Key infrastructure projects face site clearance issues, material shortages

By Hai Yen, Trong Hieu
Thu, May 2, 2024 | 3:35 pm GMT+7

Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.

National key projects gradually built up

The Long Thanh airport project in the southern province of Dong Nai has an estimated investment of VND336.63 trillion ($16.06 billion), with its first phase requiring VND114.45 trillion ($5.45 billion).

The first phase of the three-stage project involves the construction of a runway and passenger terminal, along with auxiliary facilities, capable of handling 25 million passengers per year. A cargo terminal is designed to have an annual capacity of 1.2 million tons of freight. The first phase is expected to come on stream by 2025 at the latest.

The second phase will cover an additional open runway and one passenger terminal, aiming to raise the airport’s yearly capacity to 50 million passengers. Additionally, a cargo terminal capable of handling 1.5 million tons of cargo per year will be supplemented.

For the third phase, further enhancements will be made to lift the project’s capacity to 100 million passengers and five million tons of cargo annually.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

The project has largely remained on schedule thus far, but the Airports Corporation of Vietnam (ACV) has reported some hurdles to site clearance.

Specifically, while the site handover for a traffic system connecting Road No.1 has been 99% completed, an issue related to site clearance persists at the intersection between Road No.1 and the Bien Hoa-Vung Tau Expressway project. Additionally, there is a similar hitch to the section extending from Km0+880 to Km0+944 of the Bung Mon bridge.

Those obstacles have delayed land increment reinforcement, posing a risk to the progress of soft roadbed soil treatment

Additionally, although over 89% of the site has been allocated for the construction of road No.2, ACV noted that approximately 80% of the area is qualified for development, and some locations have still not been fully cleared for construction.

For example, the non-cleared location at the intersection between Road No.2 and the Ho Chi Minh City-Long Thanh-Dau Giay Expressway has impacted the progress of an overpass spanning the expressway’s T12-to-T22 section, which may take 12 months to construct.

Additionally, certain existing technical issues, particularly power lines, along Road No.2 have yet to be cleared or relocated, impacting both safety assurance and construction progress.

Therefore, ACV proposed the People’s Committee of Dong Nai province to ask relevant units to accelerate site clearance for a complete handover to ensure the project runs on schedule.

In early February, Prime Minister Pham Minh Chinh inspected the Long Thanh airport project. During his visit, the PM emphasized that while previous years had laid the foundation for the airport, this year marks a period of acceleration, and 2025 is slated as the breakthrough year.

He also stressed the urgency of completing the airport project within the first half of 2026. Drawing from past experiences, Chinh asked for the timeline to be adjusted with a view to shortening the progress by three-six months to offset any delays.

As a key national project, Long Thanh airport will significantly enhance flight routes, bolster Vietnam’s economic links with countries in ASEAN and the world, and alleviate congestion at Tan Son Nhat International Airport, which is located in the adjacent metropolis of Ho Chi Minh City.

It is expected to serve as a pivotal transit hub for Asia and beyond by 2030. However, site clearance setbacks have made investors and contractors fret over deadlines committed to by the government.

North-South Expressway component projects likely to miss 2025 completion deadline

After one year of construction, the component projects of the North-South Expressway’s eastern section in the 2021-2025 period are facing many challenges related to site clearance and material shortages. If these issues are not addressed promptly, the Ministry of Transport (MoT) acknowledges that it will be difficult to complete the component projects by 2025 as required by the government and National Assembly.

Notably, the 49-km Dien Chau-Bai Vot Expressway project, kicked off in May 2021 with a total investment of VND11.15 trillion ($446.2 million), is designed to connect Nghe An and Ha Tinh provinces, both in the central region.

A 30-kilometer segment of the project, extending from the intersection of National Highway No.7 (Dien Chau district) to the intersection of National Highway No.46B (Hung Nguyen district), was inaugurated on April 28, shortening the travel time between Hanoi and Nghe An’s Vinh town from five and a half hours to three hours by car.

However, the remaining 19 kilometers from National Highway No.46B to Bai Vot district (Ha Tinh province), characterized by soft soil, requires additional time for ground reinforcement and will be inaugurated this September.

Similarly, the Cam Lam-Vinh Hao Expressway, spanning the central provinces of Khanh Hoa, Ninh Thuan, and Binh Thuan, was opened to traffic on April 26 after 28 months of construction. The 78.5-km route, with a total investment of VND3.92 trillion ($352.14 million), slashes the travel time from Ho Chi Minh City to Khanh Hoa’s Nha Trang town from eight hours to five hours by car.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

Regarding the 12 component projects of the North-South Expressway in 2021-2025, the MoT said that their investors and contractors had basically adhered to the timetable. However, the Can Tho-Hau Giang and Hau Giang-Ca Mau sections, both in the south, are lagging behind schedule due to a shortage of sand.

Specifically, for component projects spanning from Ha Tinh to Khanh Hoa provinces, both in central Vietnam, contractors have exploited 14 out of 17 sand quarries, meeting about 91% of the demand. The remaining three quarries, located along the Quang Ngai province-Hoai Nhon town section, remain unexploited due to disagreements with owners of mining land over compensation prices. Besides, 43 out of 55 sand quarries scattered all over the Ha Tinh-Khanh Hoa section are reported to have satisfied around 77% of the demand.

For the Can Tho-Ca Mau Expressway project, the Mekong Delta provinces of An Giang, Dong Thap, and Vinh Long have arranged a total supply of 16.02 million cubic meters of sand. Meanwhile, a source for 2.98 million m3 of sand has not yet been determined (one million m3 for An Giang and 1.98 million m3 for Vinh Long). Of the total supply, nine million m3 of sand is being exploited, and the remaining seven million is awaiting procedures for exploitation.

Contractors have delivered 2.7 million m3 of sand to the construction site, comprising 400,000 m3 for An Giang, 2.3 million m3 from Dong Thap, and 4,400 m3 for Vinh Long. The sand mining capacity in the Mekong Delta region remains considerably low, averaging only 18,000 m3/day. This falls short of the project’s daily demand of 50,000 m3, primarily due to restrictions on capacity and exploitation means/hours.

In terms of site clearance, the ministry assessed that if the site was not handed over for construction before April 30, the component projects might slip behind the scheduled completion year of 2025.

In addition, unless the amendments of Resolution 273 on changing the use purpose of forest, forest land, and rice farming land cultivated for two crops and beyond are submitted to the National Assembly’s Standing Committee for approval in April, the progress of the component projects of the North-South Expressway in 2021-2025 will be greatly impacted.

Viewing site clearance as a principal task, the MoT has requested local authorities to address hitches for these projects.

Comments (0)
  • Read More
Coca-Cola Beverages Vietnam loses lawsuit against local tax authority

Coca-Cola Beverages Vietnam loses lawsuit against local tax authority

The Ho Chi Minh City People's Court on Thursday dismissed a lawsuit filed by Coca-Cola Beverages Vietnam against the Ministry of Finance's Department of Taxation, thereby upholding the department's decision to collect back taxes and impose a fine of over VND821 billion ($31.14 million) in total.

Finance - Sat, November 29, 2025 | 2:27 pm GMT+7

Honda Vietnam rejects information Honda Mobilityland plans 600-ha tourism, entertainment, sports complex in southern Vietnam

Honda Vietnam rejects information Honda Mobilityland plans 600-ha tourism, entertainment, sports complex in southern Vietnam

Honda Vietnam on Friday rejected the information that Honda Mobilityland Corporation, a subsidiary of Japan’s Honda Motor Co., plans to build an international circuit in Tay Ninh province, towards developing a 600-hectare tourism, entertainment, and sports complex there.

Industries - Sat, November 29, 2025 | 10:23 am GMT+7

Vietnam's largest tungsten mine has updated planning okayed

Vietnam's largest tungsten mine has updated planning okayed

Vietnam’s Nui Phao mine, one of the world’s largest tungsten deposits outside China, has had its updated planning approved under a decision signed by Deputy Prime Minister Tran Hong Ha.

Economy - Sat, November 29, 2025 | 9:34 am GMT+7

Foreign-backed Arque Degi to build $322 mln floating tourism-urban projects in central Vietnam

Foreign-backed Arque Degi to build $322 mln floating tourism-urban projects in central Vietnam

Authorities in Gia Lai province have granted an investment certificate to Arque Degi JSC to develop three floating tourism-urban projects worth a combined VND8.5 trillion ($322.42 million) in the De Gi lagoon area.

Real Estate - Sat, November 29, 2025 | 8:00 am GMT+7

Indonesia eyes trilateral data-center tie-up with Singapore, Malaysia

Indonesia eyes trilateral data-center tie-up with Singapore, Malaysia

Indonesia is in talks with Singapore and Malaysia to develop a cross-border data-center network linked to its Green Super Grid.

Southeast Asia - Fri, November 28, 2025 | 9:57 pm GMT+7

Malaysia’s export growth expected to slow in 2026

Malaysia’s export growth expected to slow in 2026

Despite Malaysia’s trade growth in October 2025 surpassing expectations, with both exports and imports reaching record levels, economists warned that the country’s export expansion may slow in 2026.

Southeast Asia - Fri, November 28, 2025 | 9:53 pm GMT+7

Singapore promotes methanol use for bunkering

Singapore promotes methanol use for bunkering

The Maritime and Port Authority of Singapore (MPA) will issue licences to supply methanol as marine fuel in the Port of Singapore from January 1, 2026, following the Call for Applications launched in March 2025.

Southeast Asia - Fri, November 28, 2025 | 9:46 pm GMT+7

Vietnam's tour operator Vietravel announces full exit from Vietravel Airlines

Vietnam's tour operator Vietravel announces full exit from Vietravel Airlines

Vietravel, one of Vietnam’s largest tour operators, will divest its entire stake in Vietravel Airlines by year-end, drawing a close to its turbulent venture into aviation during five years.

Travel - Fri, November 28, 2025 | 9:22 pm GMT+7

VinSpeed, Thaco vie for investment role in North-South high-speed railway

VinSpeed, Thaco vie for investment role in North-South high-speed railway

Several major Vietnamese companies, including Vingroup subsidiary VinSpeed and automaker Thaco, are vying for a role in Vietnam’s gigantic North-South high-speed railway project.

Infrastructure - Fri, November 28, 2025 | 5:14 pm GMT+7

Finnish fund PYN Elite raises VN-Index forecast to 3,200 points

Finnish fund PYN Elite raises VN-Index forecast to 3,200 points

PYN Elite (Finland), one of the largest foreign funds in the Vietnamese stock market, has revised up its forecast for the benchmark VN-Index to 3,200 points, much higher than the 1,690.99 recorded on Friday.

Finance - Fri, November 28, 2025 | 4:49 pm GMT+7

Mind the gap

Mind the gap

Without stronger digital and physical networks, global productivity will falter at precisely the moment the world needs new engines of growth, writes Benjamin Hung, president, International, Standard Chartered.

Consulting - Fri, November 28, 2025 | 3:49 pm GMT+7

Alliance claiming $100 bln investment for trans-Vietnam high-speed railway 'uncontactable'

Alliance claiming $100 bln investment for trans-Vietnam high-speed railway 'uncontactable'

An alliance between Mekolor, a relatively unknown Vietnamese company, and American entity Great USA, which claimed it could mobilize $100 billion for the North-South high-speed railway project, could not be contacted, said standing Deputy Prime Minister Nguyen Hoa Binh.

Infrastructure - Fri, November 28, 2025 | 3:19 pm GMT+7

Mitsui eyes new opportunites in Vietnam's energy sector, projects related to carbon emission reduction

Mitsui eyes new opportunites in Vietnam's energy sector, projects related to carbon emission reduction

Mitsui & Co., Ltd. plans to expand its investment in Vietnam in the energy sector and projects related to carbon emission reduction, president and CEO Kenichi Hori told Prime Minister Pham Minh Chinh at a Thursday meeting in Hanoi.

Industries - Fri, November 28, 2025 | 2:39 pm GMT+7

Russian heavyweight Zarubezhneft seeks to build energy center in Vietnam

Russian heavyweight Zarubezhneft seeks to build energy center in Vietnam

Zarubezhneft, a wholly state-owned oil & gas group of Russia, wants to develop an energy center in Vietnam, as it seeks to expand into other fields including energy and minerals.

Energy - Fri, November 28, 2025 | 1:08 pm GMT+7

Carlsberg Vietnam accelerates its path toward net-zero emission in production by 2028 with stronger renewable-energy commitments

Carlsberg Vietnam accelerates its path toward net-zero emission in production by 2028 with stronger renewable-energy commitments

As Vietnam advances toward its 2050 net-zero vision, businesses are expected to play a decisive role in enabling the country’s green transition. At the Green Economy Forum 2025, Carlsberg Vietnam shared how a long-standing FDI enterprise is reshaping its operations and energy strategy to align with Vietnam’s sustainability goals.

Companies - Fri, November 28, 2025 | 11:52 am GMT+7

PV Power says profit may fall in 2026 despite higher output due to extreme weather

PV Power says profit may fall in 2026 despite higher output due to extreme weather

PV Power (HoSE: POW), a subsidiary of state-owned energy giant Petrovietnam, expects electricity output to rise next year, but says profit may decline from this year’s strong results due to increasingly erratic weather conditions.

Companies - Fri, November 28, 2025 | 9:00 am GMT+7