Key infrastructure projects face site clearance issues, material shortages

By Hai Yen, Trong Hieu
Thu, May 2, 2024 | 3:35 pm GMT+7

Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.

National key projects gradually built up

The Long Thanh airport project in the southern province of Dong Nai has an estimated investment of VND336.63 trillion ($16.06 billion), with its first phase requiring VND114.45 trillion ($5.45 billion).

The first phase of the three-stage project involves the construction of a runway and passenger terminal, along with auxiliary facilities, capable of handling 25 million passengers per year. A cargo terminal is designed to have an annual capacity of 1.2 million tons of freight. The first phase is expected to come on stream by 2025 at the latest.

The second phase will cover an additional open runway and one passenger terminal, aiming to raise the airport’s yearly capacity to 50 million passengers. Additionally, a cargo terminal capable of handling 1.5 million tons of cargo per year will be supplemented.

For the third phase, further enhancements will be made to lift the project’s capacity to 100 million passengers and five million tons of cargo annually.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

The project has largely remained on schedule thus far, but the Airports Corporation of Vietnam (ACV) has reported some hurdles to site clearance.

Specifically, while the site handover for a traffic system connecting Road No.1 has been 99% completed, an issue related to site clearance persists at the intersection between Road No.1 and the Bien Hoa-Vung Tau Expressway project. Additionally, there is a similar hitch to the section extending from Km0+880 to Km0+944 of the Bung Mon bridge.

Those obstacles have delayed land increment reinforcement, posing a risk to the progress of soft roadbed soil treatment

Additionally, although over 89% of the site has been allocated for the construction of road No.2, ACV noted that approximately 80% of the area is qualified for development, and some locations have still not been fully cleared for construction.

For example, the non-cleared location at the intersection between Road No.2 and the Ho Chi Minh City-Long Thanh-Dau Giay Expressway has impacted the progress of an overpass spanning the expressway’s T12-to-T22 section, which may take 12 months to construct.

Additionally, certain existing technical issues, particularly power lines, along Road No.2 have yet to be cleared or relocated, impacting both safety assurance and construction progress.

Therefore, ACV proposed the People’s Committee of Dong Nai province to ask relevant units to accelerate site clearance for a complete handover to ensure the project runs on schedule.

In early February, Prime Minister Pham Minh Chinh inspected the Long Thanh airport project. During his visit, the PM emphasized that while previous years had laid the foundation for the airport, this year marks a period of acceleration, and 2025 is slated as the breakthrough year.

He also stressed the urgency of completing the airport project within the first half of 2026. Drawing from past experiences, Chinh asked for the timeline to be adjusted with a view to shortening the progress by three-six months to offset any delays.

As a key national project, Long Thanh airport will significantly enhance flight routes, bolster Vietnam’s economic links with countries in ASEAN and the world, and alleviate congestion at Tan Son Nhat International Airport, which is located in the adjacent metropolis of Ho Chi Minh City.

It is expected to serve as a pivotal transit hub for Asia and beyond by 2030. However, site clearance setbacks have made investors and contractors fret over deadlines committed to by the government.

North-South Expressway component projects likely to miss 2025 completion deadline

After one year of construction, the component projects of the North-South Expressway’s eastern section in the 2021-2025 period are facing many challenges related to site clearance and material shortages. If these issues are not addressed promptly, the Ministry of Transport (MoT) acknowledges that it will be difficult to complete the component projects by 2025 as required by the government and National Assembly.

Notably, the 49-km Dien Chau-Bai Vot Expressway project, kicked off in May 2021 with a total investment of VND11.15 trillion ($446.2 million), is designed to connect Nghe An and Ha Tinh provinces, both in the central region.

A 30-kilometer segment of the project, extending from the intersection of National Highway No.7 (Dien Chau district) to the intersection of National Highway No.46B (Hung Nguyen district), was inaugurated on April 28, shortening the travel time between Hanoi and Nghe An’s Vinh town from five and a half hours to three hours by car.

However, the remaining 19 kilometers from National Highway No.46B to Bai Vot district (Ha Tinh province), characterized by soft soil, requires additional time for ground reinforcement and will be inaugurated this September.

Similarly, the Cam Lam-Vinh Hao Expressway, spanning the central provinces of Khanh Hoa, Ninh Thuan, and Binh Thuan, was opened to traffic on April 26 after 28 months of construction. The 78.5-km route, with a total investment of VND3.92 trillion ($352.14 million), slashes the travel time from Ho Chi Minh City to Khanh Hoa’s Nha Trang town from eight hours to five hours by car.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

Regarding the 12 component projects of the North-South Expressway in 2021-2025, the MoT said that their investors and contractors had basically adhered to the timetable. However, the Can Tho-Hau Giang and Hau Giang-Ca Mau sections, both in the south, are lagging behind schedule due to a shortage of sand.

Specifically, for component projects spanning from Ha Tinh to Khanh Hoa provinces, both in central Vietnam, contractors have exploited 14 out of 17 sand quarries, meeting about 91% of the demand. The remaining three quarries, located along the Quang Ngai province-Hoai Nhon town section, remain unexploited due to disagreements with owners of mining land over compensation prices. Besides, 43 out of 55 sand quarries scattered all over the Ha Tinh-Khanh Hoa section are reported to have satisfied around 77% of the demand.

For the Can Tho-Ca Mau Expressway project, the Mekong Delta provinces of An Giang, Dong Thap, and Vinh Long have arranged a total supply of 16.02 million cubic meters of sand. Meanwhile, a source for 2.98 million m3 of sand has not yet been determined (one million m3 for An Giang and 1.98 million m3 for Vinh Long). Of the total supply, nine million m3 of sand is being exploited, and the remaining seven million is awaiting procedures for exploitation.

Contractors have delivered 2.7 million m3 of sand to the construction site, comprising 400,000 m3 for An Giang, 2.3 million m3 from Dong Thap, and 4,400 m3 for Vinh Long. The sand mining capacity in the Mekong Delta region remains considerably low, averaging only 18,000 m3/day. This falls short of the project’s daily demand of 50,000 m3, primarily due to restrictions on capacity and exploitation means/hours.

In terms of site clearance, the ministry assessed that if the site was not handed over for construction before April 30, the component projects might slip behind the scheduled completion year of 2025.

In addition, unless the amendments of Resolution 273 on changing the use purpose of forest, forest land, and rice farming land cultivated for two crops and beyond are submitted to the National Assembly’s Standing Committee for approval in April, the progress of the component projects of the North-South Expressway in 2021-2025 will be greatly impacted.

Viewing site clearance as a principal task, the MoT has requested local authorities to address hitches for these projects.

Comments (0)
  • Read More
Japanese retailer Aeon to build 2-hectare mall in Vietnam’s Mekong Delta

Japanese retailer Aeon to build 2-hectare mall in Vietnam’s Mekong Delta

Retail giant Aeon will develop a 2-hectare mall in the Mekong Delta province of Tien Giang, with an estimated investment of VND1.16 trillion ($44.6 million).

Industries - Fri, May 30, 2025 | 4:44 pm GMT+7

76% of Vietnamese survey respondents say trade uncertainty encourages them to explore new opportunities: HSBC

76% of Vietnamese survey respondents say trade uncertainty encourages them to explore new opportunities: HSBC

Vietnamese businesses have experienced exponentially higher cost increases than the global average and are expecting additional short-term costs due to trade uncertainty. But many survey respondents (76%) think trade uncertainty has encouraged their business to evolve and explore new opportunities, write HSBC analysts.

Consulting - Fri, May 30, 2025 | 2:41 pm GMT+7

AgriS partners with IFC: Optimizing environmental and social management system, accelerating net zero 2035 goal

AgriS partners with IFC: Optimizing environmental and social management system, accelerating net zero 2035 goal

TTC AgriS (Thanh Thanh Cong-Bien Hoa JSC or AgriS) and International Finance Corporation (IFC) - a member of the World Bank Group - has signed an MoU to strengthen sustainable development governance in alignment with global standards.

Companies - Fri, May 30, 2025 | 2:30 pm GMT+7

Vietnam's stock market attractively priced: Finnish fund PYN Elite

Vietnam's stock market attractively priced: Finnish fund PYN Elite

Vietnam’s stock market is attractively priced, with a price-to-sales (P/S) ratio of 1.3, said Petri Deryng, portfolio manager at Finnish investment fund PYN Elite.

Finance - Fri, May 30, 2025 | 2:09 pm GMT+7

S Korea's SK Group eyes 3 LNG power projects in Vietnam: chairman

S Korea's SK Group eyes 3 LNG power projects in Vietnam: chairman

SK Group, South Korea’s second-largest chaebol, is exploring several LNG-fueled power projects in Vietnam, including three proposed to be included in the country's green growth project portfolio, said chairman Tae-Won Chey.

Energy - Fri, May 30, 2025 | 1:37 pm GMT+7

Vietnam's Hoa Phat Group to become Southeast Asia’s first producer of steel rails for high-speed railways

Vietnam's Hoa Phat Group to become Southeast Asia’s first producer of steel rails for high-speed railways

Hoa Phat Group, a top steelmaker in Vietnam, on Thursday signed an agreement with Germany’s SMS Group under which the latter will provide the former technology and production lines for manufacturing steel rails and shaped steel, with an annual capacity of 700,000 tons.

Companies - Fri, May 30, 2025 | 11:48 am GMT+7

Vietnamese firm lands first $1 mln order on Alibaba after 8-year struggle to export

Vietnamese firm lands first $1 mln order on Alibaba after 8-year struggle to export

After five months of operating a virtual storefront on Alibaba’s B2B e-commerce platform, Sukavina Co., Ltd., a Binh Duong province-based manufacturer of metal tables, chairs, and beds, secured its first international order, marking a significant milestone in the company’s eight-year journey to global markets.

Companies - Fri, May 30, 2025 | 9:00 am GMT+7

Vietnam's telco giant Viettel signs deal with France’s John Cockerill Defense

Vietnam's telco giant Viettel signs deal with France’s John Cockerill Defense

Viettel High Tech, the core military and civilian R&D arm of Vietnam’s military-run telecom giant Viettel, has signed a cooperation agreement with John Cockerill Defense, a leading weapon designer and manufacturer in France.

Companies - Thu, May 29, 2025 | 9:14 pm GMT+7

MB showcases comprehensive financial solution Biz MBBank at Digital Transformation Day event

MB showcases comprehensive financial solution Biz MBBank at Digital Transformation Day event

Vietnam's leading bank MB on Thursday introduced its latest digital technology solutions, notably the Biz MBBank digital financial platform, at the "Smart Digital Ecosystem in the New Era" event organized by the central bank.

Companies - Thu, May 29, 2025 | 8:02 pm GMT+7

Vietnam's auto distributor TMT to launch $3.8 mln charging station firm

Vietnam's auto distributor TMT to launch $3.8 mln charging station firm

Vietnamese auto distributor TMT Motors has announced the establishment of a charging station company with a charter capital of VND100 billion ($3.84 million).

Companies - Thu, May 29, 2025 | 4:45 pm GMT+7

US's Excelerate Energy affirms intention to turn Vietnam into LNG hub for ASEAN

US's Excelerate Energy affirms intention to turn Vietnam into LNG hub for ASEAN

Excelerate Energy wants to make Vietnam a center for LNG distribution to the ASEAN region, president and CEO Steven Kobos told Prime Minister Pham Minh Chinh at a meeting in Hanoi on Thursday.

Energy - Thu, May 29, 2025 | 4:33 pm GMT+7

Bourse shifts to heat up Vietnam's banking stocks

Bourse shifts to heat up Vietnam's banking stocks

Several Vietnamese banks are planning to move their shares from the Unlisted Public Companies Market (UPCoM) to the Ho Chi Minh Stock Exchange (HoSE) this year, creating new momentum for banking stocks, long dubbed the “king” group.

Finance - Thu, May 29, 2025 | 2:48 pm GMT+7

Dairy giant TH Group proposes 5 projects in southern Vietnam

Dairy giant TH Group proposes 5 projects in southern Vietnam

TH Group, one of Vietnam’s leading dairy producers, has proposed five major projects in the southern province of Binh Phuoc, in the fields of industrial production and urban area, golf course and high-tech agricultural production zone developments.

Industries - Thu, May 29, 2025 | 12:02 pm GMT+7

2024 cyberattack 'a blessing in disguise' for Vietnam's leading broker VNDirect: chairwoman

2024 cyberattack 'a blessing in disguise' for Vietnam's leading broker VNDirect: chairwoman

The cybersecurity breach that major Vietnamese brokerage VNDirect Securities encountered in 2024 was "an unfortunate incident, but also a lucky chance", chairwoman Pham Minh Huong said on Wednesday.

Finance - Thu, May 29, 2025 | 9:48 am GMT+7

Vietnam prioritizes smart, green seaport projects: Deputy PM

Vietnam prioritizes smart, green seaport projects: Deputy PM

Vietnam encourages smart and green seaport investments, as technical barriers related to CO2 emissions and CO2 taxes begin to be tightened up globally.

Infrastructure - Wed, May 28, 2025 | 10:07 pm GMT+7

New Zealand, Vietnam expand timber trade partnership

New Zealand, Vietnam expand timber trade partnership

New Zealand Forestry and Trade Minister Todd McClay on Tuesday unveiled a new bilateral agreement with Vietnam designed to boost timber exports and remove potential trade barriers in the two countries' forestry sectors.

Companies - Wed, May 28, 2025 | 8:53 pm GMT+7