Key infrastructure projects face site clearance issues, material shortages

By Hai Yen, Trong Hieu
Thu, May 2, 2024 | 3:35 pm GMT+7

Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.

National key projects gradually built up

The Long Thanh airport project in the southern province of Dong Nai has an estimated investment of VND336.63 trillion ($16.06 billion), with its first phase requiring VND114.45 trillion ($5.45 billion).

The first phase of the three-stage project involves the construction of a runway and passenger terminal, along with auxiliary facilities, capable of handling 25 million passengers per year. A cargo terminal is designed to have an annual capacity of 1.2 million tons of freight. The first phase is expected to come on stream by 2025 at the latest.

The second phase will cover an additional open runway and one passenger terminal, aiming to raise the airport’s yearly capacity to 50 million passengers. Additionally, a cargo terminal capable of handling 1.5 million tons of cargo per year will be supplemented.

For the third phase, further enhancements will be made to lift the project’s capacity to 100 million passengers and five million tons of cargo annually.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

The project has largely remained on schedule thus far, but the Airports Corporation of Vietnam (ACV) has reported some hurdles to site clearance.

Specifically, while the site handover for a traffic system connecting Road No.1 has been 99% completed, an issue related to site clearance persists at the intersection between Road No.1 and the Bien Hoa-Vung Tau Expressway project. Additionally, there is a similar hitch to the section extending from Km0+880 to Km0+944 of the Bung Mon bridge.

Those obstacles have delayed land increment reinforcement, posing a risk to the progress of soft roadbed soil treatment

Additionally, although over 89% of the site has been allocated for the construction of road No.2, ACV noted that approximately 80% of the area is qualified for development, and some locations have still not been fully cleared for construction.

For example, the non-cleared location at the intersection between Road No.2 and the Ho Chi Minh City-Long Thanh-Dau Giay Expressway has impacted the progress of an overpass spanning the expressway’s T12-to-T22 section, which may take 12 months to construct.

Additionally, certain existing technical issues, particularly power lines, along Road No.2 have yet to be cleared or relocated, impacting both safety assurance and construction progress.

Therefore, ACV proposed the People’s Committee of Dong Nai province to ask relevant units to accelerate site clearance for a complete handover to ensure the project runs on schedule.

In early February, Prime Minister Pham Minh Chinh inspected the Long Thanh airport project. During his visit, the PM emphasized that while previous years had laid the foundation for the airport, this year marks a period of acceleration, and 2025 is slated as the breakthrough year.

He also stressed the urgency of completing the airport project within the first half of 2026. Drawing from past experiences, Chinh asked for the timeline to be adjusted with a view to shortening the progress by three-six months to offset any delays.

As a key national project, Long Thanh airport will significantly enhance flight routes, bolster Vietnam’s economic links with countries in ASEAN and the world, and alleviate congestion at Tan Son Nhat International Airport, which is located in the adjacent metropolis of Ho Chi Minh City.

It is expected to serve as a pivotal transit hub for Asia and beyond by 2030. However, site clearance setbacks have made investors and contractors fret over deadlines committed to by the government.

North-South Expressway component projects likely to miss 2025 completion deadline

After one year of construction, the component projects of the North-South Expressway’s eastern section in the 2021-2025 period are facing many challenges related to site clearance and material shortages. If these issues are not addressed promptly, the Ministry of Transport (MoT) acknowledges that it will be difficult to complete the component projects by 2025 as required by the government and National Assembly.

Notably, the 49-km Dien Chau-Bai Vot Expressway project, kicked off in May 2021 with a total investment of VND11.15 trillion ($446.2 million), is designed to connect Nghe An and Ha Tinh provinces, both in the central region.

A 30-kilometer segment of the project, extending from the intersection of National Highway No.7 (Dien Chau district) to the intersection of National Highway No.46B (Hung Nguyen district), was inaugurated on April 28, shortening the travel time between Hanoi and Nghe An’s Vinh town from five and a half hours to three hours by car.

However, the remaining 19 kilometers from National Highway No.46B to Bai Vot district (Ha Tinh province), characterized by soft soil, requires additional time for ground reinforcement and will be inaugurated this September.

Similarly, the Cam Lam-Vinh Hao Expressway, spanning the central provinces of Khanh Hoa, Ninh Thuan, and Binh Thuan, was opened to traffic on April 26 after 28 months of construction. The 78.5-km route, with a total investment of VND3.92 trillion ($352.14 million), slashes the travel time from Ho Chi Minh City to Khanh Hoa’s Nha Trang town from eight hours to five hours by car.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

Regarding the 12 component projects of the North-South Expressway in 2021-2025, the MoT said that their investors and contractors had basically adhered to the timetable. However, the Can Tho-Hau Giang and Hau Giang-Ca Mau sections, both in the south, are lagging behind schedule due to a shortage of sand.

Specifically, for component projects spanning from Ha Tinh to Khanh Hoa provinces, both in central Vietnam, contractors have exploited 14 out of 17 sand quarries, meeting about 91% of the demand. The remaining three quarries, located along the Quang Ngai province-Hoai Nhon town section, remain unexploited due to disagreements with owners of mining land over compensation prices. Besides, 43 out of 55 sand quarries scattered all over the Ha Tinh-Khanh Hoa section are reported to have satisfied around 77% of the demand.

For the Can Tho-Ca Mau Expressway project, the Mekong Delta provinces of An Giang, Dong Thap, and Vinh Long have arranged a total supply of 16.02 million cubic meters of sand. Meanwhile, a source for 2.98 million m3 of sand has not yet been determined (one million m3 for An Giang and 1.98 million m3 for Vinh Long). Of the total supply, nine million m3 of sand is being exploited, and the remaining seven million is awaiting procedures for exploitation.

Contractors have delivered 2.7 million m3 of sand to the construction site, comprising 400,000 m3 for An Giang, 2.3 million m3 from Dong Thap, and 4,400 m3 for Vinh Long. The sand mining capacity in the Mekong Delta region remains considerably low, averaging only 18,000 m3/day. This falls short of the project’s daily demand of 50,000 m3, primarily due to restrictions on capacity and exploitation means/hours.

In terms of site clearance, the ministry assessed that if the site was not handed over for construction before April 30, the component projects might slip behind the scheduled completion year of 2025.

In addition, unless the amendments of Resolution 273 on changing the use purpose of forest, forest land, and rice farming land cultivated for two crops and beyond are submitted to the National Assembly’s Standing Committee for approval in April, the progress of the component projects of the North-South Expressway in 2021-2025 will be greatly impacted.

Viewing site clearance as a principal task, the MoT has requested local authorities to address hitches for these projects.

Comments (0)
  • Read More
Japanese retailer Aeon to debut another northern Vietnam shopping mall by end-2026

Japanese retailer Aeon to debut another northern Vietnam shopping mall by end-2026

Japanese-backed Aeonmall Vietnam is ramping up construction on its Aeon Mall Ha Long project in Quang Ninh province, home to Ha Long Bay, with an aim to open it to the public by end-2026.

Industries - Tue, September 16, 2025 | 3:54 pm GMT+7

Hanoi terminates Vinaxuki auto plant project, repurposes land for commercial complex

Hanoi terminates Vinaxuki auto plant project, repurposes land for commercial complex

A long-stalled automotive manufacturing project by Xuan Kien Auto JSC (Vinaxuki) has been officially terminated by Hanoi authorities, and the reclaimed land in Phuc Thinh commune will be repurposed for a new commercial and service complex.

Industries - Tue, September 16, 2025 | 2:44 pm GMT+7

Central Vietnam province reviews investment proposal for thermal power project after Thai EGATi pullout

Central Vietnam province reviews investment proposal for thermal power project after Thai EGATi pullout

Authorities in the central province of Quang Tri are evaluating a proposal from Power Generation JSC 1 (EVNGENCO 1), a subsidiary of state utility Vietnam Electricity (EVN), to take over the Quang Tri thermal power plant project, following the withdrawal of Thai investor EGATi.

Energy - Tue, September 16, 2025 | 1:44 pm GMT+7

Amata to sell stakes worth $46 mln in Vietnam units to Novaland-tied buyers

Amata to sell stakes worth $46 mln in Vietnam units to Novaland-tied buyers

Amata VN, the Vietnam arm of Thailand’s leading industrial park developer Amata, has approved a plan for its subsidiary Amata City Long Thanh Urban JSC (ACLT) to sell its remaining 51% stakes in two entities to local developer Novaland-linked buyers.

Real Estate - Tue, September 16, 2025 | 12:19 pm GMT+7

Vietnam already meets FTSE's criteria for stock market status upgrade: Finance Minister

Vietnam already meets FTSE's criteria for stock market status upgrade: Finance Minister

Vietnam has fulfilled the criteria for a stock market status upgrade by FTSE Russell through reforms aimed at facilitating foreign investment inflows into its market, said Minister of Finance Nguyen Van Thang.

Economy - Tue, September 16, 2025 | 9:36 am GMT+7

Banks should be allowed to distribute, invest in mutual fund certificates: Vietnam's finance ministry

Banks should be allowed to distribute, invest in mutual fund certificates: Vietnam's finance ministry

The Ministry of Finance is proposing a key reform that would allow commercial banks to invest in and distribute mutual fund certificates, as part of a broader plan to restructure the investor base and foster the development of Vietnam’s fund management industry.

Finance - Tue, September 16, 2025 | 8:00 am GMT+7

E-commerce boom a major driver of Vietnam's packaging paper industry growth

E-commerce boom a major driver of Vietnam's packaging paper industry growth

Vietnam's paper packaging industry is entering a period of strong growth, with an average annual growth rate forecasted at 10% until 2030.

Companies - Mon, September 15, 2025 | 10:20 pm GMT+7

Vietnam needs support from UK in developing international financial center: Deputy PM

Vietnam needs support from UK in developing international financial center: Deputy PM

Permanent Deputy Prime Minister Nguyen Hoa Binh has called on the UK and the City of London to continue supporting and accompanying Vietnam in promoting and introducing its international financial center (IFC).

Finance - Mon, September 15, 2025 | 10:12 pm GMT+7

Vietnam enforces 8% capital adequacy ratio for banks from Sept 15

Vietnam enforces 8% capital adequacy ratio for banks from Sept 15

Commercial banks and foreign bank branches in Vietnam must maintain a minimum capital adequacy ratio (CAR) of 8%, including at least 4.5% in Tier 1 core capital and 6% in Tier 1 capital, starting from September 15.

Banking - Mon, September 15, 2025 | 10:04 pm GMT+7

Tool for wood traceability management debuts in Vietnam

Tool for wood traceability management debuts in Vietnam

The Vn-WoodID application has been officially launched in Vietnam, becoming a key tool contributing to wood traceability.

Companies - Mon, September 15, 2025 | 10:00 pm GMT+7

Sun Group, US Embassy foster aviation-hospitality cooperation

Sun Group, US Embassy foster aviation-hospitality cooperation

Sun Group, in collaboration with the US Embassy in Vietnam, hosted the US – Vietnam Aviation Partnership Roundtable on September 12, bringing together 15 leading American corporations in aviation, technology, and financial services, opening up opportunities to position Phu Quoc as a new aviation and tourism hub in the region.

Companies - Mon, September 15, 2025 | 9:54 pm GMT+7

Vietnam tops Thai giant SCG’s overseas markets with 9% revenue contribution in H1

Vietnam tops Thai giant SCG’s overseas markets with 9% revenue contribution in H1

Vietnam remained the largest overseas market for Thailand’s Siam Cement Group (SCG) in the first half of 2025, contributing 9% of consolidated sales.

Companies - Mon, September 15, 2025 | 8:10 pm GMT+7

Central Vietnam to have new airport Mang Den

Central Vietnam to have new airport Mang Den

Procedures to adjust Vietnam's airport system planning, including the addition of Mang Den Airport in central Vietnam, are being proceeded, according to the Ministry of Construction.

Infrastructure - Mon, September 15, 2025 | 5:16 pm GMT+7

Vietnam's government seeks to position country as 'regulated hub for digital assets in Asia': Dragon Capital

Vietnam's government seeks to position country as 'regulated hub for digital assets in Asia': Dragon Capital

The Vietnamese Government has advanced the regulation of digital assets, with a resolution launching a five-year pilot framework for issuance and trading. This framework signals the Government’s intent to position the country as a regulated hub for digital assets in Asia, which could attract new capital inflows, write Dragon Capital analysts.

Economy - Mon, September 15, 2025 | 2:20 pm GMT+7

Agribank introduces sizable $4.17 bln preferential credit package

Agribank introduces sizable $4.17 bln preferential credit package

Right from the beginning of 2025, Agribank launched a substantial preferential credit package worth VND110 trillion ($4.17 billion) to support individual customers.

Companies - Mon, September 15, 2025 | 1:32 pm GMT+7

'Precious space' in Vietnam's monetary policy

'Precious space' in Vietnam's monetary policy

The Federal Reserve's continued cuts in 2025, with the most recent in September, are considered a valuable policy "space" for the State Bank of Vietnam (SBV) to maintain low interest rates to support growth without having to worry too much about exchange rates.

Economy - Mon, September 15, 2025 | 10:15 am GMT+7