Key infrastructure projects face site clearance issues, material shortages
Progress of the Long Thanh international airport project and component projects for the North-South Expressway’s eastern section in the 2021-2025 period is being held back by uneven site clearance and material shortages.
National key projects gradually built up
The Long Thanh airport project in the southern province of Dong Nai has an estimated investment of VND336.63 trillion ($16.06 billion), with its first phase requiring VND114.45 trillion ($5.45 billion).
The first phase of the three-stage project involves the construction of a runway and passenger terminal, along with auxiliary facilities, capable of handling 25 million passengers per year. A cargo terminal is designed to have an annual capacity of 1.2 million tons of freight. The first phase is expected to come on stream by 2025 at the latest.
The second phase will cover an additional open runway and one passenger terminal, aiming to raise the airport’s yearly capacity to 50 million passengers. Additionally, a cargo terminal capable of handling 1.5 million tons of cargo per year will be supplemented.
For the third phase, further enhancements will be made to lift the project’s capacity to 100 million passengers and five million tons of cargo annually.

An overall view of the Long Thanh airport project in Dong Nai province, southern Vietnam. Photo by Cao Nguyen.
The project has largely remained on schedule thus far, but the Airports Corporation of Vietnam (ACV) has reported some hurdles to site clearance.
Specifically, while the site handover for a traffic system connecting Road No.1 has been 99% completed, an issue related to site clearance persists at the intersection between Road No.1 and the Bien Hoa-Vung Tau Expressway project. Additionally, there is a similar hitch to the section extending from Km0+880 to Km0+944 of the Bung Mon bridge.
Those obstacles have delayed land increment reinforcement, posing a risk to the progress of soft roadbed soil treatment
Additionally, although over 89% of the site has been allocated for the construction of road No.2, ACV noted that approximately 80% of the area is qualified for development, and some locations have still not been fully cleared for construction.
For example, the non-cleared location at the intersection between Road No.2 and the Ho Chi Minh City-Long Thanh-Dau Giay Expressway has impacted the progress of an overpass spanning the expressway’s T12-to-T22 section, which may take 12 months to construct.
Additionally, certain existing technical issues, particularly power lines, along Road No.2 have yet to be cleared or relocated, impacting both safety assurance and construction progress.
Therefore, ACV proposed the People’s Committee of Dong Nai province to ask relevant units to accelerate site clearance for a complete handover to ensure the project runs on schedule.
In early February, Prime Minister Pham Minh Chinh inspected the Long Thanh airport project. During his visit, the PM emphasized that while previous years had laid the foundation for the airport, this year marks a period of acceleration, and 2025 is slated as the breakthrough year.
He also stressed the urgency of completing the airport project within the first half of 2026. Drawing from past experiences, Chinh asked for the timeline to be adjusted with a view to shortening the progress by three-six months to offset any delays.
As a key national project, Long Thanh airport will significantly enhance flight routes, bolster Vietnam’s economic links with countries in ASEAN and the world, and alleviate congestion at Tan Son Nhat International Airport, which is located in the adjacent metropolis of Ho Chi Minh City.
It is expected to serve as a pivotal transit hub for Asia and beyond by 2030. However, site clearance setbacks have made investors and contractors fret over deadlines committed to by the government.
North-South Expressway component projects likely to miss 2025 completion deadline
After one year of construction, the component projects of the North-South Expressway’s eastern section in the 2021-2025 period are facing many challenges related to site clearance and material shortages. If these issues are not addressed promptly, the Ministry of Transport (MoT) acknowledges that it will be difficult to complete the component projects by 2025 as required by the government and National Assembly.
Notably, the 49-km Dien Chau-Bai Vot Expressway project, kicked off in May 2021 with a total investment of VND11.15 trillion ($446.2 million), is designed to connect Nghe An and Ha Tinh provinces, both in the central region.
A 30-kilometer segment of the project, extending from the intersection of National Highway No.7 (Dien Chau district) to the intersection of National Highway No.46B (Hung Nguyen district), was inaugurated on April 28, shortening the travel time between Hanoi and Nghe An’s Vinh town from five and a half hours to three hours by car.
However, the remaining 19 kilometers from National Highway No.46B to Bai Vot district (Ha Tinh province), characterized by soft soil, requires additional time for ground reinforcement and will be inaugurated this September.
Similarly, the Cam Lam-Vinh Hao Expressway, spanning the central provinces of Khanh Hoa, Ninh Thuan, and Binh Thuan, was opened to traffic on April 26 after 28 months of construction. The 78.5-km route, with a total investment of VND3.92 trillion ($352.14 million), slashes the travel time from Ho Chi Minh City to Khanh Hoa’s Nha Trang town from eight hours to five hours by car.

The Cam Lam-Vinh Hao Expressway, part of the North-South Expressway project, was opened to traffic on April 26, 2024. Photo by DC.
Regarding the 12 component projects of the North-South Expressway in 2021-2025, the MoT said that their investors and contractors had basically adhered to the timetable. However, the Can Tho-Hau Giang and Hau Giang-Ca Mau sections, both in the south, are lagging behind schedule due to a shortage of sand.
Specifically, for component projects spanning from Ha Tinh to Khanh Hoa provinces, both in central Vietnam, contractors have exploited 14 out of 17 sand quarries, meeting about 91% of the demand. The remaining three quarries, located along the Quang Ngai province-Hoai Nhon town section, remain unexploited due to disagreements with owners of mining land over compensation prices. Besides, 43 out of 55 sand quarries scattered all over the Ha Tinh-Khanh Hoa section are reported to have satisfied around 77% of the demand.
For the Can Tho-Ca Mau Expressway project, the Mekong Delta provinces of An Giang, Dong Thap, and Vinh Long have arranged a total supply of 16.02 million cubic meters of sand. Meanwhile, a source for 2.98 million m3 of sand has not yet been determined (one million m3 for An Giang and 1.98 million m3 for Vinh Long). Of the total supply, nine million m3 of sand is being exploited, and the remaining seven million is awaiting procedures for exploitation.
Contractors have delivered 2.7 million m3 of sand to the construction site, comprising 400,000 m3 for An Giang, 2.3 million m3 from Dong Thap, and 4,400 m3 for Vinh Long. The sand mining capacity in the Mekong Delta region remains considerably low, averaging only 18,000 m3/day. This falls short of the project’s daily demand of 50,000 m3, primarily due to restrictions on capacity and exploitation means/hours.
In terms of site clearance, the ministry assessed that if the site was not handed over for construction before April 30, the component projects might slip behind the scheduled completion year of 2025.
In addition, unless the amendments of Resolution 273 on changing the use purpose of forest, forest land, and rice farming land cultivated for two crops and beyond are submitted to the National Assembly’s Standing Committee for approval in April, the progress of the component projects of the North-South Expressway in 2021-2025 will be greatly impacted.
Viewing site clearance as a principal task, the MoT has requested local authorities to address hitches for these projects.
- Read More
Vietnam’s army-backed construction firm proposes 14 offshore wind power projects
Lung Lo Construction Corporation (LLC), under the Ministry of National Defense, has submitted investment proposals for 14 offshore wind power projects with a combined capacity of 9,000 MW.
Energy - Thu, August 7, 2025 | 5:07 pm GMT+7
Vietnam's agri major Hoang Anh Gia Lai fined for bond information disclosure failure
Vietnam's agri major Hoang Anh Gia Lai JSC has been fined VND92.5 million ($3,528) for failing to disclose bond-related information as required by law.
Companies - Thu, August 7, 2025 | 4:31 pm GMT+7
Northern Vietnam province accelerates $2.2 bln LNG-to-power project
Quang Ninh province will hand over 4.9 hectares of reclaimed land to the Quang Ninh LNG-fuelled power plant project before August 11, local authorities stated at a meeting on Wednesday.
Energy - Thu, August 7, 2025 | 4:17 pm GMT+7
Vietnam's seafood firms ride profit wave ahead of US tariff hike
Vietnam’s seafood companies reported surging profits in Q2/2025, driven by importers ramping up purchases ahead of new U.S. reciprocal tariffs.
Economy - Thu, August 7, 2025 | 2:21 pm GMT+7
Le Anh Tuan appointed new CEO of Dragon Capital Vietfund Management JSC
Dragon Capital Group, Vietnam's largest asset manager, has appointed Le Anh Tuan as CEO of its arm Dragon Capital Vietfund Management Joint Stock Company (DCVFM), starting from October 1, 2025.
Companies - Thu, August 7, 2025 | 2:01 pm GMT+7
Indonesia, Malaysia, Thailand expand local currency transaction network
Bank Indonesia, Bank Negara Malaysia, and Bank of Thailand have added new Appointed Cross Currency Dealer (ACCD) participating banks to broaden services for bilateral transactions in local currencies across the three nations, Bank Indonesia said in a statement on Tuesday.
Southeast Asia - Thu, August 7, 2025 | 12:48 pm GMT+7
ASEAN to sign MoU on regional power grid implementation
ASEAN member states are set to sign an MoU on the implementation of the ASEAN Power Grid during the bloc’s Energy Ministers’ Meeting this October.
Southeast Asia - Thu, August 7, 2025 | 12:43 pm GMT+7
Vietnam overtakes Thailand to become world's second-largest rice exporter
Vietnam has outranked Thailand as the world’s second-largest rice exporter in the first half of 2025, Thai PBS reported on August 3, citing the Thai Rice Exporters Association.
Companies - Thu, August 7, 2025 | 12:41 pm GMT+7
Vietnam posts trade surplus of $10.18 bln in 7 months
Vietnam’s export earnings grew by 14.8% to $262.44 billion in the first seven months of this year, while its import turnover rose by 17.9% to $252.26 billion, resulting in a trade surplus of $10.18 billion.
Economy - Thu, August 7, 2025 | 12:19 pm GMT+7
Malaysia pledges big purchases, investments with US
Malaysia has agreed to buy and invest over $240 billion (MYR1.02 trillion) in the U.S. to help reduce the trade gap between the two countries.
Southeast Asia - Thu, August 7, 2025 | 12:08 pm GMT+7
Vietnam's leading property developer Novaland to issue 152 mln shares to settle $229 mln debt
Novaland, a major real estate developer in Vietnam, plans to issue nearly 152 million new shares to swap more than VND6 trillion ($228.8 million) worth of bond principal.
Companies - Thu, August 7, 2025 | 10:11 am GMT+7
Vietnam's FDI capital disbursement hits five-year record high despite US tariff turmoil
Disbursed foreign direct investment (FDI) capital in Vietnam reached $13.6 billion in Jan-July, up 8.4% year-on-year, despite U.S. tariff concerns.
Economy - Thu, August 7, 2025 | 9:57 am GMT+7
Malaysia steps up efforts to explore nuclear energy potential
Malaysia’s Minister of Science, Technology and Innovation Chang Lih Kang on Wednesday reaffirmed his ministry’s commitment to enhancing cooperation with the Ministry of Energy Transition and Water Transformation (PETRA) in exploring the potential of nuclear energy.
Southeast Asia - Thu, August 7, 2025 | 8:10 am GMT+7
Indonesia's economy grows faster than expected
Indonesia's economy expanded by 5.12% year-on-year in Q2/2025, up from 4.87% in the previous quarter, exceeding the forecasts of many economic organizations, which had previously projected a rate of less than 5%, according to Statistics Indonesia (BPS).
Southeast Asia - Thu, August 7, 2025 | 8:07 am GMT+7
Philippine energy group eyes investment in Vietnam’s power sector
AboitizPower wants to invest in Vietnam’s electricity industry, especially in transmission infrastructure, said Danel Aboitiz, executive director of the corporation.
Energy - Wed, August 6, 2025 | 11:11 pm GMT+7
Vietnam seeks 8.3-8.5% economic expansion for 2025
The Government has requested the State Bank of Vietnam to proactively adjust the credit growth aim for this year in line with a GDP expansion target of 8.3-8.5%.
Economy - Wed, August 6, 2025 | 10:41 pm GMT+7