Vietnam urged to start route-to-market process for offshore wind power goal
Vietnam urgently needs to embark on a route-to-market strategy to expedite the installation of over 6 gigawatts of offshore wind capacity by 2030 in the country as targeted in its latest power development plan, says the Global Wind Energy Council (GWEC).
To date, Vietnam has not initiated any true offshore wind projects and has only developed intertidal wind projects situated in close proximity to the shore; thus the target of installing 6 GW of offshore wind capacity by 2030 presents considerable challenges, the council says in its latest report.

The Dong Hai 1-Tra Vinh wind power project in Tra Vinh province, southern Vietnam. Photo courtesy of Trung Nam SMC.
GWEC highlighted that an offshore wind project needs six to eight years from greenfield to commercial operation date (COD), which was adopted by the Ministry of Industry and Trade (MoIT).
The MoIT estimates that the first pilot offshore wind project may not be completed until 2032.
“Consequently, connecting the first generation of offshore wind projects by 2030 necessitates the immediate establishment of policy and regulatory frameworks,” the council notes.
It elaborates that key components of the route-to-market process include implementing a simple remuneration mechanism for initial pilot projects; developing a streamlined permitting process to ensure timely implementation; developing a robust Marine Spatial Planning (MSP) and site allocation approach; defining a clear timeline for auction implementation; enhancing Power Purchase Agreement (PPA) bankability to attract international finance; and upgrading grid infrastructure for seamless offshore wind integration.
GWEC points out that recent developments signal significant progress in advancing offshore wind energy development in Vietnam. These include the submission of Marine Spatial Planning to the National Assembly; an MOIT draft proposal for the pilot mechanism of offshore wind projects, which includes the proposal for the State Energy Steering Committee (established in November 2023) to oversee the offshore wind projects.
Finally, the national Power Development Plan VIII (PDP VIII) implementation plan was issued in April 2024, determining regional allocations for offshore wind development, and the Draft Law on Electricity includes regulations for offshore wind power development.
Considering that the regulatory framework to support offshore wind development under PDP VIII is still underdeveloped, as well as the six-eight-year project development lead time, GWEC Market Intelligence believes that no real offshore wind development will take place until route-to-market policies and potentially new law(s) are in place.
GWEC expects Vietnam to miss its 2030 offshore wind target.
In recent years, GWEC has actively engaged with industry stakeholders and the Vietnamese government, facilitating dialogue through regular taskforce and working group meetings, as well as closed-door bilateral discussions. These efforts have been instrumental in gathering industry feedback and sharing crucial insights for advancing offshore wind development in Vietnam.
GWEC and its members will continue to work with governments to make this workable for the whole offshore wind industry, it adds.
- Read More
First turbine of central Vietnam thermal power plant inaugurated
The first turbine of the Vung Ang II thermal power plant was inaugurated on Thursday at Vung Ang Economic Zone in Ha Tinh province.
Companies - Fri, September 19, 2025 | 8:53 pm GMT+7
Vietnam, Japan firms forge strategic alliance to form cold-chain logistics hub
Toan Phat Logistics Joint Stock Company (TPL) on Thursday signed a strategic alliance with Japan’s Kawanishi Warehouse Co., Ltd and MOL Logistics Co., Ltd - a member of Mitsui O.S.K. Lines - to create the Mekong Logistics Hub, designed to pioneer a closed-loop and comprehensive cold-chain system in Vietnam.
Companies - Fri, September 19, 2025 | 8:46 pm GMT+7
Vietnam’s pilot of crypto trading market a bold step towards global fintech standards: experts
The Vietnamese Government’s resolution on the five-year crypto trading market pilot goes beyond keeping pace with global fintech trends to reflect the country’s pioneering role in setting international governance standards for this area, according to insiders.
Companies - Fri, September 19, 2025 | 8:36 pm GMT+7
Central Vietnam province Ha Tinh okays $644 mln wind power project
Ha Tinh province's authorities have green-lighted the 400MW Ky Anh wind power project with an investment of VND17 trillion ($644.37 million), which is set to go into operation in Q4/2028.
Energy - Fri, September 19, 2025 | 6:27 pm GMT+7
Emerging trends in Vietnam's real estate market
Analysts from Indochina Strategic, the real estate advisory arm of Indochina Capital (ICC), offer an insight into 10 emerging trends shaping Vietnam’s real estate M&A market in 2025.
Real Estate - Fri, September 19, 2025 | 4:58 pm GMT+7
Quang Ngai Sugar JSC expands power-sugar complex in central Vietnam
Gia Lai province's authorities have allowed Quang Ngai Sugar Joint Stock Company (UPCoM: QNS) to raise the capacity of its An Khe Biomass Power Plant project from 95 MW to 135 MW.
Energy - Fri, September 19, 2025 | 4:06 pm GMT+7
Lotte to 'terminate' Eco Smart City project in HCMC
Lotte Properties HCMC Co., Ltd. has sent a document to Ho Chi Minh City's Department of Finance announcing the termination of its $900 million Lotte Eco Smart City project in the Thu Thiem New Urban Area.
Real Estate - Fri, September 19, 2025 | 11:11 am GMT+7
Mining giant Vinacomin proposes coal processing, warehouse project in central Vietnam
State-owned Vinacomin, also called TKV, has proposed adjusting the Southeast Quang Tri Economic Zone planning to accommodate its VND800 billion ($30.32 million) coal processing and warehouse project.
Industries - Fri, September 19, 2025 | 8:31 am GMT+7
Vietnam, Russia eye setting up joint venture for maritime transport route
Vietnam and Russia are studying establishing a joint venture operator of a maritime transport route, underscoring their shared commitment to deepening cooperation in shipbuilding, logistics, and maritime infrastructure.
Companies - Thu, September 18, 2025 | 9:31 pm GMT+7
Coteccons consortium wins Long Thanh Airport contract worth $128 mln
HANTA2, a consortium of Coteccons Construction JSC, Hanoi Construction Corporation – JSC and ATAD Steel Structure Corporation, has won the bid for a construction package worth VND3.38 trillion ($128 million) at Long Thanh International Airport.
Companies - Thu, September 18, 2025 | 9:22 pm GMT+7
Vietnam PM orders full disbursement of public investment in 2025
Prime Minister Pham Minh Chinh has requested ministries, central agencies, and localities to ensure 100% disbursement of public investment capital in 2025.
Companies - Thu, September 18, 2025 | 9:18 pm GMT+7
EU, Indonesia to sign trade deal next week
The European Union and Indonesia have finalized a trade agreement that is expected to be signed on September 23.
Southeast Asia - Thu, September 18, 2025 | 9:06 pm GMT+7
The first project at VSIP Can Tho industrial park licensed
Can Tho city's export processing and industrial zones authorities have granted an investment registration certificate for the $100 million Bestway Can Tho sports technology plant project in Vinh Trinh commune.
Industries - Thu, September 18, 2025 | 9:04 pm GMT+7
Lego Manufacturing Vietnam signs direct power purchase agreement with VSIP
Lego Manufacturing Vietnam has signed a Direct Power Purchase Agreement (DPPA) with Vietnam-Singapore Industrial Park (VSIP) as part of the company's ambition to operate its new factory, which opened in April 2025, on 100% renewable energy.
Industries - Thu, September 18, 2025 | 4:07 pm GMT+7
Con Vanh golf course in northern Vietnam to debut in 2028
Huy Hoang Urban Development and Investment JSC aims to put its VND2,156 billion ($81.75 million) Con Vanh golf course project in Hung Yen province into operation in early 2028.
Real Estate - Thu, September 18, 2025 | 3:21 pm GMT+7
No new grade B office supply in HCMC’s CBD until 2028: Knight Frank
No new Grade B office supply is entering Ho Chi Minh City's central business district (CBD), marking a significant shift in the market as developers are forced to build affordable office space further afield, said Knight Frank Vietnam.
Real Estate - Thu, September 18, 2025 | 1:42 pm GMT+7