Tender for Long Thanh airport terminal extended due to tight deadline

By Dinh Nguyen, Huong Dung
Tue, May 2, 2023 | 2:46 pm GMT+7

The selection of a contractor to build the passenger terminal at Long Thanh International Airport, a key national project, is facing challenges because none of the applicants have been able to commit to meeting the construction deadline.

The Airports Corporation of Vietnam (ACV), the main investor of Long Thanh International Airport in the southern province of Dong Nai, which borders Ho Chi Minh City, has announced that the second bidding invitation for Package No. 5.10 “Construction and Equipment Installation for the Passenger Terminal Building” has been extended to June 12 this year instead of April 28.

The key package includes design, construction, and equipment installation for the terminal. With a total investment of VND35.23 trillion ($1.49 billion), it is the biggest package for the first phase of the airport.

It was planned to take 990 days, or 33 months, including weekends, holidays, and the Lunar New Year (Tet) holiday from the effective date of the contract.

According to ACV, the extension of the bidding invitation aims to attract more capable contractors. The bidding invitation was previously rescheduled from March 28 to April 28.

The construction site of Long Thanh Internatinal Airport project in Dong Nai province, southern Vietnam. Photo by The Investor/Hoang Long.

The construction site of Long Thanh Internatinal Airport project in Dong Nai province, southern Vietnam. Photo by The Investor/Hoang Long.

In his April 18 dispatch, Prime Minister Pham Minh Chinh noted the slow progress of the airport's main component projects: "It is necessary to clearly identify the causes and specific responsibilities of all stakeholders and handle them in accordance with Party and State regulations. Timely measures need to be taken to accelerate the project's progress."

The PM requested the Ministry of Transport and the Commission for the Management of State Capital at Enterprises to urgently direct the assessment of ACV's project implementation capacity and clarify the responsibilities of organizations and individuals in holding the tender for Package 5.10.

The cabinet leader emphasized the need for effective and feasible plans to select a capable contractor in May 2023.

The airport project has a total estimated investment of VND336.63 trillion ($14.12 billion), with three phases. The first phase, costing VND110 trillion, will include a runway, passenger terminal and auxiliary works capable of serving 25 million passengers a year.

In the second phase, an additional runway and terminal will be built to reach a capacity of 50 million passengers a year. The remaining items will be completed in the third phase to reach a capacity of 100 million.

Work began in 2021 and the new airport is set to open in 2025. The second phase is scheduled for completion by 2050.

Covering more than 5,580 hectares in Long Thanh district, about 40 kilometers east of HCMC, the new airport is expected to help ease overloading at Tan Son Nhat International Airport in HCMC, Vietnam’s southern economic hub.

However, given the phase 1 deadline of 33 months, the airport is unlikely to open on time.

On September 24, 2022, ACV first issued tender invitations for the passenger terminal. However, when the bidding closed on November 8, it was found that related files were not qualified under Article 17 of the Law on Bidding. Thus, the corporation extended the deadline for bids to the end of November.

ACV then received only one bid from a consortium of companies: Coteccons, Vinaconex, Centra, Phuc Hung Holdings, REE, Hoa Binh Construction, and Hawee. It decided to cancel the bidding in mid-December as the dossier did not meet all the requirements.

According to ACV's deputy general director Do Tat Binh, also head of the management board of the Long Thanh International Airport project, some contractors claimed that the contract implementation time of 33 months is too short for the contractor to complete such a large package.

Therefore, ACV has extended the duration to complete the airport’s passenger terminal by six months, from 33 to 39, after consulting foreign consultants, Binh said.

Inspecting the project on March 16, Deputy Prime Minister Tran Hong Ha affirmed that the Long Thanh airport is a work of the century. "Therefore, its contractors must be those who have ever done large works in the world."

He assigned ACV to take responsibility before the government for selecting capable and experienced contractors to carry out bidding packages to ensure the project quality, progress and efficiency.

Comments (0)
  • Read More
Vietnam mulls opening door for private investment in small modular reactors

Vietnam mulls opening door for private investment in small modular reactors

Vietnam’s Ministry of Industry and Trade has drafted a parliamentary resolution that, for the first time, would allow private companies to participate in the development of small modular nuclear reactors (SMRs).

Energy - Fri, October 17, 2025 | 4:37 pm GMT+7

Kido seeks buyer for remaining 49% stake in frozen food affiliate

Kido seeks buyer for remaining 49% stake in frozen food affiliate

Kido Group (HoSE: KDC), a leading food company in Vietnam, has approved a plan to divest the firm's remaining 49% stake in its affiliate Kido Frozen Food JSC (Kido Foods).

Companies - Fri, October 17, 2025 | 4:25 pm GMT+7

Le Ngoc Quang appointed Danang city's Party chief

Le Ngoc Quang appointed Danang city's Party chief

Le Ngoc Quang, a Party Central Committee member and Party chief of Quang Tri province, has been appointed Party chief of Danang for the 2025-2030 term - the highest position in the city, central Vietnam's economic hub.

Politics - Fri, October 17, 2025 | 4:17 pm GMT+7

T&T Group seeks to reshape north-central Vietnam’s urban landscape with major projects

T&T Group seeks to reshape north-central Vietnam’s urban landscape with major projects

Multi-sector conglomerate T&T Group is developing a model eco-urban complex in Ha Tinh province and plans to build a massive 236-hectare urban area in neighboring Nghe An, with an aim to reshape north-central Vietnam's urban landscape.

Investing - Fri, October 17, 2025 | 2:44 pm GMT+7

Toyota plans $359 mln plant expansion in northern Vietnam

Toyota plans $359 mln plant expansion in northern Vietnam

Toyota Motor Vietnam (TMV) plans to invest about VND9.46 trillion ($359.2 million) in the first phase of its plant expansion project in Phu Tho province.

Investing - Fri, October 17, 2025 | 2:09 pm GMT+7

PVI Insurance sees 9-month profit before tax more than doubling

PVI Insurance sees 9-month profit before tax more than doubling

PVI Insurance has reaffirmed its position as the No. 1 non-life insurer in Vietnam, with total revenue increasing nearly 1.4 times in the first nine months of 2025 and pre-tax profit more than doubling year-on-year - surpassing its full-year targets for both revenue and profit.

Companies - Fri, October 17, 2025 | 9:08 am GMT+7

Vingroup to develop 4,600ha coastal urban project in northern Vietnam

Vingroup to develop 4,600ha coastal urban project in northern Vietnam

A consortium of Vingroup (HoSE: VIC) and its real estate arm Vinhomes (HoSE: VHM) will develop a 4,600-hectare coastal urban complex in Ha An ward, Quang Ninh province, following local authorities’ approval of a zoning plan.

Real Estate - Fri, October 17, 2025 | 8:30 am GMT+7

Indonesia resumes int’l carbon trading after 4-year hiatus

Indonesia resumes int’l carbon trading after 4-year hiatus

Indonesian President Prabowo Subianto has issued a new decree to restart international carbon emissions trading after a four-year hiatus.

Southeast Asia - Thu, October 16, 2025 | 9:23 pm GMT+7

Investors seek 2-year delay for $2.56 bln LNG power project in northern Vietnam, citing equipment hurdles

Investors seek 2-year delay for $2.56 bln LNG power project in northern Vietnam, citing equipment hurdles

Investors of a $2.56 billion LNG-fired power plant in Hung Yen province have proposed delaying the project’s commercial operation schedule by two years due to difficulties securing key equipment.

Energy - Thu, October 16, 2025 | 9:04 pm GMT+7

Vietnam to soon raise taxpayers' personal deduction: official

Vietnam to soon raise taxpayers' personal deduction: official

The personal income tax deduction in Vietnam is "very likely" to increase to VND21.7 million ($823,940) per month, including VND15.5 million (588,530) for the taxpayer and VND6.2 million ($235,410) for each dependent.

Finance - Thu, October 16, 2025 | 6:25 pm GMT+7

Business confidence climbs as reforms gain traction amid global headwinds: EuroCham Vietnam

Business confidence climbs as reforms gain traction amid global headwinds: EuroCham Vietnam

The index climbed to 66.5, surpassing pre-tariffs level and reaching its highest in three years – showcasing resilience and adaptability amid global headwinds and evolving U.S. tariff pressures.

Economy - Thu, October 16, 2025 | 4:36 pm GMT+7

Vietnam's stock market watchdog suspends two Grant Thornton auditors

Vietnam's stock market watchdog suspends two Grant Thornton auditors

Vietnam's State Securities Commission (SSC) has suspended two auditors from Grant Thornton Vietnam after determining that the 2024 audited financial statements of Saigon Water Infrastructure Corporation (HoSE: SII) failed to meet required standards.

Finance - Thu, October 16, 2025 | 3:35 pm GMT+7

Law No. 56 a major policy breakthrough for Vietnam's stock market development

Law No. 56 a major policy breakthrough for Vietnam's stock market development

The Law No. 56, effective January 1, 2025, is one of the major legal breakthroughs in recent years that will enhance the transparency and operational efficiency of the Vietnamese stock market.

Finance - Thu, October 16, 2025 | 2:30 pm GMT+7

WHA Group breaks ground on smart technology industrial zone in central Vietnam

WHA Group breaks ground on smart technology industrial zone in central Vietnam

Thailand's WHA Group on Tuesday broke ground on a world-class, modern, and environmentally friendly industrial zone in central Vietnam, namely the WHA Smart Technology Industrial Zone-Thanh Hoa.

Real Estate - Thu, October 16, 2025 | 2:00 pm GMT+7

Vietnam a key partner in Murphy Oil’s global strategy: exec

Vietnam a key partner in Murphy Oil’s global strategy: exec

Vietnam remains a key partner in Murphy Oil’s global business strategy, said Eric Hambly, the U.S. corporation's president and CEO.

Companies - Thu, October 16, 2025 | 12:06 pm GMT+7

VNPT, Qualcomm debut Vietnam’s 1st original design-based excellence center

VNPT, Qualcomm debut Vietnam’s 1st original design-based excellence center

State-owned Vietnam Posts and Telecommunications Group (VNPT) and Qualcomm have officially launched the VNPT-Qualcomm Excellence Center (VQEC), the first facility in the country to operate under an original design co-development model using Qualcomm’s core technologies.

Companies - Thu, October 16, 2025 | 8:41 am GMT+7