Bidding criteria for Long Thanh Airport terminal to remain unchanged

By Dinh Nguyen, Huong Dung
Thu, February 2, 2023 | 3:01 pm GMT+7

The Airports Corporation of Vietnam (ACV) will again issue tender invitations for the Long Thanh airport passenger terminal in March with contractor selection criteria and contract implementation period unchanged.

The information was revealed by ACV deputy general director Do Tat Binh, also head of the management board of the Long Thanh International Airport project in the southern province of Dong Nai, which borders Ho Chi Minh City.

Construction site of the Long Thanh International Airport project. Photo by The Investor/Pham Nguyen.

Construction site of the Long Thanh International Airport project. Photo by The Investor/Pham Nguyen.

In December 2022, ACV canceled the first tender for Package No. 5.10 “Construction and Equipment Installation for the Passenger Terminal Building”. The VND35,233 billion ($1.49 billion) package includes design, construction, and equipment installation for the terminal. It is classed as the biggest package for the first phase of the airport.

It was planned to take 990 days, or 33 months, including weekends, holidays, and the Lunar New Year (Tet) holiday as prescribed by Vietnamese laws from the effective date of the contract.

In October 2022, ACV held a pre-bidding conference, with around 10 contractors from Germany, Japan, South Korea, China and Vietnam taking part. However, when the bidding closed on November 8, it was found that related files were not qualified under Article 17 of the Law on Bidding. Thus, ACV extended the deadline for bids to the end of November.

ACV then received only one bid from a consortium of companies: Coteccons, Vinaconex, Centra, Phuc Hung Holdings, REE, Hoa Binh Construction, and Hawee. It decided to cancel the bidding in mid-December as the dossier did not meet all the requirements.

"According to the law, we will invite bids again with the same criteria as the first tender," Binh told The Investor.

As the package has a huge value and includes multiple complex works, the selection of a capable contractor is very important, he said.

However, he also noted that the criteria are causing difficulties for bidders. For example, they are required to have completed the construction of an airport terminal or a special structure worth no less than VND14,093 billion ($601 million), which is rare in Vietnam.

The contract implementation time of 33 months also puts pressure on the contractor to complete such a large package, he added. However, Binh held that if the time is lengthened, the completion of the airport may miss the deadline set by the National Assembly and Government

"The cancellation of the package will not only delay the start of the passenger terminal in particular, but also affect the progress of the whole project," he noted.

According to the Ministry of Transport, site clearance for the airport project is behind schedule, with the passenger terminal, cargo terminal, runway, and aircraft apron facing procedural problems.

Inspecting the key national project on January 29, Prime Minister Pham Minh Chinh requested provincial authorities to complete the handover of ground for the first stage of construction by the end of the first quarter. “By the end of the second quarter, the sites for logistics and access roads for the airport must be ready,” the government leader said.

The PM asked relevant ministries and state agencies to urgently work on solutions to speed up the second tender. He demanded reports from concerned units on why the first bidding process failed, and reminded ACV to prepare alternatives to avoid a similar failure.

A key infrastructure project in southern Vietnam, Long Thanh International Airport has a designed capacity of 100 million passengers per year. It is expected to help ease overloading at Tan Son Nhat International Airport in HCMC. The new airport will cover more than 5,580 hectares in Dong Nai's Long Thanh district.

Construction work began in 2021 and the new airport is set to open in 2025. The second phase is scheduled for completion by 2050.

The new airport is located about 40 kilometers east of HCMC, Vietnam’s southern economic hub.

Comments (0)
  • Read More
Major industrial park developer Kinh Bac suffers setback with $3 mln Q1 loss

Major industrial park developer Kinh Bac suffers setback with $3 mln Q1 loss

Vietnamese industrial park developer Kinh Bac Urban Development Corporation recorded Q1/2024 losses of VND76.7 billion ($3 million), a setback considering its annual profit target of VND4,000 billion ($157.8 million).

Industrial real estate - Wed, May 1, 2024 | 3:51 pm GMT+7

Founder of Vietnam’s ACB bank passes away

Founder of Vietnam’s ACB bank passes away

Asia Commercial Bank founder Tran Mong Hung, father of the current chairman Tran Hung Huy, passed away Thursday. He was 72.

Banking - Wed, May 1, 2024 | 3:37 pm GMT+7

Singapore Management University opens office in HCMC

Singapore Management University opens office in HCMC

Singapore Management University (SMU) has chosen to open a representative office in Vietnam after Indonesia and Thailand as part of its vision to 2025.

Companies - Wed, May 1, 2024 | 3:18 pm GMT+7

Exhibition displays 300 artefacts of Dien Bien Phu Campaign

Exhibition displays 300 artefacts of Dien Bien Phu Campaign

The thematic exhibition named "Dien Bien Phu Victory - An Eternal Epic" showcases some documentaries and artefacts for the first time to the public about Dien Bien Phu Campaign.

Travel - Wed, May 1, 2024 | 3:02 pm GMT+7

Six dead as boiler explodes at southern Vietnam wood factory

Six dead as boiler explodes at southern Vietnam wood factory

Six persons including a Chinese national died and five others were injured after a boiler exploded Wednesday morning at a wooden products factory in Vinh Cuu district, Dong Nai province.

Society - Wed, May 1, 2024 | 2:55 pm GMT+7

Trungnam Group eyes green energy development in Ninh Thuan province

Trungnam Group eyes green energy development in Ninh Thuan province

Private Vietnamese conglomerate Trungnam Group plans to develop a green energy complex with an expected green hydrogen capacity of 824,400 tons per year in the south-central province of Ninh Thuan.

Energy - Wed, May 1, 2024 | 11:37 am GMT+7

S Korea's Jeil E&C to invest $35 mln in southern Vietnam high-tech logistics project

S Korea's Jeil E&C to invest $35 mln in southern Vietnam high-tech logistics project

Jeil E&C, a major South Korean construction-real estate business, will invest $35.4 million in a high-tech logistics project in Dong Nai province - an industrial hub in southern Vietnam.

Industries - Wed, May 1, 2024 | 9:34 am GMT+7

Brewer giant Habeco posts biggest quarterly loss in 4 years

Brewer giant Habeco posts biggest quarterly loss in 4 years

Habeco, among the top four brewers in Vietnam by market share, suffered a net loss of VND21 billion ($828,570) in the first quarter of 2024, up nearly sixfold from the same period last year.

Companies - Wed, May 1, 2024 | 7:00 am GMT+7

Retailer Mobile World Q1 profit rises 43 times after reshuffle

Retailer Mobile World Q1 profit rises 43 times after reshuffle

Mobile World Investment Corporation (MWG) reported an after-tax profit of nearly VND903 billion ($35.63 million) in the first quarter of 2024, a 43-fold increase year-on-year, according to the company’s financial statements.

Companies - Tue, April 30, 2024 | 9:09 pm GMT+7

Vietnam welcomes 6.2 mln foreign arrivals in Jan-Apr, 3.9% above pre-pandemic level

Vietnam welcomes 6.2 mln foreign arrivals in Jan-Apr, 3.9% above pre-pandemic level

Vietnam welcomed over 6.2 million foreign tourists in the first four months of this year, up 68.3% year-on-year, the General Statistics Office reported.

Travel - Tue, April 30, 2024 | 3:32 pm GMT+7

April 30 Victory – Glorious milestone in national history

April 30 Victory – Glorious milestone in national history

The Liberation of the South Day (April 30) is an occasion of great significance for all Vietnamese people.

Politics - Tue, April 30, 2024 | 3:10 pm GMT+7

$32 mln ecotourism project inaugurated in central Vietnam

$32 mln ecotourism project inaugurated in central Vietnam

Hang Gop Ecology Tourism JSC, a subsidiary of FVG Group, inaugurated its VND800 million ($31.56 million) Dong Giang Heaven Gate ecotourism project in Vietnam’s central province of Quang Nam on Sunday.

Travel - Tue, April 30, 2024 | 2:00 pm GMT+7

Dien Bien Phu Campaign's historic 3D panorama painting to be exhibited in Hanoi

Dien Bien Phu Campaign's historic 3D panorama painting to be exhibited in Hanoi

The impressive 3D panorama painting showcasing the Dien Bien Phu Campaign, which captivates visitors at the Dien Bien Phu Victory Museum in the northern province of Dien Bien, will now be exhibited in Hanoi using 3D mapping technology.

Travel - Tue, April 30, 2024 | 12:59 pm GMT+7

HCMC ready for spectacular fireworks display to celebrate national holidays

HCMC ready for spectacular fireworks display to celebrate national holidays

Ho Chi Minh City is getting ready for a spectacular fireworks display at five different locations to celebrate the Reunification Day on the night of April 30.

Travel - Tue, April 30, 2024 | 12:56 pm GMT+7

Vietnam’s FDI sector posts $16.64 bln trade surplus in Jan-Apr

Vietnam’s FDI sector posts $16.64 bln trade surplus in Jan-Apr

Foreign-invested enterprises in Vietnam recorded a trade surplus of $16.64 billion in the first four months of 2024, with crude oil activities factored into account, according to the General Statistics Office.

Economy - Tue, April 30, 2024 | 11:50 am GMT+7

Vietnam attracts $9.27 bln in registered FDI from Jan-Apr, Ba Ria-Vung Tau top recipient

Vietnam attracts $9.27 bln in registered FDI from Jan-Apr, Ba Ria-Vung Tau top recipient

Registered foreign direct investment (FDI) in Vietnam reached $9.27 billion in the year to April 22, while disbursed FDI hit $6.28 billion, the highest figure in the last five years.

Economy - Tue, April 30, 2024 | 10:43 am GMT+7