Quality, capacity hamper wind farms in Gia Lai

By Ngoc Tan
Thu, June 9, 2022 | 10:44 am GMT+7

Five completed wind power projects in Gia Lai cannot start commercial operations due to some quality issues and lower-than-expected electricity transmission capacity in the Central Highland province.

The five projects are Ia Pech 2, Song An, Yang Trung, with two belonging to wind power development company Chu Prong Gia Lai.

Both Chu Prong Gia Lai projects are hampered by a dysfunctional 110kV transmission line and transformer station.

Meanwhile, the Ia Pech project registered for commercial operations with 12 turbines, but only five turbines were qualified in testing, according to the Gia Lai Department of Industry and Trade. Projects Ia Pech 2 (two turbines), Song An (five turbines), and Yang Trung (one turbine) have registered for commercial operations but all failed when tested.

A wind power project in Gia Lai province, Central Highlands is completed but has not been put into operation. Photo by The Investor/Ngoc Tan.

A wind power project in Gia Lai province, Central Highlands is completed but has not been put into operation. Photo by The Investor/Ngoc Tan.

A recent report from the department said 11 out of 16 wind power projects in the province have to date started commercial operations with a total capacity of 563 megawatts installed, or 47% of the total designed figure.

Pham Van Binh, director of the department, said that projects completed after October 31, 2021 - the deadline for Vietnam’s feed-in tariff (FIT) mechanism - cannot operate because they have not been approved. He added the Ministry of Industry and Trade has not issued a new pricing scheme for selling and buying electricity, making them unable to switch on.

A project investor who asked not to be named told The Investor, "It is very difficult for investors in this situation as they have to bear financial pressure and capital costs while the projects are unable to operate. We expect the ministry will soon announce the new pricing mechanism to solve our problems and save national resources."

Apart from Gia Lai, other wind power projects across the country are waiting for a commercial operation day (COD). According to Ministry of Industry and Trade statistics, as of October 31, 2021, there were only 69 wind power projects with a total capacity of 3,298.95 MW recognized with COD nationwide. Compared to 106 projects with a total capacity of 5,655.5 MW registered, about 2,300 MW are missing.

Of this, about 1,000 MW of wind power has completed investment but failed to enjoy the FIT and is still waiting for a new pricing mechanism.

Comments (0)
  • Read More
'Tunnel king' Deo Ca plans to invest over $3.7 billion in building roads

'Tunnel king' Deo Ca plans to invest over $3.7 billion in building roads

“Tunnel king” Deo Ca Group plans to build about 400km of highways and ring roads with a total investment of more than VND94,000 billion ($3.7 billion) by 2030.

Companies - Sat, April 27, 2024 | 5:17 pm GMT+7

Real estate major DIC plans high-end medical centers for Vietnam expats

Real estate major DIC plans high-end medical centers for Vietnam expats

Real estate major DIC Corp has plans to build facilities offering advanced medical care for long-term expat residents in the central province of Thanh Hoa and the southern province of Ba Ria-Vung Tau.

Companies - Sat, April 27, 2024 | 4:40 pm GMT+7

Vietnam-based Boviet Solar to invest $294 mln in photovoltaics plant in US

Vietnam-based Boviet Solar to invest $294 mln in photovoltaics plant in US

Vietnam-based Boviet Solar Technology Co. Ltd. (Boviet Solar) will invest $294 million in a photovoltaics (PV) factory in Pitt County, North Carolina, the United States.

Energy - Sat, April 27, 2024 | 12:28 pm GMT+7

FPT Retail turns profitable after four consecutive quarterly losses

FPT Retail turns profitable after four consecutive quarterly losses

FPT Digital Retail JSC, known as FPT Retail, posted VND39 billion ($1.54 million) in consolidated net profit in the first quarter of 2024, marking a return to profitability after four consecutive quarters of losses.

Companies - Sat, April 27, 2024 | 10:20 am GMT+7

Agriculture major PAN Group to pay 5% cash dividend

Agriculture major PAN Group to pay 5% cash dividend

Leaders of PAN Group JSC, listed on the HCMC Stock Exchange (HoSE) as PAN, proposed paying a cash dividend of 5% this year and beyond at the company's AGM on Friday.

Companies - Sat, April 27, 2024 | 9:53 am GMT+7

Japan’s Sojitz invests in Vietnam cashless payment firm Finviet

Japan’s Sojitz invests in Vietnam cashless payment firm Finviet

Japanese conglomerate Sojitz Corporation has invested an undisclosed amount in Finviet Technology Corporation, a software as a service (SaaS) company in Vietnam that provides cashless payment smartphone apps and an online ordering platform for small retail stores.

Companies - Sat, April 27, 2024 | 9:36 am GMT+7

Real estate businesses’ cash flow worst in five years: expert

Real estate businesses’ cash flow worst in five years: expert

Real estate developers are experiencing their worst cash flow in five years as the property market is facing several economic hurdles, said Dinh The Hien, head of the Institute of Information and Business Research.

Real Estate - Sat, April 27, 2024 | 7:46 am GMT+7

Former Binh Thuan province chairman detained for state asset management violations

Former Binh Thuan province chairman detained for state asset management violations

The Ministry of Public Security's investigative agency has launched legal proceedings against and arrested Le Tien Phuong, former chairman of Binh Thuan province for the 2011-2016 term.

Politics - Fri, April 26, 2024 | 9:41 pm GMT+7

Vietnam central bank to keep interest rate steady: deputy governor

Vietnam central bank to keep interest rate steady: deputy governor

The State Bank of Vietnam (SBV), the country’s central bank, will continue to keep policy interest rates unchanged at present and in the coming time, affirmed its deputy governor Dao Minh Tu.

Banking - Fri, April 26, 2024 | 9:11 pm GMT+7

Nam Kim Steel builds $178 mln factory in southern Vietnam

Nam Kim Steel builds $178 mln factory in southern Vietnam

Ho Minh Quang, chairman of Nam Kim Group, says work is proceeding space on the VND4.5 trillion ($177.55 million) Phu My steel roofing factory in Ba Ria-Vung Tau province and it should become operational in Q4/2025 or Q1/2026.

Companies - Fri, April 26, 2024 | 5:57 pm GMT+7

Vietnam parliament chairman Vuong Dinh Hue to step down

Vietnam parliament chairman Vuong Dinh Hue to step down

The Party Central Committee has accepted the resignation of Vuong Dinh Hue, a member of the Poliburo - the country's highest decision-making body, and chairman of the National Assembly.

Politics - Fri, April 26, 2024 | 5:05 pm GMT+7

Nvidia keen on building AI center, relocating GPU production in Vietnam

Nvidia keen on building AI center, relocating GPU production in Vietnam

Nvidia is keen on working with Vietnamese authorities to establish a training-research-development center for artificial intelligence (AI), install super computers, and relocate part of its graphics processing unit (GPU) production to the country.

Industries - Fri, April 26, 2024 | 4:56 pm GMT+7

Japan energy firm Erex eyes 50 MW biomass power plant in northern Vietnam

Japan energy firm Erex eyes 50 MW biomass power plant in northern Vietnam

Japanese renewable energy firm Erex Co., Ltd. plans to build a 50-MW biomass power plant in the northern mountainous province of Lao Cai, Erex representative director and president Honna Hitoshi said Wednesday.

Energy - Fri, April 26, 2024 | 3:30 pm GMT+7

New stock trading system KRX unable to go-live on May 2: regulator

New stock trading system KRX unable to go-live on May 2: regulator

The State Securities Commission (SSC) has rejected the Ho Chi Minh Stock Exchange’s (HoSE) proposal to officially operate a new stock trading system called KRX on May 2, citing some securities firms as saying that there were errors during the testing process.

Finance - Fri, April 26, 2024 | 3:05 pm GMT+7

New expressway shortens Hanoi-Nghe An travel time to three hours by car

New expressway shortens Hanoi-Nghe An travel time to three hours by car

The Dien Chau-Bai Vot Expressway will be opened to traffic on Sunday, shortening the travel time between Hanoi and Vinh town, capital of Nghe An province, from five hours and a half by car to three hours.

Infrastructure - Fri, April 26, 2024 | 12:00 pm GMT+7

Dairy giant Vinamilk targets 5% pre-tax profit growth in 2024

Dairy giant Vinamilk targets 5% pre-tax profit growth in 2024

Vietnamese dairy giant Vinamilk aims to earn VND63.16 trillion ($2.5 billion) in revenue and VND11.5 trillion ($453.92 million) in pre-tax profit this year, up 4.4% and 5.1% year-on-year, respectively, CEO Mai Kieu Lien said on Thursday.

Companies - Fri, April 26, 2024 | 11:53 am GMT+7