Long An authorities show lax management of solar, LNG power projects: inspectors
The authorities of Long An province in the Mekong Delta had shown lax management that led to violations in the management and use of land and investment in solar power and liquefied natural gas (LNG) thermal power plants, concluded the Government Inspectorate.
The inspectorate on Monday announced its conclusion on the observance of policies and laws in the management and implementation of the national power development plan for the 2011-2020 period (PDP VII) and its amended version (2016-2020).
Under the conclusion, the inspectors said although the Long An I & II LNG thermal power plants had their investment plans approved in 2021, their developer VinaCapital GS Energy Pte. .Ltd had failed to make a deposit or bank guarantee on the deposit obligation at a rate of 1% of the project's total investment capital, equivalent to $31.2 million.

The Long An I LNG thermal power plant in Long An province, the Mekong Delta. Photo courtesy of VietnamFinance.
In addition to the developer, the provincial Department of Planning and Investment and the provincial People's Committee were also responsible for this violation, the Government Inspectorate said.
At the same time, the provincial People's Committee was found to have committed violations when approving the construction site of Long An I and Long An II at the Southeast Asia Industrial Park, which does not have approval for industrial production. It added functional zones to the industrial park development plan without submitting them to the Ministry of Planning and Investment for appraisal and to the prime minister for consideration.
The provincial authorities also showed loose management, leading to a series of violations in converting land use purposes, leasing land beyond the allowed limit, commencing solar power projects without a land lease, and putting solar power plants into commercial operations when they were not eligible.
For example, Hanwha – BCG Bang Duong Energy JSC and Hoancau L.A Co., Ltd started construction on the GAIA and Solar Park 02 solar power plants on 124.8 hectares and 52.53 hectares of production forest land, respectively.
In addition, Vietnam Solar Energy JSC kicked off construction on Solar Park 02 on an area of 50.3 hectares; Long An Solar Park JSC with the 48.3-hectare Solar Park 03 solar power plant; Solar Energy LA JSC with the 49.5-hectare Solar Park 04 solar power plant; and Long An Europlast Solar Power JSC with the Europlast Long An Solar PV Park on 58.66 hectares.
All eight solar power projects in Long An province were put into use by the developers and the Electric Power Trading Company (EPTC) under state utility Vietnam Electricity (EVN), with the appraisal process yet to be inspected and approved by competent state agencies.
EPTC's recognition of the commercial operation date and electricity purchase of the above-mentioned power plants at preferential FIT prices for 20 years (four enjoying the FIT price of 9.35 U.S. cents per kWh and four 7.09 U.S. cents per kWh) when competent state agencies had not inspected and approved the developers’ appraisal results is a violation of regulations set by the Ministry of Industry and Trade and the prime minister, according to the inspectorate.
Although the prime minister had not yet allowed the People's Committee of Long An province to change the purpose of use of 124.84 hectares of production land and forest to energy development land, the General Administration of Forestry guided the provincial Department of Natural Resources and Environment to organize an auction to lease the right to use this land for developing energy projects. The provincial People's Committee’s organization of the auction also violated regulations.
Thanh Hoa district’s construction investment project management unit’s handover of 124.8 hectares of land to Hanwha – BCG Bang Duong Energy JSC and 50 hectares to BCG - Bang Duong Energy JSC before being leased by the provincial People's Committee ran counter to regulations.
The inspectors also determined that the authorities of Long An leased land to developers to build solar power plants exceeding the prescribed limit by 11.05 hectares, including 9.76 hectares to TTC - Duc Hue Long An Electric JSC and 1.29 hectares to BCG - Bang Duong Energy JSC.
They were also responsible for lax management, allowing developers to start construction without land leases issued by the provincial People's Committee.
- Read More
Vietnam aims to finalize negotiations for Ninh Thuan 1 nuclear power plant by August
The Vietnamese government targets completing negotiations for Ninh Thuan 1 nuclear power plant in former Ninh Thuan province (now Khanh Hoa) by August 2025, and for Ninh Thuan 2 by May 2026 at the latest.
Energy - Fri, August 8, 2025 | 4:18 pm GMT+7
Software giant SAP invests $175 ml in R&D center in Vietnam
German software heavyweight SAP has officially launched a research & development center in Vietnam, with plans to invest more than €150 million ($175 million) over the next five years.
Industries - Fri, August 8, 2025 | 3:43 pm GMT+7
Carlsberg’s $130 mln plant expansion in central Vietnam set to start brewing next month
The expansion of Carlsberg’s brewery in Hue city, central Vietnam, with an investment of over VND3.4 trillion ($129.66 million), has entered trial runs and is scheduled to begin full production in September, Carlsberg Vietnam said.
Industries - Fri, August 8, 2025 | 2:43 pm GMT+7
Indonesia promotes nickel-based EV battery production
Indonesia is advocating regulations to encourage electric vehicle (EV) manufacturers to switch from the commonly used lithium-based batteries to nickel-based ones.
Southeast Asia - Fri, August 8, 2025 | 1:54 pm GMT+7
BRICS countries account for over 35% of Malaysia’s total foreign trade turnover
Malaysia’s trade with BRICS nations climbed to RM818 billion ($193.47 billion) in 2024, making up 35.2% of the country’s total global trade, according to the Ministry of Investment, Trade and Industry (MITI).
Southeast Asia - Fri, August 8, 2025 | 1:52 pm GMT+7
Vietnam consumer finance major F88’s stock hits ceiling price on UPCoM debut
The stock of F88 Investment JSC (F88), a leading consumer finance company in Vietnam, hit its ceiling price of VND888,800 ($34) on Friday, the first day of trading on the Unlisted Public Companies Market (UPCoM).
Companies - Fri, August 8, 2025 | 1:32 pm GMT+7
US tariff unlikely to dent Vietnam’s long-term FDI appeal: broker
The U.S. tariff gap between Vietnamese goods and those from four other Southeast Asian countries would not erode Vietnam’s competitive edge in manufacturing and investment, said Hanoi-based Vietcombank Securities (VCBS).
Economy - Fri, August 8, 2025 | 12:24 pm GMT+7
Land clearance for Vietnam's North-South high-speed railway project to start on December 19
Prime Minister Pham Minh Chinh has requested localities to start land clearance en masse for the gigantic North-South high-speed railway project on December 19.
Economy - Fri, August 8, 2025 | 11:52 am GMT+7
Vietnam might launch pilot digital asset exchange in August
A digital asset exchange might be launched in August on a pilot basis, Deputy Minister of Finance Nguyen Duc Chi told a government press meeting on Thursday.
Finance - Fri, August 8, 2025 | 11:25 am GMT+7
Vietnam’s steel giant Hoa Sen spends $34 mln on land near Long Thanh airport for urban development
Hoa Sen Group (HoSE: HSG), Vietnam’s top producer of coated steel products, has spent VND900 billion ($34.3 million) acquiring land for a major urban development project in the southern province of Dong Nai.
Real Estate - Fri, August 8, 2025 | 8:22 am GMT+7
Halal market presents major opportunities for Vietnamese businesses
The global Halal market is projected to reach $5 trillion by 2030, with Malaysia alone expected to hit $113.2 billion, said Shariza binti Abdul Rasheed, Halal product manager at Maybank Malaysia.
Economy - Thu, August 7, 2025 | 9:18 pm GMT+7
Steel major Hoa Phat to pour extra $130 mln into central Vietnam plant
Vietnam’s leading steelmaker, Hoa Phat Group (HoSE: HPG), will increase investment in its Dung Quat 2 iron and steel production complex by VND3.4 trillion ($129.7 million) as part of an expansion plan.
Industries - Thu, August 7, 2025 | 8:03 pm GMT+7
Vietnam’s army-backed construction firm proposes 14 offshore wind power projects
Lung Lo Construction Corporation (LLC), under the Ministry of National Defense, has submitted investment proposals for 14 offshore wind power projects with a combined capacity of 9,000 MW.
Energy - Thu, August 7, 2025 | 5:07 pm GMT+7
Vietnam's agri major Hoang Anh Gia Lai fined for bond information disclosure failure
Vietnam's agri major Hoang Anh Gia Lai JSC has been fined VND92.5 million ($3,528) for failing to disclose bond-related information as required by law.
Companies - Thu, August 7, 2025 | 4:31 pm GMT+7
Northern Vietnam province accelerates $2.2 bln LNG-to-power project
Quang Ninh province will hand over 4.9 hectares of reclaimed land to the Quang Ninh LNG-fuelled power plant project before August 11, local authorities stated at a meeting on Wednesday.
Energy - Thu, August 7, 2025 | 4:17 pm GMT+7
Vietnam's seafood firms ride profit wave ahead of US tariff hike
Vietnam’s seafood companies reported surging profits in Q2/2025, driven by importers ramping up purchases ahead of new U.S. reciprocal tariffs.
Economy - Thu, August 7, 2025 | 2:21 pm GMT+7