EVNNPT strives to complete 220kV Vung Ang substation project and connection in July

By Nguyen Huong, Chau Anh
Mon, July 7, 2025 | 5:02 pm GMT+7

All available resources should be maximized to complete the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam within July, said Pham Le Phu, general director of state utility Vietnam Electricity's (EVN) National Power Transmission Corporation (EVNNPT) - the project investor.

Phu made the request last Thursday during a field trip to the project, whose construction is being accelerated under an emulation movement jointly launched by the Vietnam General Confederation of Labor (VGCL) and EVN.

Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.

Stringing work is underway on the grid connection line of the 220kV Vung Ang substation project in Ha Tinh province, central Vietnam. Photo courtesy of the company.

The Central Power Projects Management Board (CPMB) acts on behalf of the investor to oversee and operate the project.

The joint venture between EVN International JSC and Energy JSC provides supervision consultancy services, while industrial engineering company Lilama serves as the main contractor.

The substation is located in Vung Ang ward, Ha Tinh province, with the grid connection line running through Vung Ang and Song Tri wards.

The substation is designed with three voltage levels - 220kV, 110kV, and 22kV. By 2030, it will be equipped with two 220/110/22kV transformers, each with a capacity of 250MVA. A third transformer of the same capacity is planned for installation after 2030 as a backup.

In the current phase, one transformer is being installed. The grid connection line spans a total length of 2 × 13.4 kilometers.

The construction has been basically completed, with only final tasks remaining, such as site finishing and asphalt paving inside and outside the station.

Electrical installation has been completed, including the connection of primary and secondary equipment and the transformer. Most of the commissioning work has been finalized, and the project team is currently reviewing and addressing remaining issues.

The 220kV grid connection line has been the most challenging project component in recent months, primarily due to obstacles in land clearance and compensation.

However, thanks to the strong involvement of local authorities, the province has so far handed over 45 out of 45 tower locations and 21 out of 25 right-of-way span anchor points along the transmission line corridor.

As for construction progress, 41 out of the 45 tower foundations have been erected, with work ongoing at the remaining four locations. The project has completed stringing for 15 out of 25 anchor spans and is currently working on three more.

At the field inspection, Phu emphasized that this is a critically important project to ensure power supply for Ha Tinh province and the region during this year’s peak summer demand.

Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.

Pham Le Phu, general director of National Power Transmission Corporation (EVNNPT), visits the construction site. Phoby by courtesy of the company.

For this reason, the VGCL and EVN have included the project in EVN’s list of urgent key works to be put into operation in 2025. EVNNPT and its trade union have launched an emulation campaign to accelerate construction and complete the project as early as possible.

Phu lauded the efforts of CPMB and the contractors involved, noting their strong commitment to delivering a substantial volume of work.

He also pointed out that some right-of-way clearance issues remain unresolved. Therefore, he called on CPMB to maintain close coordination with contractors and local authorities to conduct public outreach, helping residents better understand the project's importance and encouraging their support in handing over the remaining land.

Although the remaining workload is not extensive, it still requires the active engagement of the entire political system, Phu said.

He requested all units to maintain a high level of focus and closely coordinate with local authorities and communities to conduct outreach and address obstacles related to right-of-way clearance.

The July completion would be a meaningful achievement to mark the 4th EVN Party Congress for the 2025-2030 term and the 96th anniversary of the Vietnam Trade Union (July 28, 1929), he noted.

The units were also required to mobilize both manpower and equipment to simultaneously carry out foundation casting and tower erection across all remaining locations to ensure progress stays on schedule.

During construction, special attention must be paid to safety, with occupational safety for both workers and equipment placed as the top priority, Phu said.

As part of the working program, Phu held a meeting with the Party Committees and People’s Committees of Song Tri and Vung Ang wards to discuss solutions to site clearance obstacles at the remaining four anchor spans along the transmission line corridor.

He emphasized the project's urgency and strategic importance, saying once compensation for affected households is calculated accurately and fairly, if any households still deliberately refuse to cooperate, Song Tri and Vung Ang authorities should implement measures to ensure site access.

In response, Song Tri and Vung Ang leaders affirmed their clear understanding of the project's importance and pledged to take strong, proactive measures to promptly resolve outstanding issues, completing the project within this month.

Comments (0)
  • Read More
Vietnam, Japan agree to target $5 bln annual investment, $60 bln trade by 2030

Vietnam, Japan agree to target $5 bln annual investment, $60 bln trade by 2030

Prime Ministers Le Minh Hung of Vietnam and Takaichi Sanae of Japan have signed six bilateral co-operation documents following summit talks at the Government headquarters.

Economy - Sat, May 2, 2026 | 4:01 pm GMT+7

Vietnam's top dairy producer Vinamilk posts Q1 profit of nearly $93 mln

Vietnam's top dairy producer Vinamilk posts Q1 profit of nearly $93 mln

Vinamilk (HoSE: VNM) reported a net profit of nearly VND2.46 trillion ($93.26 million) in the first quarter of 2026, up 55% from the same period last year, as the dairy producer met about a quarter of its full-year target after three months.

Companies - Sat, May 2, 2026 | 3:26 pm GMT+7

Vietnamese PM hosts welcome ceremony for Japanese counterpart

Vietnamese PM hosts welcome ceremony for Japanese counterpart

Prime Minister Le Minh Hung on Saturday morning hosted an official welcome ceremony for Japanese Prime Minister Takaichi Sanae, who is on a three-day official visit to Vietnam.

Politics - Sat, May 2, 2026 | 12:37 pm GMT+7

PV Oil completes 81% of full-year profit target in Q1

PV Oil completes 81% of full-year profit target in Q1

PV Oil, a subsidiary of state-owned Petrovietnam, reported a sharp surge in first-quarter earnings, achieving 81% of its full-year profit target within the first three months of 2026, driven largely by favorable inventory dynamics.

Companies - Sat, May 2, 2026 | 8:17 am GMT+7

Major players eye Vietnam’s wastewater treatment market

Major players eye Vietnam’s wastewater treatment market

Vietnam’s wastewater treatment sector is entering a transition phase as a growing number of large corporations signal plans to enter or expand investments, driven by rising environmental infrastructure demand and expectations of clearer wastewater pricing mechanisms.

Companies - Sat, May 2, 2026 | 8:00 am GMT+7

Work on $92 mln eco-urban resort project starts in northern Vietnam tourist hotspot

Work on $92 mln eco-urban resort project starts in northern Vietnam tourist hotspot

A consortium of Hong Phong ID Co. Ltd. and Ecopark Hai Duong JSC has broken ground on a VND2.42 trillion ($91.97 million) eco-urban tourism project in Vietnam's northern border province of Lao Cai.

Real Estate - Fri, May 1, 2026 | 9:08 pm GMT+7

Royal Shore Beachclub announces grand opening in Hoi An

Royal Shore Beachclub announces grand opening in Hoi An

Royal Capital Group on Thursday announced the grand opening of its newest beachfront destination, set along the pristine coastline of Hoi An.

Travel - Fri, May 1, 2026 | 6:48 pm GMT+7

Novaland posts Q1 profit of $33 mln, shares hit three-year high

Novaland posts Q1 profit of $33 mln, shares hit three-year high

Novaland (HoSE: NVL) reported a strong turnaround in the first quarter of 2026, swinging to a net profit of VND860 billion ($32.63 million) from a loss a year earlier, as revenue doubled on increased property handovers.

Companies - Fri, May 1, 2026 | 3:09 pm GMT+7

Vinaconex, Vietjet have new CEOs

Vinaconex, Vietjet have new CEOs

Vietnamese construction heavyweight Vinaconex on Wednesday appointed deputy CEO Pham Thai Duong as CEO and legal representative, replacing Nguyen Xuan Dong.

Companies - Fri, May 1, 2026 | 2:41 pm GMT+7

Japanese retailer Aeon Mall to build another shopping center in northern Vietnam

Japanese retailer Aeon Mall to build another shopping center in northern Vietnam

Japan’s Aeon Mall is set to invest nearly $150 million in a shopping mall project in the northern province of Bac Ninh, marking a further push into Vietnam’s fast-growing industrial localities.

Industries - Fri, May 1, 2026 | 10:59 am GMT+7

Hyosung Vina raises $7.6 mln in unsecured bond sale

Hyosung Vina raises $7.6 mln in unsecured bond sale

Hyosung Vina Chemicals, the Vietnam arm of South Korean chaebol Hyosung, has completed a VND200 billion ($7.59 million) domestic bond issuance, according to disclosures on the Hanoi Stock Exchange.

Companies - Fri, May 1, 2026 | 10:16 am GMT+7

Vietnam central bank to add new metrics to oversee banking activity

Vietnam central bank to add new metrics to oversee banking activity

The State Bank of Vietnam is proposing a set of new prudential metrics to strengthen oversight of banking operations, replacing the traditional loan-to-deposit ratio (LDR) with a broader framework aligned with Basel III standards.

Banking - Fri, May 1, 2026 | 8:00 am GMT+7

From national reunification to aspiration for an integrated development space

From national reunification to aspiration for an integrated development space

In 1975, Vietnam united the country through determination and a shared aspiration for independence. Today, in a very different context, the country faces a new challenge: unifying its market through institutional reform, writes Dr. Nguyen Sy Dung, former deputy head of the Office of the National Assembly - the country's legislature.

Economy - Thu, April 30, 2026 | 10:27 pm GMT+7

Vietjet seeks deeper engagement in Vietnam's aviation infrastructure development

Vietjet seeks deeper engagement in Vietnam's aviation infrastructure development

Vietjet, Vietnam’s first private airline, has proposed earlier and broader participation in Vietnam’s airport planning and infrastructure development, as the budget carrier looks to expand its role beyond flight operations into ground services and logistics.

Companies - Thu, April 30, 2026 | 9:42 pm GMT+7

Vietnamese giants kick off 4 mega projects in HCMC

Vietnamese giants kick off 4 mega projects in HCMC

The Ho Chi Minh City People’s Committee on Wednesday held a groundbreaking ceremony for four large-scale projects invested by Vietnamese conglomerates including Vingroup, Sun Group and Truong Hai Group (Thaco).

Economy - Thu, April 30, 2026 | 8:01 pm GMT+7

Vingroup starts work on $2.2 bln int'l university township in southern Vietnam

Vingroup starts work on $2.2 bln int'l university township in southern Vietnam

Vietnam’s conglomerate Vingroup (HoSE: VIC) on Wednesday broke ground on a VND59 trillion ($2.24 billion) international university township in Ho Chi Minh City.

Real Estate - Thu, April 30, 2026 | 12:38 pm GMT+7