Electricity shortage looms as key power projects delayed
Difficulties are likely to linger despite Vietnam’s electricity supply efforts as new slow-moving power generation sources cannot match increasing demand, said an industry report.
This June and July - the peak of the dry season - are likely to witness power supply shortages, according to the National Steering Committee on Electricity Development's report on the implementation of projects in the amended National Power Development Plan (PDP VII).
During the peak of the dry season, hydropower plants in the country supply less, while electricity transmission from the southern and central regions to the north is limited due to the national transmission system, the report noted.
Though the central and southern regions have already managed enough electricity supply for the whole period of 2022 - 2025, there are likely cases in which electricity demand grow in line with a high development scenario or major planned power generation sources are behind schedule, it added.
The Van Phong 500 kV transformer station is under construction in Khanh Hoa province, central Vietnam. Photo courtesy of Vietnam News Agency.
As for updates on the situation across the country, the report said work has started on the expansion project of Hoa Binh hydropower plant in the north, invested by state utility Vietnam Electricity (EVN). Some landslides at the foundation have just taken place, requiring time to fix, but construction would resume soon.
In the central region, work started this May on the expansion of the Ialy hydropower plant. However, the project has fallen behind schedule due to procedures needed for changing land use purposes. Quang Trach 1 thermal power plant is also under construction, expected to begin commercial operations in 2025.
A number of projects are implementing investment steps, including Quang Trach 2 thermal power plant, expected to switch from coal-fired to gas-fired power and raise its capacity from 1,200 MW to 3,000 MW; O Mon power center, which includes the O Mon 3 thermal power plant proposed for official development assistance loans, the O Mon 4 coal-fired plant that has completed international bidding procedures for its EPC package; Dung Quat power center that includes Dung Quat 1 and 2 thermal power plants; Tri An hydropower plant expansion; and Bac Ai hydropower generation and storage project.
Petrovietnam is currently carrying out nine major projects with a total capacity of 8,100 MW, but all are facing obstacles, therefore they cannot be completed as scheduled, according to the report.
It detailed that Thai Binh 2 thermal power plant is dealing with legal difficulties and has completed its first oil burning and connected to the national grid. Song Hau 2 thermal power has completed 99.99% and signed a power purchase agreement to prepare for commercial operations. Long Phu 1 thermal power plant is undergoing some negotiations with subcontractors in construction.
State-run mining group Vinacomin is implementing four projects with a total capacity of 2,950 MW, but they are facing some obstacles. Among these, Cam Pha 3 and Hai Phong 3 projects cannot continue.
The Ministry of Industry and Trade is also managing and monitoring 20 thermal power plant projects, carried out in the build-operate-transfer (BOT) form, with a total capacity of 26,000 MW. Six have been put into commercial operation, two others are under construction, two projects have signed BOT contracts and the investors are making financial arrangements.
The 10 others are independent power plant (IPP) projects, designed with a total capacity of 11,092 MW, but all have fallen behind schedule, according to the report.
According to the committee, the country’s total installed power generation capacity has so far reached 76,620 megawatts, almost 7,500 MW higher than in 2020. Of the supply, renewables account for 27% with 20,670 MW.
- Read More
Consortium proposes three wastewater plant projects in HCMC
A consortium comprising three Vietnamese companies - Petrosetco, Gelex Infrastructure and Viconship - has proposed three major wastewater treatment projects in Ho Chi Minh City, highlighting growing private-sector interest in environmental infrastructure.
Industries - Tue, April 21, 2026 | 8:00 am GMT+7
Vietnam: Energy shock clouds the outlook for 2026
The most difficult period will be in Q2 and Q3/2026 as high global energy prices (and limited supplies) hit their peaks before easing toward end-2026, write UOB analysts in their latest report on Vietnam economic forecasts released last Friday.
Economy - Mon, April 20, 2026 | 5:22 pm GMT+7
Vietnam's top retailer MWG targets 30% profit growth this year, $10 bln sales by 2030
Mobile World Investment Corporation (HoSE: MWG) set net profit goal at VND9.2 trillion ($349.4 million) this year, up 30% year-on-year, as the leading Vietnamese retailer accelerates separate plans for its core subsidiaries.
Companies - Mon, April 20, 2026 | 4:52 pm GMT+7
Steel giant Hoa Phat inaugurates $76 mln steel pipe plant in southern Vietnam
Vietnam’s conglomerate Hoa Phat Group (HoSE: HPG) on Saturday inaugurated a new steel pipe plant in the southern province of Tay Ninh with an investment of VND2 trillion ($75.6 million), as the country’s top steelmaker expands capacity to capture recovering demand in construction and infrastructure.
Industries - Mon, April 20, 2026 | 3:01 pm GMT+7
DNSE margin lending and advance receivables up nearly 40% year-on-year
Brokerage DNSE Securities JSC reported operating revenue of more than VND395 billion ($15 million) in the first quarter of 2026, up 62% from a year earlier, driven by strong growth in margin lending and advances on securities sales.
Companies - Mon, April 20, 2026 | 1:47 pm GMT+7
Major corporations back Ho Chi Minh City Venture Capital Fund
Several large regional and Vietnamese corporations have become founding shareholders of the Ho Chi Minh City Venture Capital Fund, launched last Friday as part of efforts to boost early-stage financing for startups.
Finance - Mon, April 20, 2026 | 1:40 pm GMT+7
Foreign investors hold over 10% stake in CAEX after capital hike
Vietnam Prosperity Crypto Asset Exchange JSC (CAEX) has completed a capital increase from VND25 billion to VND10 trillion ($380 million), with foreign investors holding a 10.6% stake.
Finance - Mon, April 20, 2026 | 8:00 am GMT+7
Are foreign capital flows gradually returning to Vietnamese stocks?
Foreign investors have remained net sellers of more than VND6.63 trillion ($251.76 million) on Vietnam’s stock market since April 8, though several sessions of net buying have re-emerged, with most of the net selling concentrated in a handful of large-cap stocks such as VIC, VHM and VPL.
Finance - Mon, April 20, 2026 | 7:30 am GMT+7
Military Bank seeks to make foreign corporate clients a key growth driver
Military Bank (HoSE: MBB) has applied to set up representative offices in Singapore, South Korea, Taiwan and mainland China as the Vietnamese lender seeks to make foreign corporate clients a key growth driver.
Banking - Sun, April 19, 2026 | 3:21 pm GMT+7
HCMC calls for investment in dozens of mega projects for 2026-2030
Ho Chi Minh City is seeking investment for a wide range of large-scale projects worth trillions of VND (VND1 trillion = $37.97 million) across key sectors in the 2026-2030 period, as the Vietnamese metropolis accelerates its transformation into a high-tech, logistics and services hub.
Investing - Sun, April 19, 2026 | 11:00 am GMT+7
HCMC eyes $1.67 bln Long Thanh-Ho Tram expressway to boost tourism connectivity
Authorities in Ho Chi Minh City have proposed a VND44 trillion ($1.67 billion) expressway linking the city's Ho Tram tourism hub with Long Thanh Internatipnal Airport in neighboring Dong Nai province, aiming to strengthen regional connectivity and unlock the tourism potential of Vietnam’s southeastern coast.
Infrastructure - Sun, April 19, 2026 | 8:00 am GMT+7
Vietnam welcomes US investment in energy, technology, telecom infrastructure: Prime Minister
Vietnam will create the most favorable conditions and accelerate reforms to help U.S. businesses expand and succeed in the country, Prime Minister Le Minh Hung said during a Thursday meeting with 52 leading American companies.
Economy - Sat, April 18, 2026 | 3:12 pm GMT+7
Sun Group proposes $1.1 bln administrative hub project in Ho Chi Minh City
A unit of Vietnam's leading real estate developer Sun Group has proposed a nearly VND29.59 trillion ($1.12 billion) investment to develop a new administrative center and central square in Ho Chi Minh City's Thu Thiem new urban area, marking one of the most ambitious urban governance projects in the metropolis in recent years.
Real Estate - Sat, April 18, 2026 | 12:44 pm GMT+7
Moc Chau Milk's Q1 profit jumps 68% as margin gains signal strong start to 2026
Moc Chau Milk (HoSE: MCM), the oldest dairy firm in Vietnam, reported a sharp rebound in profitability in the first quarter of 2026, with net profit rising 67.7% year-on-year to VND80.1 billion ($3.04 million), driven by improved margins and stronger core operations.
Companies - Sat, April 18, 2026 | 10:07 am GMT+7
Firms with hundreds of thousands of shareholders signal strong expansion of Vietnam’s stock market
A sharp rise in investor participation is not only reflected in a surge of new brokerage accounts, but also in the rapidly expanding shareholder bases of listed companies.
Finance - Sat, April 18, 2026 | 8:00 am GMT+7
Gemadept, CMA CGM start work on phase 2 of flagship port in HCMC
Vietnam’s leading port and logistics operator Gemadept (HoSE: GMD) and its strategic French partner CMA CGM have broken ground on phase two of the Gemalink deep-water port in Ho Chi Minh City, as cargo volumes and vessel sizes continue to expand.
Infrastructure - Fri, April 17, 2026 | 9:14 pm GMT+7




















