Bidding criteria for Long Thanh Airport terminal to remain unchanged
The Airports Corporation of Vietnam (ACV) will again issue tender invitations for the Long Thanh airport passenger terminal in March with contractor selection criteria and contract implementation period unchanged.
The information was revealed by ACV deputy general director Do Tat Binh, also head of the management board of the Long Thanh International Airport project in the southern province of Dong Nai, which borders Ho Chi Minh City.
Construction site of the Long Thanh International Airport project. Photo by The Investor/Pham Nguyen.
In December 2022, ACV canceled the first tender for Package No. 5.10 “Construction and Equipment Installation for the Passenger Terminal Building”. The VND35,233 billion ($1.49 billion) package includes design, construction, and equipment installation for the terminal. It is classed as the biggest package for the first phase of the airport.
It was planned to take 990 days, or 33 months, including weekends, holidays, and the Lunar New Year (Tet) holiday as prescribed by Vietnamese laws from the effective date of the contract.
In October 2022, ACV held a pre-bidding conference, with around 10 contractors from Germany, Japan, South Korea, China and Vietnam taking part. However, when the bidding closed on November 8, it was found that related files were not qualified under Article 17 of the Law on Bidding. Thus, ACV extended the deadline for bids to the end of November.
ACV then received only one bid from a consortium of companies: Coteccons, Vinaconex, Centra, Phuc Hung Holdings, REE, Hoa Binh Construction, and Hawee. It decided to cancel the bidding in mid-December as the dossier did not meet all the requirements.
"According to the law, we will invite bids again with the same criteria as the first tender," Binh told The Investor.
As the package has a huge value and includes multiple complex works, the selection of a capable contractor is very important, he said.
However, he also noted that the criteria are causing difficulties for bidders. For example, they are required to have completed the construction of an airport terminal or a special structure worth no less than VND14,093 billion ($601 million), which is rare in Vietnam.
The contract implementation time of 33 months also puts pressure on the contractor to complete such a large package, he added. However, Binh held that if the time is lengthened, the completion of the airport may miss the deadline set by the National Assembly and Government
"The cancellation of the package will not only delay the start of the passenger terminal in particular, but also affect the progress of the whole project," he noted.
According to the Ministry of Transport, site clearance for the airport project is behind schedule, with the passenger terminal, cargo terminal, runway, and aircraft apron facing procedural problems.
Inspecting the key national project on January 29, Prime Minister Pham Minh Chinh requested provincial authorities to complete the handover of ground for the first stage of construction by the end of the first quarter. “By the end of the second quarter, the sites for logistics and access roads for the airport must be ready,” the government leader said.
The PM asked relevant ministries and state agencies to urgently work on solutions to speed up the second tender. He demanded reports from concerned units on why the first bidding process failed, and reminded ACV to prepare alternatives to avoid a similar failure.
A key infrastructure project in southern Vietnam, Long Thanh International Airport has a designed capacity of 100 million passengers per year. It is expected to help ease overloading at Tan Son Nhat International Airport in HCMC. The new airport will cover more than 5,580 hectares in Dong Nai's Long Thanh district.
Construction work began in 2021 and the new airport is set to open in 2025. The second phase is scheduled for completion by 2050.
The new airport is located about 40 kilometers east of HCMC, Vietnam’s southern economic hub.
- Read More
VinEnergo ramps up renewable energy push with 4 new subsidiaries
VinEnergo, the energy arm of Vietnamese conglomerate Vingroup, has accelerated its expansion into the power sector, establishing four new subsidiaries within a week as it builds a growing portfolio of renewable energy and infrastructure projects across Vietnam.
Companies - Mon, June 15, 2026 | 4:52 pm GMT+7
Thaco deepens ties with Hyundai Rotem to localize railway manufacturing in Vietnam
Vietnamese conglomerate Thaco and South Korea’s Hyundai Rotem have signed a detailed technology transfer and localization agreement for railway rolling stock production.
Industries - Mon, June 15, 2026 | 4:01 pm GMT+7
UOB Vietnam appoints Pham Hong Hai as deputy country CEO
Singapore's United Overseas Bank (Vietnam) Limited on Monday appointed Pham Hong Hai, former CEO of HSBC Vietnam and later Vietnamese bank OCB, as deputy country CEO, effective immediately.
Banking - Mon, June 15, 2026 | 2:26 pm GMT+7
Shinhan Bank Vietnam launches AI translation desk, strengthening customer experience, digital innovation
Shinhan Bank Vietnam has officially launched AI Translation Desk, an AI-powered interpretation solution designed to help foreign customers communicate more easily while using banking services in Vietnam.
Banking - Mon, June 15, 2026 | 12:03 pm GMT+7
FDI listings a missing piece in Vietnam's stock market development
As Vietnam's stock market moves closer to its long-awaited upgrade to secondary emerging market status and seeks to attract higher-quality capital, allowing more foreign-invested companies to list on domestic exchanges could broaden the pool of investable assets and support the next phase of capital market development.
Finance - Mon, June 15, 2026 | 11:14 am GMT+7
Chinese robot 'eyes' manufacturer builds 10-hectare factory in northern Vietnam
Orbbec Inc., a Chinese company specializing in 3D vision sensors and robotic hardware, is building an over-10-hectare manufacturing center in the northern province of Bac Ninh to serve international markets.
Industries - Mon, June 15, 2026 | 8:00 am GMT+7
Long Thanh airport project faces shortage of 2,000 workers
The Long Thanh International Airport project in the southern province of Dong Nai is still short nearly 2,000 workers compared to actual requirements during its final acceleration phase.
Infrastructure - Sun, June 14, 2026 | 6:08 pm GMT+7
Nghi Son Refinery and Petrochemical Complex turns profitable in Q1 on full-capacity operations
Operating at full capacity, the Nghi Son Refinery and Petrochemical Complex in Vietnam's central province of Thanh Hoa reported its first profit in Q1/2026, marking a significant turnaround after years of losses.
Economy - Sun, June 14, 2026 | 2:45 pm GMT+7
50 years of Gamuda Berhad and its urban development journey in Vietnam
Celebrating 50 years of establishment and growth, Gamuda Berhad – one of Malaysia’s leading infrastructure and urban development groups – has evolved from an infrastructure specialist into an integrated urban developer with a growing presence across Asia.
Real Estate - Sun, June 14, 2026 | 11:21 am GMT+7
Industrials, technology top Vietnamese sectors in M&A transaction volume
Vietnam’s M&A market recorded 24 transactions in May, with industrials, technology and healthcare sectors being the most active sectors in terms of transaction volume, writes Grant Thornton analysts.
Consulting - Sun, June 14, 2026 | 9:00 am GMT+7
Top Vietnamese garment maker Vinatex's H1 profit rises 14%, weak order visibility clouds outlook
Vietnam National Textile and Garment Group (UPCoM: VGT) reported consolidated profit growth of 14.4% in the first half of 2026, driven by a strong recovery in its yarn business, even as weakening global demand and uncertainty over U.S. trade policy cast a shadow over the sector’s outlook.
Companies - Sun, June 14, 2026 | 8:00 am GMT+7
Gamuda Land Vietnam recognized among Top 10 Enterprises Pioneering Green Transformation 2025-2026
Gamuda Land Vietnam has been recognized as one of the “Top 10 Enterprises Pioneering Green Transformation 2025-2026” at the 25th Golden Dragon Awards.
Companies - Sat, June 13, 2026 | 7:45 pm GMT+7
T&T pushes ahead with $97 mln industrial park project, eyes new urban area projects in northern Vietnam
Vietnamese conglomerate T&T Group is seeking to accelerate five projects in Bac Ninh while proposing two new developments in this northern province.
Infrastructure - Sat, June 13, 2026 | 7:09 pm GMT+7
VinFast guns for 300,000 EV deliveries in 2026, spins off manufacturing operations
VinFast, the EV arm of Vietnamese conglomerate Vingroup (HoSE: VIC) targets at least 300,000 electric vehicle deliveries globally this year, up 52% year-on-year, while pursuing a restructuring plan aimed at improving capital efficiency, according to a report by Vietcap Securities.
Companies - Sat, June 13, 2026 | 3:07 pm GMT+7
Vietnam economy resilience amid cost pressures, external strains: UOB
The VND has stabilized in recent weeks, trading in a range of VND26,291-26,372 per U.S. dollars in April-May, well within the State Bank of Vietnam’s ±5% band. In a report released on Friday, UOB analysts say on balance, they retain a gradual depreciation bias for the USD/VND, with updated forecasts of 26,500 in Q3/2026, 26,400 in Q4/2026, 26,300 in Q1/2027, and 26,100 in Q2/2027.
Consulting - Sat, June 13, 2026 | 11:49 am GMT+7
Vietnam Politburo issues resolution on FDI sector development
The Politburo, Vietnam's highest decision-making body, has issued a resolution that establishes a new mindset in developing the FDI sector.
Economy - Sat, June 13, 2026 | 8:17 am GMT+7