Tender for Long Thanh airport terminal extended due to tight deadline

By Dinh Nguyen, Huong Dung
Tue, May 2, 2023 | 2:46 pm GMT+7

The selection of a contractor to build the passenger terminal at Long Thanh International Airport, a key national project, is facing challenges because none of the applicants have been able to commit to meeting the construction deadline.

The Airports Corporation of Vietnam (ACV), the main investor of Long Thanh International Airport in the southern province of Dong Nai, which borders Ho Chi Minh City, has announced that the second bidding invitation for Package No. 5.10 “Construction and Equipment Installation for the Passenger Terminal Building” has been extended to June 12 this year instead of April 28.

The key package includes design, construction, and equipment installation for the terminal. With a total investment of VND35.23 trillion ($1.49 billion), it is the biggest package for the first phase of the airport.

It was planned to take 990 days, or 33 months, including weekends, holidays, and the Lunar New Year (Tet) holiday from the effective date of the contract.

According to ACV, the extension of the bidding invitation aims to attract more capable contractors. The bidding invitation was previously rescheduled from March 28 to April 28.

The construction site of Long Thanh Internatinal Airport project in Dong Nai province, southern Vietnam. Photo by The Investor/Hoang Long.

The construction site of Long Thanh Internatinal Airport project in Dong Nai province, southern Vietnam. Photo by The Investor/Hoang Long.

In his April 18 dispatch, Prime Minister Pham Minh Chinh noted the slow progress of the airport's main component projects: "It is necessary to clearly identify the causes and specific responsibilities of all stakeholders and handle them in accordance with Party and State regulations. Timely measures need to be taken to accelerate the project's progress."

The PM requested the Ministry of Transport and the Commission for the Management of State Capital at Enterprises to urgently direct the assessment of ACV's project implementation capacity and clarify the responsibilities of organizations and individuals in holding the tender for Package 5.10.

The cabinet leader emphasized the need for effective and feasible plans to select a capable contractor in May 2023.

The airport project has a total estimated investment of VND336.63 trillion ($14.12 billion), with three phases. The first phase, costing VND110 trillion, will include a runway, passenger terminal and auxiliary works capable of serving 25 million passengers a year.

In the second phase, an additional runway and terminal will be built to reach a capacity of 50 million passengers a year. The remaining items will be completed in the third phase to reach a capacity of 100 million.

Work began in 2021 and the new airport is set to open in 2025. The second phase is scheduled for completion by 2050.

Covering more than 5,580 hectares in Long Thanh district, about 40 kilometers east of HCMC, the new airport is expected to help ease overloading at Tan Son Nhat International Airport in HCMC, Vietnam’s southern economic hub.

However, given the phase 1 deadline of 33 months, the airport is unlikely to open on time.

On September 24, 2022, ACV first issued tender invitations for the passenger terminal. However, when the bidding closed on November 8, it was found that related files were not qualified under Article 17 of the Law on Bidding. Thus, the corporation extended the deadline for bids to the end of November.

ACV then received only one bid from a consortium of companies: Coteccons, Vinaconex, Centra, Phuc Hung Holdings, REE, Hoa Binh Construction, and Hawee. It decided to cancel the bidding in mid-December as the dossier did not meet all the requirements.

According to ACV's deputy general director Do Tat Binh, also head of the management board of the Long Thanh International Airport project, some contractors claimed that the contract implementation time of 33 months is too short for the contractor to complete such a large package.

Therefore, ACV has extended the duration to complete the airport’s passenger terminal by six months, from 33 to 39, after consulting foreign consultants, Binh said.

Inspecting the project on March 16, Deputy Prime Minister Tran Hong Ha affirmed that the Long Thanh airport is a work of the century. "Therefore, its contractors must be those who have ever done large works in the world."

He assigned ACV to take responsibility before the government for selecting capable and experienced contractors to carry out bidding packages to ensure the project quality, progress and efficiency.

Comments (0)
  • Read More
Vietnam aims to finalize negotiations for Ninh Thuan 1 nuclear power plant by August

Vietnam aims to finalize negotiations for Ninh Thuan 1 nuclear power plant by August

The Vietnamese government targets completing negotiations for Ninh Thuan 1 nuclear power plant in former Ninh Thuan province (now Khanh Hoa) by August 2025, and for Ninh Thuan 2 by May 2026 at the latest.

Energy - Fri, August 8, 2025 | 4:18 pm GMT+7

Software giant SAP invests $175 ml in R&D center in Vietnam

Software giant SAP invests $175 ml in R&D center in Vietnam

German software heavyweight SAP has officially launched a research & development center in Vietnam, with plans to invest more than €150 million ($175 million) over the next five years.

Industries - Fri, August 8, 2025 | 3:43 pm GMT+7

Carlsberg’s $130 mln plant expansion in central Vietnam set to start brewing next month

Carlsberg’s $130 mln plant expansion in central Vietnam set to start brewing next month

The expansion of Carlsberg’s brewery in Hue city, central Vietnam, with an investment of over VND3.4 trillion ($129.66 million), has entered trial runs and is scheduled to begin full production in September, Carlsberg Vietnam said.

Industries - Fri, August 8, 2025 | 2:43 pm GMT+7

Indonesia promotes nickel-based EV battery production

Indonesia promotes nickel-based EV battery production

Indonesia is advocating regulations to encourage electric vehicle (EV) manufacturers to switch from the commonly used lithium-based batteries to nickel-based ones.

Southeast Asia - Fri, August 8, 2025 | 1:54 pm GMT+7

BRICS countries account for over 35% of Malaysia’s total foreign trade turnover

BRICS countries account for over 35% of Malaysia’s total foreign trade turnover

Malaysia’s trade with BRICS nations climbed to RM818 billion ($193.47 billion) in 2024, making up 35.2% of the country’s total global trade, according to the Ministry of Investment, Trade and Industry (MITI).

Southeast Asia - Fri, August 8, 2025 | 1:52 pm GMT+7

Vietnam consumer finance major F88’s stock hits ceiling price on UPCoM debut

Vietnam consumer finance major F88’s stock hits ceiling price on UPCoM debut

The stock of F88 Investment JSC (F88), a leading consumer finance company in Vietnam, hit its ceiling price of VND888,800 ($34) on Friday, the first day of trading on the Unlisted Public Companies Market (UPCoM).

Companies - Fri, August 8, 2025 | 1:32 pm GMT+7

US tariff unlikely to dent Vietnam’s long-term FDI appeal: broker

US tariff unlikely to dent Vietnam’s long-term FDI appeal: broker

The U.S. tariff gap between Vietnamese goods and those from four other Southeast Asian countries would not erode Vietnam’s competitive edge in manufacturing and investment, said Hanoi-based Vietcombank Securities (VCBS).

Economy - Fri, August 8, 2025 | 12:24 pm GMT+7

Land clearance for Vietnam's North-South high-speed railway project to start on December 19

Land clearance for Vietnam's North-South high-speed railway project to start on December 19

Prime Minister Pham Minh Chinh has requested localities to start land clearance en masse for the gigantic North-South high-speed railway project on December 19.

Economy - Fri, August 8, 2025 | 11:52 am GMT+7

Vietnam might launch pilot digital asset exchange in August

Vietnam might launch pilot digital asset exchange in August

A digital asset exchange might be launched in August on a pilot basis, Deputy Minister of Finance Nguyen Duc Chi told a government press meeting on Thursday.

Finance - Fri, August 8, 2025 | 11:25 am GMT+7

Vietnam’s steel giant Hoa Sen spends $34 mln on land near Long Thanh airport for urban development

Vietnam’s steel giant Hoa Sen spends $34 mln on land near Long Thanh airport for urban development

Hoa Sen Group (HoSE: HSG), Vietnam’s top producer of coated steel products, has spent VND900 billion ($34.3 million) acquiring land for a major urban development project in the southern province of Dong Nai.

Real Estate - Fri, August 8, 2025 | 8:22 am GMT+7

Halal market presents major opportunities for Vietnamese businesses

Halal market presents major opportunities for Vietnamese businesses

The global Halal market is projected to reach $5 trillion by 2030, with Malaysia alone expected to hit $113.2 billion, said Shariza binti Abdul Rasheed, Halal product manager at Maybank Malaysia.

Economy - Thu, August 7, 2025 | 9:18 pm GMT+7

Steel major Hoa Phat to pour extra $130 mln into central Vietnam plant

Steel major Hoa Phat to pour extra $130 mln into central Vietnam plant

Vietnam’s leading steelmaker, Hoa Phat Group (HoSE: HPG), will increase investment in its Dung Quat 2 iron and steel production complex by VND3.4 trillion ($129.7 million) as part of an expansion plan.

Industries - Thu, August 7, 2025 | 8:03 pm GMT+7

Vietnam’s army-backed construction firm proposes 14 offshore wind power projects

Vietnam’s army-backed construction firm proposes 14 offshore wind power projects

Lung Lo Construction Corporation (LLC), under the Ministry of National Defense, has submitted investment proposals for 14 offshore wind power projects with a combined capacity of 9,000 MW.

Energy - Thu, August 7, 2025 | 5:07 pm GMT+7

Vietnam's agri major Hoang Anh Gia Lai fined for bond information disclosure failure

Vietnam's agri major Hoang Anh Gia Lai fined for bond information disclosure failure

Vietnam's agri major Hoang Anh Gia Lai JSC has been fined VND92.5 million ($3,528) for failing to disclose bond-related information as required by law.

Companies - Thu, August 7, 2025 | 4:31 pm GMT+7

Northern Vietnam province accelerates $2.2 bln LNG-to-power project

Northern Vietnam province accelerates $2.2 bln LNG-to-power project

Quang Ninh province will hand over 4.9 hectares of reclaimed land to the Quang Ninh LNG-fuelled power plant project before August 11, local authorities stated at a meeting on Wednesday.

Energy - Thu, August 7, 2025 | 4:17 pm GMT+7

Vietnam's seafood firms ride profit wave ahead of US tariff hike

Vietnam's seafood firms ride profit wave ahead of US tariff hike

Vietnam’s seafood companies reported surging profits in Q2/2025, driven by importers ramping up purchases ahead of new U.S. reciprocal tariffs.

Economy - Thu, August 7, 2025 | 2:21 pm GMT+7