Key infrastructure projects face site clearance issues, material shortages

By Hai Yen, Trong Hieu
Thu, May 2, 2024 | 3:35 pm GMT+7

Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.

National key projects gradually built up

The Long Thanh airport project in the southern province of Dong Nai has an estimated investment of VND336.63 trillion ($16.06 billion), with its first phase requiring VND114.45 trillion ($5.45 billion).

The first phase of the three-stage project involves the construction of a runway and passenger terminal, along with auxiliary facilities, capable of handling 25 million passengers per year. A cargo terminal is designed to have an annual capacity of 1.2 million tons of freight. The first phase is expected to come on stream by 2025 at the latest.

The second phase will cover an additional open runway and one passenger terminal, aiming to raise the airport’s yearly capacity to 50 million passengers. Additionally, a cargo terminal capable of handling 1.5 million tons of cargo per year will be supplemented.

For the third phase, further enhancements will be made to lift the project’s capacity to 100 million passengers and five million tons of cargo annually.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.

The project has largely remained on schedule thus far, but the Airports Corporation of Vietnam (ACV) has reported some hurdles to site clearance.

Specifically, while the site handover for a traffic system connecting Road No.1 has been 99% completed, an issue related to site clearance persists at the intersection between Road No.1 and the Bien Hoa-Vung Tau Expressway project. Additionally, there is a similar hitch to the section extending from Km0+880 to Km0+944 of the Bung Mon bridge.

Those obstacles have delayed land increment reinforcement, posing a risk to the progress of soft roadbed soil treatment

Additionally, although over 89% of the site has been allocated for the construction of road No.2, ACV noted that approximately 80% of the area is qualified for development, and some locations have still not been fully cleared for construction.

For example, the non-cleared location at the intersection between Road No.2 and the Ho Chi Minh City-Long Thanh-Dau Giay Expressway has impacted the progress of an overpass spanning the expressway’s T12-to-T22 section, which may take 12 months to construct.

Additionally, certain existing technical issues, particularly power lines, along Road No.2 have yet to be cleared or relocated, impacting both safety assurance and construction progress.

Therefore, ACV proposed the People’s Committee of Dong Nai province to ask relevant units to accelerate site clearance for a complete handover to ensure the project runs on schedule.

In early February, Prime Minister Pham Minh Chinh inspected the Long Thanh airport project. During his visit, the PM emphasized that while previous years had laid the foundation for the airport, this year marks a period of acceleration, and 2025 is slated as the breakthrough year.

He also stressed the urgency of completing the airport project within the first half of 2026. Drawing from past experiences, Chinh asked for the timeline to be adjusted with a view to shortening the progress by three-six months to offset any delays.

As a key national project, Long Thanh airport will significantly enhance flight routes, bolster Vietnam’s economic links with countries in ASEAN and the world, and alleviate congestion at Tan Son Nhat International Airport, which is located in the adjacent metropolis of Ho Chi Minh City.

It is expected to serve as a pivotal transit hub for Asia and beyond by 2030. However, site clearance setbacks have made investors and contractors fret over deadlines committed to by the government.

North-South Expressway component projects likely to miss 2025 completion deadline

After one year of construction, the component projects of the North-South Expressway’s eastern section in the 2021-2025 period are facing many challenges related to site clearance and material shortages. If these issues are not addressed promptly, the Ministry of Transport (MoT) acknowledges that it will be difficult to complete the component projects by 2025 as required by the government and National Assembly.

Notably, the 49-km Dien Chau-Bai Vot Expressway project, kicked off in May 2021 with a total investment of VND11.15 trillion ($446.2 million), is designed to connect Nghe An and Ha Tinh provinces, both in the central region.

A 30-kilometer segment of the project, extending from the intersection of National Highway No.7 (Dien Chau district) to the intersection of National Highway No.46B (Hung Nguyen district), was inaugurated on April 28, shortening the travel time between Hanoi and Nghe An’s Vinh town from five and a half hours to three hours by car.

However, the remaining 19 kilometers from National Highway No.46B to Bai Vot district (Ha Tinh province), characterized by soft soil, requires additional time for ground reinforcement and will be inaugurated this September.

Similarly, the Cam Lam-Vinh Hao Expressway, spanning the central provinces of Khanh Hoa, Ninh Thuan, and Binh Thuan, was opened to traffic on April 26 after 28 months of construction. The 78.5-km route, with a total investment of VND3.92 trillion ($352.14 million), slashes the travel time from Ho Chi Minh City to Khanh Hoa’s Nha Trang town from eight hours to five hours by car.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.

Regarding the 12 component projects of the North-South Expressway in 2021-2025, the MoT said that their investors and contractors had basically adhered to the timetable. However, the Can Tho-Hau Giang and Hau Giang-Ca Mau sections, both in the south, are lagging behind schedule due to a shortage of sand.

Specifically, for component projects spanning from Ha Tinh to Khanh Hoa provinces, both in central Vietnam, contractors have exploited 14 out of 17 sand quarries, meeting about 91% of the demand. The remaining three quarries, located along the Quang Ngai province-Hoai Nhon town section, remain unexploited due to disagreements with owners of mining land over compensation prices. Besides, 43 out of 55 sand quarries scattered all over the Ha Tinh-Khanh Hoa section are reported to have satisfied around 77% of the demand.

For the Can Tho-Ca Mau Expressway project, the Mekong Delta provinces of An Giang, Dong Thap, and Vinh Long have arranged a total supply of 16.02 million cubic meters of sand. Meanwhile, a source for 2.98 million m3 of sand has not yet been determined (one million m3 for An Giang and 1.98 million m3 for Vinh Long). Of the total supply, nine million m3 of sand is being exploited, and the remaining seven million is awaiting procedures for exploitation.

Contractors have delivered 2.7 million m3 of sand to the construction site, comprising 400,000 m3 for An Giang, 2.3 million m3 from Dong Thap, and 4,400 m3 for Vinh Long. The sand mining capacity in the Mekong Delta region remains considerably low, averaging only 18,000 m3/day. This falls short of the project’s daily demand of 50,000 m3, primarily due to restrictions on capacity and exploitation means/hours.

In terms of site clearance, the ministry assessed that if the site was not handed over for construction before April 30, the component projects might slip behind the scheduled completion year of 2025.

In addition, unless the amendments of Resolution 273 on changing the use purpose of forest, forest land, and rice farming land cultivated for two crops and beyond are submitted to the National Assembly’s Standing Committee for approval in April, the progress of the component projects of the North-South Expressway in 2021-2025 will be greatly impacted.

Viewing site clearance as a principal task, the MoT has requested local authorities to address hitches for these projects.

Comments (0)
  • Read More
Thailand, Australia boost ties in transport, logistics

Thailand, Australia boost ties in transport, logistics

Thailand and Australia are seeking to strengthen cooperation in transport infrastructure and carbon emission reduction in the logistics sector.

Southeast Asia - Mon, February 17, 2025 | 8:20 pm GMT+7

China surpasses US as biggest importer of Vietnamese shrimp

China surpasses US as biggest importer of Vietnamese shrimp

China imported $834 million worth of Vietnamese shrimp last year, surpassing the U.S. to become the largest buyer of this item from Vietnam, according to the Vietnam Association of Seafood Exporters and Producers (VASEP).

Economy - Mon, February 17, 2025 | 7:51 pm GMT+7

Malaysia, S Korea resume FTA talks

Malaysia, S Korea resume FTA talks

Malaysia and South Korea are set to hold their seventh round of negotiations for a bilateral free trade agreement (FTA) as they look to expand their trade portfolio and strengthen cooperation, according to the latter's Ministry of Trade, Industry and Energy.

Southeast Asia - Mon, February 17, 2025 | 5:23 pm GMT+7

Indonesia to launch new sovereign wealth fund this month

Indonesia to launch new sovereign wealth fund this month

Indonesia will launch a new sovereign wealth fund called Danantara this month, with an initial capital of around $20 billion.

Southeast Asia - Mon, February 17, 2025 | 5:19 pm GMT+7

Singapore's Billion Union builds $70 mln fabric factory in Vietnam

Singapore's Billion Union builds $70 mln fabric factory in Vietnam

Hong Kong-invested Thanh Hoa Billion Union Textile kicked off the construction of a $70 million factory in Vietnam’s central province of Thanh Hoa on Monday.

Industries - Mon, February 17, 2025 | 5:04 pm GMT+7

Vietnam’s construction ministry plans real estate exchanges for improved transparency

Vietnam’s construction ministry plans real estate exchanges for improved transparency

The Vietnamese Ministry of Construction is advancing a plan to establish real estate exchanges, similar to the stock market, in a bid to enhance transparency and efficiency in property transactions.

Real Estate - Mon, February 17, 2025 | 4:57 pm GMT+7

Vietnam plans to increase electricity imports from China, Laos by 2030

Vietnam plans to increase electricity imports from China, Laos by 2030

The Vietnamese Ministry of Industry and Trade (MoIT) aims to raise electricity imports from China and Laos by 3,000 MW and 2,500 MW by 2030, over 5 times and nearly 1.6 times higher than those stated in the current Power Development Plan VIII (PDP VIII), respectively.

Energy - Mon, February 17, 2025 | 4:14 pm GMT+7

Vietnam urges Turkish contractor to speed up mega Long Thanh airport's terminal construction

Vietnam urges Turkish contractor to speed up mega Long Thanh airport's terminal construction

Türkiye-based IC ICTAS, the lead contractor of the passenger terminal within the under-construction Long Thanh International Airport, should speed up the construction of the package, said Vietnamese Deputy Prime Minister Tran Hong Ha.

Infrastructure - Mon, February 17, 2025 | 3:27 pm GMT+7

Vietnam tech giant FPT to provide high-quality AI human resources

Vietnam tech giant FPT to provide high-quality AI human resources

With the groundbreaking of an inter-level school on Sunday, FPT Corporation is completing its education system from elementary to university levels in the south-central province of Binh Dinh, to provide high-quality human resources, particularly in AI.

Companies - Mon, February 17, 2025 | 11:32 am GMT+7

Japan pneumatics firm SMC to start $330 mln Vietnam expansion from July

Japan pneumatics firm SMC to start $330 mln Vietnam expansion from July

SMC Manufacturing Vietnam, under Japanese pneumatic instrument producer SMC, aims to start its $330 million expansion in Vietnam from July.

Industries - Mon, February 17, 2025 | 10:47 am GMT+7

Institutional breakthroughs to provide solid foundation for heightened business confidence: economists

Institutional breakthroughs to provide solid foundation for heightened business confidence: economists

At a meeting of the National Assembly's Economic Committee in early February, the government proposed the 2025 GDP growth be "8% or more", instead of 6.5-7% set last November. The Investor introduces opinions of some leading Vietnamese economists on this proposed target.

Economy - Mon, February 17, 2025 | 8:02 am GMT+7

Vietnam consumer credit enters new growth cycle

Vietnam consumer credit enters new growth cycle

After the decrease in consumer capital demand, negative growth, and peaking bad debts in 2023, Vietnam’s consumer financial market is entering a new growth cycle, backed by positive signs from the macroeconomic environment.

Finance - Sun, February 16, 2025 | 3:19 pm GMT+7

Vietnam property investors seek new opportunities in provincial markets

Vietnam property investors seek new opportunities in provincial markets

Real estate investors in Vietnam, both individuals and organizations, are shifting their investments from city centers to suburban regions and neighboring provinces where land remains abundant and significant investments are being made in infrastructure, particularly in transportation.

Real Estate - Sun, February 16, 2025 | 2:00 pm GMT+7

Five Vietnam pilgrimage destinations perfect for spiritual seekers: Booking.com

Five Vietnam pilgrimage destinations perfect for spiritual seekers: Booking.com

Booking.com, the world's leading digital travel company, has suggested some destinations in Vietnam for those seeking spiritual enrichment and a chance for reflection and connection, including Ba Den mountain and Bai Dinh pagoda.

Travel - Sun, February 16, 2025 | 10:59 am GMT+7

Malaysia takes the lead in data center development

Malaysia takes the lead in data center development

Malaysia is making efforts to align with the global trend towards digitalization, which is driving demand for data centers, cloud computing, blockchain, and artificial intelligence (AI).

Southeast Asia - Sun, February 16, 2025 | 10:57 am GMT+7

WB sees Thai fiscal risks mounting due to spending surge

WB sees Thai fiscal risks mounting due to spending surge

Thailand’s pursuit of an expansionary fiscal policy strategy to propel growth faces the risk of rising costs for elderly care, investment and the need to keep public debt level to sustainable levels, according to the World Bank.

Southeast Asia - Sun, February 16, 2025 | 10:41 am GMT+7