Korea-backed Hai Lang LNG power project at risk of delay

An illustration of the Hai Lang LNG to power center project in Quang Tri province, central Vietnam. Photo courtesy of the investor consortium.
South Korean investors are fretting over possible delays in their liquefied natural gas to power project, Hai Lang phase 1, in Quang Tri province as it is not included in Vietnam’s draft power development plan VIII.
Together with Vietnam’s T&T Group, Korea Gas Corporation (KOGAS), South Power (KOSPO) and Hanwha Energy (HEC) are participating in the project phase 1, which is expected to start commercial exploitation in the period 2026-2027 in Southeast Quang Tri Economic Zone, central Vietnam.
The project progress (2026-2027) was mentioned in the country’s approved power development plan VII (PDP VII), but the draft PDP VIII states that phase 1 would be put into commercial operation in 2036-2040 and phase 2 in 2041-2045.
“Therefore, investors as well as provincial authorities are facing quite a serious problem. We hope that the Vietnamese government would pay attention and create conditions for the project to be implemented as originally planned,” the Korea Chamber of Commerce in Vietnam said in its presentation made at the recent Vietnam Business Forum (VBF).
Kocham quoted the South Korean investors as saying they understand that the Hai Lang project is located quite far from the area with electricity demand in the North or the South, so the Ministry of Industry and Trade is concerned about the cost of electricity transmission.
“However, the Hai Lang phase 1 project (1,500 MW) has points that are very suitable for Vietnam’s development interests such as not requiring expansion of the existing 500 kV line, having the optimal location to put the LNG production model in, investor’s capacity and high level of enterprise’s contribution to the country’s balanced development.”
Specifically, according to the pre-feasibility project implemented by the Institute of Energy, the Hai Lang phase 1 project can operate normally without expanding the existing power transmission network. In general, the loss during power transmission on the 500 kV grid is not significant, about 0.1 percent from Quang Tri province to the North. This is a reasonable loss that can be fully compensated by the introduction of the LNG system with economic and competitive advantages due to favorable geographical conditions.
In terms of seaport equipment and operating costs of LNG carriers necessary for the implementation of LNG project development, the investors noted that the land area for the Hai Lang project is economical and stable because this area ensures the deep water level necessary for the porting of LNG carriers, which is quite rare in Vietnam.
In southern or northern Vietnam, the water depth of most coastal areas is low, so large-scale dredging or establishment of floating LNG terminals (FSRU), construction of long undersea pipelines for LNG carriers to access is required.
The investors also highlighted their ability to execute the project in a timely and economically efficient manner. “KOGAS can provide LNG in the most economical way to Vietnam thanks to its LNG purchasing power equivalent to 9 percent of the total global LNG trade (35 million tons per year). KOSPO has the largest number of LNG power plants in Korea, so KOSPO has excellent LNG power generation capacity, related operating technology capability, and excellent key equipment negotiation capacity.”
They added that the project would contribute to the balanced development of provinces in central Vietnam and revitalizing new industrial complexes in the country like Southeast Quang Tri Economic Zone in Quang Tri province and Chan May Lang Co area in Hue town.
"Although using fossil fuel sources, LNG power generation is the optimal solution to help achieve the goal of net-zero emissions with a stable baseload in the process of replacing coal-fired power sources."
The investors noted that if PDP VIII stipulates that the plan is to be rolled back beyond 2030, the project development may become practically impossible. “For example, it will be difficult to coordinate with finance, construction, and equipment companies that are intending to participate in the Hai Lang project.”
With investment capital of nearly VND54 trillion (over $2.3 billion), the Hai Lang project, set to use more than 120 hectares of land, embarked on its technical component in mid January 2022.
According to the plan, the project includes Hai Lang LNG Terminal phase 1, which will receive LNG ships from 170,000 to 226,000 cubic meters with an annual reception capacity of 1.5 million tonnes of LNG per year, and Hai Lang Power Center phase 1, which will have a generation capacity of 1,500 MW.
Do Quang Hien, Chairman and General Director of T&T Group, said that the project applies new-generation gas turbine technology that is being used in many developed countries like the U.S., France, Japan and South Korea, with high power generation efficiency.
After operation, Hai Lang Power Center will supply the national electricity system with about 8.25 billion kWh/year and can make up for the shortage of capacity at times as renewable energy like solar power and wind power in the central region accounts for a large proportion but fluctuates due to the weather.
A source told local press that the Hai Lang project investors have not yet proceeded negotiations on a power purchasing agreement (PPA) with the electricity purchase company under Vietnam Electricity (EVN). Such negotiations in Vietnam are notoriously time-consuming.
- Read More
Vietnam’s e-motorbike market enters stage of fierce competition
Vietnam’s electric motorbike market is entering a new phase of intense competition as domestic and foreign manufacturers are accelerating their expansion, diversify products, and invest heavily in infrastructure.
Companies - Sun, September 7, 2025 | 6:06 pm GMT+7
HCMC fast-tracks rail projects proposed by private conglomerates
The Ho Chi Minh City People’s Committee has asked municipal agencies to work with major private conglomerates to finalize investment plans for the railway projects they proposed.
Infrastructure - Sun, September 7, 2025 | 1:52 pm GMT+7
Vietnam's Finance Ministry targets 60% public investment disbursement by end-Q3
Vietnam’s public investment disbursement reached VND409.17 trillion ($15.49 billion) in the year to August 31, equal to 39.9% of the year's plan and 46.3% of the Prime Minister’s target, the Ministry of Finance (MoF) reported.
Economy - Sun, September 7, 2025 | 10:53 am GMT+7
Vietnam posts nearly $14 bln trade surplus in 8 months
Vietnam recorded a trade surplus of $13.99 billion in the first eight months of 2025, according to the General Statistics Office under the Ministry of Finance.
Economy - Sun, September 7, 2025 | 10:41 am GMT+7
S&P upgrades ratings of three Vietnamese banks, citing resilient economy
S&P Global Ratings has raised the long-term credit ratings of three major Vietnamese banks, reflecting the stronger resilience of the country’s financial system and continued above-average economic growth.
Banking - Sun, September 7, 2025 | 10:34 am GMT+7
Luong Nguyen Minh Triet appointed top leader of central Vietnam hub Danang
Luong Nguyen Minh Triet, deputy Party chief of Danang and Chairman of the municipal People's Committee, has been appointed the city's Party chief - the highest position in the locality.
Politics - Sun, September 7, 2025 | 9:53 am GMT+7
Sun Group aims to launch $2 bln casino-resort complex in northern Vietnam by 2032
Sun Group, one of Vietnam’s leading property developers, targets to complete its VND51.6 trillion ($2 billion) casino and resort complex project in the northern coastal province of Quang Ninh by 2032.
Real Estate - Sun, September 7, 2025 | 8:00 am GMT+7
Vietnam's industrial production on upward trend
Vietnam's industrial production index continued to rise in the first eight months of the year, with all 34 cities and provinces recording an increase.
Economy - Sat, September 6, 2025 | 10:20 pm GMT+7
Vietnam's leading industrial park developer Becamex IDC raises $75 mln in latest bond issuance
Becamex IDC (HoSE: BCM), a leading Vietnamese industrial park developer, has raised VND2 trillion ($75.4 million) in its latest bond issuance.
Finance - Sat, September 6, 2025 | 8:35 pm GMT+7
Vietnam's FDI capital disbursement hits five-year high amid global decline
Disbursed foreign direct investment (FDI) capital in Vietnam hit $15.4 billion in Jan-August, up 8.8% year-on-year, despite declining global investment flows, the Foreign Investment Agency (FIA) reported.
Economy - Sat, September 6, 2025 | 4:30 pm GMT+7
EVNNPT leader inspects 220kV substation project progress in central Vietnam
Pham Le Phu, CEO of EVNNPT, a subsidiary of state utility Electricity Vietnam (EVN), on Thursday inspected the construction of the 220kV Chan May Substation and its associated transmission line in the central city of Hue.
Companies - Sat, September 6, 2025 | 3:42 pm GMT+7
Vietnam’s gas transmission firm PV Gas SE: a journey of creation and pride
For over two decades, Petrovietnam Gas South East Transmission Company (PV Gas SE) has stood as a lasting symbol within Petrovietnam Gas Joint Stock Corporation (PV Gas) - one of the earliest-established units closely tied to the pioneering steps of Vietnam’s gas industry.
Companies - Sat, September 6, 2025 | 3:33 pm GMT+7
Politician Anutin Charnvirakul wins vote to become new Thai PM
Thailand’s Bhumjaithai Party leader Anutin Charnvirakul has secured enough votes to become the country's new Prime Minister.
Southeast Asia - Sat, September 6, 2025 | 10:55 am GMT+7
Vietnam’s sugar productivity maintains top regional spot
In the 2024-2025 crop, Vietnam maintained its position as the regional leader in sugar productivity, reaping 6.69 tons per hectare, outpacing other major producers such as Thailand, Indonesia, and the Philippines.
Companies - Sat, September 6, 2025 | 10:53 am GMT+7
Gaming drives Vietnam tech unicorn VNG’s H1 revenue
Vietnamese tech unicorn VNG Corp (UPCoM: VNZ) reported net revenue of over VND4.8 trillion ($181.82 million) in H1, up 11% year-on-year, with gaming remaining its major contributor at VND3.59 trillion ($135.98 million).
Companies - Sat, September 6, 2025 | 10:39 am GMT+7
Hanoi gives green light to fifth metro line Van Cao-Hoa Lac
Vietnam's capital city of Hanoi has approved a plan to build the Metro Line No. 5, connecting Van Cao with Hoa Lac.
Infrastructure - Sat, September 6, 2025 | 9:02 am GMT+7