Key infrastructure projects face site clearance issues, material shortages
Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.
National key projects gradually built up
The Long Thanh airport project in the southern province of Dong Nai has an estimated investment of VND336.63 trillion ($16.06 billion), with its first phase requiring VND114.45 trillion ($5.45 billion).
The first phase of the three-stage project involves the construction of a runway and passenger terminal, along with auxiliary facilities, capable of handling 25 million passengers per year. A cargo terminal is designed to have an annual capacity of 1.2 million tons of freight. The first phase is expected to come on stream by 2025 at the latest.
The second phase will cover an additional open runway and one passenger terminal, aiming to raise the airport’s yearly capacity to 50 million passengers. Additionally, a cargo terminal capable of handling 1.5 million tons of cargo per year will be supplemented.
For the third phase, further enhancements will be made to lift the project’s capacity to 100 million passengers and five million tons of cargo annually.
An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.
The project has largely remained on schedule thus far, but the Airports Corporation of Vietnam (ACV) has reported some hurdles to site clearance.
Specifically, while the site handover for a traffic system connecting Road No.1 has been 99% completed, an issue related to site clearance persists at the intersection between Road No.1 and the Bien Hoa-Vung Tau Expressway project. Additionally, there is a similar hitch to the section extending from Km0+880 to Km0+944 of the Bung Mon bridge.
Those obstacles have delayed land increment reinforcement, posing a risk to the progress of soft roadbed soil treatment
Additionally, although over 89% of the site has been allocated for the construction of road No.2, ACV noted that approximately 80% of the area is qualified for development, and some locations have still not been fully cleared for construction.
For example, the non-cleared location at the intersection between Road No.2 and the Ho Chi Minh City-Long Thanh-Dau Giay Expressway has impacted the progress of an overpass spanning the expressway’s T12-to-T22 section, which may take 12 months to construct.
Additionally, certain existing technical issues, particularly power lines, along Road No.2 have yet to be cleared or relocated, impacting both safety assurance and construction progress.
Therefore, ACV proposed the People’s Committee of Dong Nai province to ask relevant units to accelerate site clearance for a complete handover to ensure the project runs on schedule.
In early February, Prime Minister Pham Minh Chinh inspected the Long Thanh airport project. During his visit, the PM emphasized that while previous years had laid the foundation for the airport, this year marks a period of acceleration, and 2025 is slated as the breakthrough year.
He also stressed the urgency of completing the airport project within the first half of 2026. Drawing from past experiences, Chinh asked for the timeline to be adjusted with a view to shortening the progress by three-six months to offset any delays.
As a key national project, Long Thanh airport will significantly enhance flight routes, bolster Vietnam’s economic links with countries in ASEAN and the world, and alleviate congestion at Tan Son Nhat International Airport, which is located in the adjacent metropolis of Ho Chi Minh City.
It is expected to serve as a pivotal transit hub for Asia and beyond by 2030. However, site clearance setbacks have made investors and contractors fret over deadlines committed to by the government.
North-South Expressway component projects likely to miss 2025 completion deadline
After one year of construction, the component projects of the North-South Expressway’s eastern section in the 2021-2025 period are facing many challenges related to site clearance and material shortages. If these issues are not addressed promptly, the Ministry of Transport (MoT) acknowledges that it will be difficult to complete the component projects by 2025 as required by the government and National Assembly.
Notably, the 49-km Dien Chau-Bai Vot Expressway project, kicked off in May 2021 with a total investment of VND11.15 trillion ($446.2 million), is designed to connect Nghe An and Ha Tinh provinces, both in the central region.
A 30-kilometer segment of the project, extending from the intersection of National Highway No.7 (Dien Chau district) to the intersection of National Highway No.46B (Hung Nguyen district), was inaugurated on April 28, shortening the travel time between Hanoi and Nghe An’s Vinh town from five and a half hours to three hours by car.
However, the remaining 19 kilometers from National Highway No.46B to Bai Vot district (Ha Tinh province), characterized by soft soil, requires additional time for ground reinforcement and will be inaugurated this September.
Similarly, the Cam Lam-Vinh Hao Expressway, spanning the central provinces of Khanh Hoa, Ninh Thuan, and Binh Thuan, was opened to traffic on April 26 after 28 months of construction. The 78.5-km route, with a total investment of VND3.92 trillion ($352.14 million), slashes the travel time from Ho Chi Minh City to Khanh Hoa’s Nha Trang town from eight hours to five hours by car.
The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.
Regarding the 12 component projects of the North-South Expressway in 2021-2025, the MoT said that their investors and contractors had basically adhered to the timetable. However, the Can Tho-Hau Giang and Hau Giang-Ca Mau sections, both in the south, are lagging behind schedule due to a shortage of sand.
Specifically, for component projects spanning from Ha Tinh to Khanh Hoa provinces, both in central Vietnam, contractors have exploited 14 out of 17 sand quarries, meeting about 91% of the demand. The remaining three quarries, located along the Quang Ngai province-Hoai Nhon town section, remain unexploited due to disagreements with owners of mining land over compensation prices. Besides, 43 out of 55 sand quarries scattered all over the Ha Tinh-Khanh Hoa section are reported to have satisfied around 77% of the demand.
For the Can Tho-Ca Mau Expressway project, the Mekong Delta provinces of An Giang, Dong Thap, and Vinh Long have arranged a total supply of 16.02 million cubic meters of sand. Meanwhile, a source for 2.98 million m3 of sand has not yet been determined (one million m3 for An Giang and 1.98 million m3 for Vinh Long). Of the total supply, nine million m3 of sand is being exploited, and the remaining seven million is awaiting procedures for exploitation.
Contractors have delivered 2.7 million m3 of sand to the construction site, comprising 400,000 m3 for An Giang, 2.3 million m3 from Dong Thap, and 4,400 m3 for Vinh Long. The sand mining capacity in the Mekong Delta region remains considerably low, averaging only 18,000 m3/day. This falls short of the project’s daily demand of 50,000 m3, primarily due to restrictions on capacity and exploitation means/hours.
In terms of site clearance, the ministry assessed that if the site was not handed over for construction before April 30, the component projects might slip behind the scheduled completion year of 2025.
In addition, unless the amendments of Resolution 273 on changing the use purpose of forest, forest land, and rice farming land cultivated for two crops and beyond are submitted to the National Assembly’s Standing Committee for approval in April, the progress of the component projects of the North-South Expressway in 2021-2025 will be greatly impacted.
Viewing site clearance as a principal task, the MoT has requested local authorities to address hitches for these projects.
- Read More
Japanese products dominate Vietnamese consumer trust, but younger shoppers rewriting rules
Japanese products continue to enjoy the highest level of trust among Vietnamese consumers, reinforcing the country’s position as the benchmark for quality and reliability in one of Southeast Asia’s fastest-growing consumer markets, according to a new survey by market research firm Q&Me.
Economy - Mon, June 15, 2026 | 6:48 pm GMT+7
VinEnergo ramps up renewable energy push with 4 new subsidiaries
VinEnergo, the energy arm of Vietnamese conglomerate Vingroup, has accelerated its expansion into the power sector, establishing four new subsidiaries within a week as it builds a growing portfolio of renewable energy and infrastructure projects across Vietnam.
Companies - Mon, June 15, 2026 | 4:52 pm GMT+7
Thaco deepens ties with Hyundai Rotem to localize railway manufacturing in Vietnam
Vietnamese conglomerate Thaco and South Korea’s Hyundai Rotem have signed a detailed technology transfer and localization agreement for railway rolling stock production.
Industries - Mon, June 15, 2026 | 4:01 pm GMT+7
UOB Vietnam appoints Pham Hong Hai as deputy country CEO
Singapore's United Overseas Bank (Vietnam) Limited on Monday appointed Pham Hong Hai, former CEO of HSBC Vietnam and later Vietnamese bank OCB, as deputy country CEO, effective immediately.
Banking - Mon, June 15, 2026 | 2:26 pm GMT+7
Shinhan Bank Vietnam launches AI translation desk, strengthening customer experience, digital innovation
Shinhan Bank Vietnam has officially launched AI Translation Desk, an AI-powered interpretation solution designed to help foreign customers communicate more easily while using banking services in Vietnam.
Banking - Mon, June 15, 2026 | 12:03 pm GMT+7
FDI listings a missing piece in Vietnam's stock market development
As Vietnam's stock market moves closer to its long-awaited upgrade to secondary emerging market status and seeks to attract higher-quality capital, allowing more foreign-invested companies to list on domestic exchanges could broaden the pool of investable assets and support the next phase of capital market development.
Finance - Mon, June 15, 2026 | 11:14 am GMT+7
Chinese robot 'eyes' manufacturer builds 10-hectare factory in northern Vietnam
Orbbec Inc., a Chinese company specializing in 3D vision sensors and robotic hardware, is building an over-10-hectare manufacturing center in the northern province of Bac Ninh to serve international markets.
Industries - Mon, June 15, 2026 | 8:00 am GMT+7
Long Thanh airport project faces shortage of 2,000 workers
The Long Thanh International Airport project in the southern province of Dong Nai is still short nearly 2,000 workers compared to actual requirements during its final acceleration phase.
Infrastructure - Sun, June 14, 2026 | 6:08 pm GMT+7
Nghi Son Refinery and Petrochemical Complex turns profitable in Q1 on full-capacity operations
Operating at full capacity, the Nghi Son Refinery and Petrochemical Complex in Vietnam's central province of Thanh Hoa reported its first profit in Q1/2026, marking a significant turnaround after years of losses.
Economy - Sun, June 14, 2026 | 2:45 pm GMT+7
50 years of Gamuda Berhad and its urban development journey in Vietnam
Celebrating 50 years of establishment and growth, Gamuda Berhad – one of Malaysia’s leading infrastructure and urban development groups – has evolved from an infrastructure specialist into an integrated urban developer with a growing presence across Asia.
Real Estate - Sun, June 14, 2026 | 11:21 am GMT+7
Industrials, technology top Vietnamese sectors in M&A transaction volume
Vietnam’s M&A market recorded 24 transactions in May, with industrials, technology and healthcare sectors being the most active sectors in terms of transaction volume, writes Grant Thornton analysts.
Consulting - Sun, June 14, 2026 | 9:00 am GMT+7
Top Vietnamese garment maker Vinatex's H1 profit rises 14%, weak order visibility clouds outlook
Vietnam National Textile and Garment Group (UPCoM: VGT) reported consolidated profit growth of 14.4% in the first half of 2026, driven by a strong recovery in its yarn business, even as weakening global demand and uncertainty over U.S. trade policy cast a shadow over the sector’s outlook.
Companies - Sun, June 14, 2026 | 8:00 am GMT+7
Gamuda Land Vietnam recognized among Top 10 Enterprises Pioneering Green Transformation 2025-2026
Gamuda Land Vietnam has been recognized as one of the “Top 10 Enterprises Pioneering Green Transformation 2025-2026” at the 25th Golden Dragon Awards.
Companies - Sat, June 13, 2026 | 7:45 pm GMT+7
T&T pushes ahead with $97 mln industrial park project, eyes new urban area projects in northern Vietnam
Vietnamese conglomerate T&T Group is seeking to accelerate five projects in Bac Ninh while proposing two new developments in this northern province.
Infrastructure - Sat, June 13, 2026 | 7:09 pm GMT+7
VinFast guns for 300,000 EV deliveries in 2026, spins off manufacturing operations
VinFast, the EV arm of Vietnamese conglomerate Vingroup (HoSE: VIC) targets at least 300,000 electric vehicle deliveries globally this year, up 52% year-on-year, while pursuing a restructuring plan aimed at improving capital efficiency, according to a report by Vietcap Securities.
Companies - Sat, June 13, 2026 | 3:07 pm GMT+7
Vietnam economy resilience amid cost pressures, external strains: UOB
The VND has stabilized in recent weeks, trading in a range of VND26,291-26,372 per U.S. dollars in April-May, well within the State Bank of Vietnam’s ±5% band. In a report released on Friday, UOB analysts say on balance, they retain a gradual depreciation bias for the USD/VND, with updated forecasts of 26,500 in Q3/2026, 26,400 in Q4/2026, 26,300 in Q1/2027, and 26,100 in Q2/2027.
Consulting - Sat, June 13, 2026 | 11:49 am GMT+7




















