary
Sony Music Entertainment Hong Kong Ltd. will invest in a unit of YeaH1 (HoSE: YEG), a leading media entertainment technology group in Vietnam, through a private placement, acquiring a 49% stake and reducing YeaH1’s ownership to 49.88%.
Companies - Thu, December 18, 2025 | 8:34 am GMT+7
Honda Vietnam expands biz registration to cover electric vehicles, charging, battery swapping
Honda Vietnam (HVN) has formally expanded its registered business lines to include electric vehicles, charging infrastructure, and battery-swapping services, marking its most comprehensive step into the electric mobility ecosystem to date.
Companies - Wed, December 17, 2025 | 5:16 pm GMT+7




















