Renewable energy projects switched off by legal procedures

By Huong Dung
Sat, May 27, 2023 | 11:24 am GMT+7

Renewable energy projects that missed out on preferential feed-in-tariffs (FiTs) were not allowed to negotiate temporary prices with state utility Vietnam Electricity because they lacked the necessary legal documents, according to the Ministry of Industry and Trade.

"Some investors were asked to supplement documents at the end of March, but so far they have failed to do so," the ministry said.

Many developers have violated regulations on planning, land and construction so they have been unable to complete legal documents to obtain an electricity generation permit - a necessary procedure under the Electricity Law for a power project to be utilized, it said.

“This is the main reason for delays to the preparation and submission of documents to the authorities,” the ministry added.

As of Tuesday, only 18 transitional renewable power projects, or 19% of the total, had been granted a license. Among 19 projects with approved temporary prices, 68% had electricity generation permits. Meanwhile, 12 more have submitted price negotiation documents but have not yet received a license, including 11 wind power projects and one solar power project.

According to the ministry's Electricity & Renewable Energy Authority, as of Friday, 52 out of 84 transitional renewable power projects with a total capacity of 3,155 megawatts had submitted applications for price negotiations.

The ministry has told Vietnam Electricity (EVN) and developers to renew their power purchase agreements (if expired) before June 5. For projects that have registered for trial runs before a commercial operation date, EVN must check to see if the results meet technical and regulatory requirements and complete all related procedures before June 10.

Temporary price negotiation procedures need to be simplified, enabling the early operation and power generation of transitional renewable projects, the ministry said.

The ministry also required investors to urgently complete procedures and submit applications in order to put these projects into operation.

A wind farm in the southern coastal province of Bac Lieu. Photo courtesy of Bac Lieu newspaper.

A wind farm in the southern coastal province of Bac Lieu. Photo courtesy of Bac Lieu newspaper.

Eighty-four renewable energy projects with a total capacity of more than 4,600 MW have missed deadlines for commercial operations. Of these, 34 transitional projects (28 wind and six solar power) with a total capacity of nearly 2,100 MW have been completed and put on trial runs.

These projects will not enjoy FiTs for 20 years as they missed out on the government's power generation deadline and have to negotiate prices with EVN at 20-30% lower than FiTs.

The 20-year preferential FiTs are 9.35 U.S. cents per kWh (Decision 11/2017) and 7.09-8.38 U.S. cents per kWh (Decision 13/2020) for solar power projects that became operational by December 31, 2020; and 8.35-9.8 U.S. cents per kWh (Decision 39/2018) for wind power projects that became operational by November 1, 2021.

To date, 19 transitional renewable energy projects have accepted temporary prices equal to 50% of the ceiling levels set in a new electricity generation price bracket under Decision 21 issued on January 7, 2023.

According to the new price bracket, the maximum purchase price for transitional solar power projects is VND1,185-1,508 (5.0-6.4 U.S. cents) per kWh, depending on the type and excluding VAT. Meanwhile, the ceiling price for transitional wind power projects is VND1,587-1,816 per kWh (6.8-7.7 U.S. cents).

The projects include 14 wind power plants, namely Nam Binh 1, VPL Ben Tre, Yang Trung, Cho Long, Hung Hai Gia Lai, Lac Hoa 2, Hoa Dong 2, Vien An, Hanbaram, Huong Hiep 1, Tan Phu Dong, Hiep Thanh, Ia Le 1 and Huong Linh 7; and five solar power plants known as Phu My 1, Phu My 3, Thien Tan 1.2, Thien Tan 1.3, and another in Phuoc Minh commune, Thuan Nam district, Ninh Thuan province.

Comments (0)
  • Read More
Use social media influencers in targeted manner for e-commerce success: Vietnam execs

Use social media influencers in targeted manner for e-commerce success: Vietnam execs

Vietnamese companies should use new generation influencers in a targeted manner, prioritizing specific market segments, standardizing quality and focusing on strong product categories to achieve e-commerce success, says Nguyen Ngoc Luan, CEO of Meet More Coffee.

Companies - Fri, November 22, 2024 | 4:26 pm GMT+7

VinFast’s parent, PV Power partner to speed up charging station expansion

VinFast’s parent, PV Power partner to speed up charging station expansion

Vietnamese private conglomerate Vingroup, the parent firm of electric vehicle manufacturer VinFast, and state-controlled PV Power have entered an agreement to develop charging stations across the country and promote rooftop solar installations.

Companies - Fri, November 22, 2024 | 4:11 pm GMT+7

Petrovietnam, Petronas to boost renewable energy cooperation

Petrovietnam, Petronas to boost renewable energy cooperation

Petrovietnam and Petronas, two state-owned oil & gas giants of Vietnam and Malaysia, will further cooperate in renewable energy, including exchange of information, knowledge, and experiences.

Energy - Fri, November 22, 2024 | 2:59 pm GMT+7

FTSE Vietnam ETF may heavily buy Vinhomes, sell Vingroup in upcoming reshuffle: broker

FTSE Vietnam ETF may heavily buy Vinhomes, sell Vingroup in upcoming reshuffle: broker

FTSE Vietnam ETF is forecast to strongly buy in several Vietnamese heavyweights such as Vinhomes, Hoa Phat, and Vietcombank in its upcoming portfolio reshuffle.

Finance - Fri, November 22, 2024 | 2:45 pm GMT+7

$681 mln central Vietnam urban area project eyed by Sun Group gets authorities' nod

$681 mln central Vietnam urban area project eyed by Sun Group gets authorities' nod

A VND17.3 trillion ($681 million) urban area project that is drawing the interest of major realty developer Sun Group has received an in-principle approval from Khanh Hoa province's administration.

Real Estate - Fri, November 22, 2024 | 1:53 pm GMT+7

Vietnam foreign ministry dismisses allegations of tightening visa rules for foreigners

Vietnam foreign ministry dismisses allegations of tightening visa rules for foreigners

Allegations of Vietnam tightening visa policies and control over foreigners are "baseless", Foreign Ministry spokeswoman Pham Thu Hang said Thursday.

Politics - Fri, November 22, 2024 | 11:29 am GMT+7

Thailand-invested food giant CP fined $31,000 for environmental violations

Thailand-invested food giant CP fined $31,000 for environmental violations

Vietnam’s southern province of Dong Nai has issued a fine of VND790 million ($31,080) to Thailand-invested C.P. Vietnam Corporation for violating environmental regulations.

Companies - Fri, November 22, 2024 | 10:48 am GMT+7

Vietnamese billionaire’s daughter spends $25 mln on Masan share purchases

Vietnamese billionaire’s daughter spends $25 mln on Masan share purchases

Nguyen Yen Linh, the daughter of chairman Nguyen Dang Quang of consumer goods giant Masan Group (HoSE: MSN), has purchased nearly 8.5 million MSN shares over the past three weeks, meeting 85% of her target.

Finance - Fri, November 22, 2024 | 10:27 am GMT+7

PYN Elite manager upbeat about Vietnam’s economy, stock market despite Trump uncertainty

PYN Elite manager upbeat about Vietnam’s economy, stock market despite Trump uncertainty

The Vietnamese economy will still fare well, and the local stock market will remain appealing despite the recent pullback following Donald Trump’s election win for a second term, said Petri Deryng, portfolio manager of Finland-based the PYN Elite fund.

Finance - Fri, November 22, 2024 | 8:25 am GMT+7

Central Vietnam province plans to build $2.4 bln LNG power plant from 2031

Central Vietnam province plans to build $2.4 bln LNG power plant from 2031

The 4,800-MW Chan May LNG power plant, with an investment of $2.4 billion, can be deployed in 2031-2035, according to Thua Thien Hue authorities.

Energy - Thu, November 21, 2024 | 10:41 pm GMT+7

Indonesia, France step up cooperation in economy, defence

Indonesia, France step up cooperation in economy, defence

Indonesian President Prabowo Subianto discussed economic and defence cooperation during a bilateral meeting on Tuesday with French President Emmanuel Macron on the sidelines of the G20 Summit in Rio de Janeiro, Brazil, Antara reported.

Southeast Asia - Thu, November 21, 2024 | 10:25 pm GMT+7

Thai economy to maintain upward momentum in 2025

Thai economy to maintain upward momentum in 2025

The National Economic and Social Development Council of Thailand (NESDC) expects the Thai economy to sustain its upward momentum in 2025 with a growth of 2.3-3.3% despite growing risks.

Southeast Asia - Thu, November 21, 2024 | 10:24 pm GMT+7

Former parliament chairman Vuong Dinh Hue warned for violations

Former parliament chairman Vuong Dinh Hue warned for violations

The Politburo, Vietnam's supreme decision making body, on Wednesday issued warnings to Vuong Dinh Hue, former Chairman of the National Assembly, and Nguyen Van The, former Minister of Transport, for violations while on duties.

Politics - Thu, November 21, 2024 | 10:10 pm GMT+7

Sumitomo insists on building LNG power plant in central Vietnam

Sumitomo insists on building LNG power plant in central Vietnam

Japanese trading house Sumitomo has been pushing for a liquefied natural gas (LNG)-fed power plant investment in Vietnam’s central province of Khanh Hoa.

Energy - Thu, November 21, 2024 | 8:53 pm GMT+7

Vietnam’s Vinhomes fulfils 67% of record buyback plan

Vietnam’s Vinhomes fulfils 67% of record buyback plan

Vinhomes, the housing development arm of conglomerate Vingroup, has purchased back 246.98 million shares, meeting 66.75% of the plan and accounting for 5.7% of the outstanding volume.

Finance - Thu, November 21, 2024 | 8:43 pm GMT+7

Vietnam high-speed railway should run beyond Hanoi, HCMC on either side: lawmakers

Vietnam high-speed railway should run beyond Hanoi, HCMC on either side: lawmakers

Vietnam’s mega North-South high-speed railway project should be redesigned and extended beyond Hanoi and Ho Chi Minh City as currently planned, several lawmakers have suggested.

Infrastructure - Thu, November 21, 2024 | 6:11 pm GMT+7