Tender for Long Thanh airport terminal extended due to tight deadline

By Dinh Nguyen, Huong Dung
Tue, May 2, 2023 | 2:46 pm GMT+7

The selection of a contractor to build the passenger terminal at Long Thanh International Airport, a key national project, is facing challenges because none of the applicants have been able to commit to meeting the construction deadline.

The Airports Corporation of Vietnam (ACV), the main investor of Long Thanh International Airport in the southern province of Dong Nai, which borders Ho Chi Minh City, has announced that the second bidding invitation for Package No. 5.10 “Construction and Equipment Installation for the Passenger Terminal Building” has been extended to June 12 this year instead of April 28.

The key package includes design, construction, and equipment installation for the terminal. With a total investment of VND35.23 trillion ($1.49 billion), it is the biggest package for the first phase of the airport.

It was planned to take 990 days, or 33 months, including weekends, holidays, and the Lunar New Year (Tet) holiday from the effective date of the contract.

According to ACV, the extension of the bidding invitation aims to attract more capable contractors. The bidding invitation was previously rescheduled from March 28 to April 28.

The construction site of Long Thanh Internatinal Airport project in Dong Nai province, southern Vietnam. Photo by The Investor/Hoang Long.

The construction site of Long Thanh Internatinal Airport project in Dong Nai province, southern Vietnam. Photo by The Investor/Hoang Long.

In his April 18 dispatch, Prime Minister Pham Minh Chinh noted the slow progress of the airport's main component projects: "It is necessary to clearly identify the causes and specific responsibilities of all stakeholders and handle them in accordance with Party and State regulations. Timely measures need to be taken to accelerate the project's progress."

The PM requested the Ministry of Transport and the Commission for the Management of State Capital at Enterprises to urgently direct the assessment of ACV's project implementation capacity and clarify the responsibilities of organizations and individuals in holding the tender for Package 5.10.

The cabinet leader emphasized the need for effective and feasible plans to select a capable contractor in May 2023.

The airport project has a total estimated investment of VND336.63 trillion ($14.12 billion), with three phases. The first phase, costing VND110 trillion, will include a runway, passenger terminal and auxiliary works capable of serving 25 million passengers a year.

In the second phase, an additional runway and terminal will be built to reach a capacity of 50 million passengers a year. The remaining items will be completed in the third phase to reach a capacity of 100 million.

Work began in 2021 and the new airport is set to open in 2025. The second phase is scheduled for completion by 2050.

Covering more than 5,580 hectares in Long Thanh district, about 40 kilometers east of HCMC, the new airport is expected to help ease overloading at Tan Son Nhat International Airport in HCMC, Vietnam’s southern economic hub.

However, given the phase 1 deadline of 33 months, the airport is unlikely to open on time.

On September 24, 2022, ACV first issued tender invitations for the passenger terminal. However, when the bidding closed on November 8, it was found that related files were not qualified under Article 17 of the Law on Bidding. Thus, the corporation extended the deadline for bids to the end of November.

ACV then received only one bid from a consortium of companies: Coteccons, Vinaconex, Centra, Phuc Hung Holdings, REE, Hoa Binh Construction, and Hawee. It decided to cancel the bidding in mid-December as the dossier did not meet all the requirements.

According to ACV's deputy general director Do Tat Binh, also head of the management board of the Long Thanh International Airport project, some contractors claimed that the contract implementation time of 33 months is too short for the contractor to complete such a large package.

Therefore, ACV has extended the duration to complete the airport’s passenger terminal by six months, from 33 to 39, after consulting foreign consultants, Binh said.

Inspecting the project on March 16, Deputy Prime Minister Tran Hong Ha affirmed that the Long Thanh airport is a work of the century. "Therefore, its contractors must be those who have ever done large works in the world."

He assigned ACV to take responsibility before the government for selecting capable and experienced contractors to carry out bidding packages to ensure the project quality, progress and efficiency.

Comments (0)
  • Read More
Vietnam high-speed railway should run beyond Hanoi, HCMC on either side: lawmakers

Vietnam high-speed railway should run beyond Hanoi, HCMC on either side: lawmakers

Vietnam’s mega North-South high-speed railway project should be redesigned and extended beyond Hanoi and Ho Chi Minh City as currently planned, several lawmakers have suggested.

Infrastructure - Thu, November 21, 2024 | 6:11 pm GMT+7

Vietnam-Malaysia relationship upgraded to comprehensive strategic partnership

Vietnam-Malaysia relationship upgraded to comprehensive strategic partnership

Vietnam and Malaysia have upgraded their relationship to a comprehensive strategic partnership, the highest level in the former’s diplomatic hierarchy.

Politics - Thu, November 21, 2024 | 5:21 pm GMT+7

Petrovietnam units sign LNG supply deal for trial run of Vietnam’s first LNG power plants

Petrovietnam units sign LNG supply deal for trial run of Vietnam’s first LNG power plants

PV Power and PV Gas, two units of state-owned Petrovietnam, have signed an LNG supply deal for trial operation of Nhon Trach 3 and Nhon Trach 4, Vietnam’s first LNG-to-power plants.

Energy - Thu, November 21, 2024 | 4:40 pm GMT+7

Sufficient first phase funds ensured for Vietnam’s new mega airport: transport minister

Sufficient first phase funds ensured for Vietnam’s new mega airport: transport minister

Minister of Transport Nguyen Van Thang affirmed Wednesday that funding would be secured for building the Long Thanh International Airport, set to become Vietnam’s biggest.

Infrastructure - Thu, November 21, 2024 | 3:53 pm GMT+7

VAFIE to organize workshop on amendments to horse racing, football betting rules

VAFIE to organize workshop on amendments to horse racing, football betting rules

The Vietnam’s Association of Foreign Invested Enterprises (VAFIE) and The Investor will organize a workshop on suggestions to amend the government’s Decree 06 on horse racing, greyhound racing and international football betting services.

Economy - Thu, November 21, 2024 | 2:38 pm GMT+7

Vietnam Politburo okays international, regional financial centers in HCMC, Danang

Vietnam Politburo okays international, regional financial centers in HCMC, Danang

Vietnam’s highest decision-making body, the Politburo, has greenlighted the establishment of an international financial center in Ho Chi Minh City and a regional financial center in the central city of Danang.

Economy - Thu, November 21, 2024 | 1:50 pm GMT+7

Singapore's Platinum Victory seeks to gain veto at Vietnam’s REE

Singapore's Platinum Victory seeks to gain veto at Vietnam’s REE

Singaporean fund Platinum Victory Pte. Ltd. has registered to buy more shares of Ho Chi Minh City-based utility firm Refrigeration Electrical Engineering Corporation (REE) to achieve the vetoing power in the latter.

Finance - Thu, November 21, 2024 | 11:29 am GMT+7

Posco keen on investing in Vietnam's $2.2 bln LNG power project

Posco keen on investing in Vietnam's $2.2 bln LNG power project

South Korea’s steelmaker Posco is eyeing to invest in the $2.2 billion Quynh Lap LNG-fired power plant project in Vietnam’s central province of Nghe An.

Energy - Thu, November 21, 2024 | 10:42 am GMT+7

Vietnam firm Hoa Lam to build $212 mln Aeon Mall in Mekong Delta

Vietnam firm Hoa Lam to build $212 mln Aeon Mall in Mekong Delta

The Mekong Delta city of Can Tho has accepted a subsidiary of private multi-sector Hoa Lam Group as the investor of the Aeon Mall Can Tho commerce and service center.

Industries - Thu, November 21, 2024 | 10:31 am GMT+7

Vietnam startup expert closes Monkey in Black coffee shop

Vietnam startup expert closes Monkey in Black coffee shop

Tung BT (Tran Thanh Tung), a popular startup expert and social media influencer, is closing his final coffee shop in Ho Chi Minh City, ending a 10-year journey of the "Monkey in Black" brand.

Companies - Thu, November 21, 2024 | 8:16 am GMT+7

Vietnam-Singapore ties set for elevation to comprehensive strategic partnership

Vietnam-Singapore ties set for elevation to comprehensive strategic partnership

Vietnam and Singapore will elevate bilateral ties to a comprehensive strategic partnership and Singaporean Prime Minister Lawrence Wong will visit Vietnam next year.

Politics - Wed, November 20, 2024 | 8:16 pm GMT+7

Vietnam’s Vingroup establishes robotics firms, with co-founder’s 2 sons as major shareholders

Vietnam’s Vingroup establishes robotics firms, with co-founder’s 2 sons as major shareholders

Vingroup, Vietnam’s largest private conglomerate by ecosystem, has set up a robotics unit as it moves to ramp up its industrial-high technology ecosystem.

Companies - Wed, November 20, 2024 | 6:17 pm GMT+7

E-commerce, digital platforms likely to pay taxes on behalf of their sellers in Vietnam

E-commerce, digital platforms likely to pay taxes on behalf of their sellers in Vietnam

E-commerce and digital platforms will have to declare and pay taxes on behalf of their sellers starting January 1, 2025, according to a draft amendment to the Law on Tax Administration.

Finance - Wed, November 20, 2024 | 5:37 pm GMT+7

Flexibility, adaptability key to effective leadership: PepsiCo Vietnam exec

Flexibility, adaptability key to effective leadership: PepsiCo Vietnam exec

In a rapidly changing world, leaders need to develop the skill of being “as flexible as seaweed,” says Nguyen Viet Ha, general director of PepsiCo Foods Vietnam.

Companies - Wed, November 20, 2024 | 3:52 pm GMT+7

Central Vietnam province okays $88 mln automobile part project

Central Vietnam province okays $88 mln automobile part project

Binh Thuan province's industrial zone authority on Tuesday granted an investment registration certificate to a $88 million project invested by Taiwan’s NeoSCM Limited.

Industries - Wed, November 20, 2024 | 3:44 pm GMT+7

Thai packaging firm Thantawan Industry makes inroad into Vietnam

Thai packaging firm Thantawan Industry makes inroad into Vietnam

Thantawan Industry Public Company Limited, a leading Thai manufacturer of premium plastic packaging, has inked a deal for a 30-year factory lease, marking its inaugural investment in Vietnam.

Industries - Wed, November 20, 2024 | 3:34 pm GMT+7