Long-delayed HCMC metro lines face even more delays

By Tuong Nguyen
Wed, October 12, 2022 | 8:22 am GMT+7

The prolonged delays to HCMC’s first and second metro lines are likely to extend even further, mired as they are in site clearance and funding problems, the transport ministry says.

In a new report to the government, the ministry (MoT) said the southern economic hub wants to complete Line 1 (Ben Thanh-Suoi Tien) in the fourth quarter of 2023 and Line 2 (Ben Thanh-Tham Luong) in 2030. The previous timeline for Line 1 was Q4/2021.

Line 1, estimated to cost over VND43.7 trillion ($1.89 billion), will run around 20 kilometers from the Ben Thanh area in District 1 to Long Binh Depot in Thu Duc city on HCMC’s outskirts.

Some railway wagons already in place for the unfinished Metro Line 1 project in HCMC. Photo courtesy of Legal newspaper.

Some railway wagons already in place for the unfinished Metro Line 1 project in HCMC. Photo courtesy of Legal newspaper.

According to the report, 92.2% of the construction of Line 1 has been completed and the ratio is expected to reach 93% by the end of this year, but site clearance is still not completed.

In terms of construction packages, the Ben Thanh-City Theater underground section is almost 97.2% complete; the City Theater-Bason Station underground section is almost 99.64% complete; the section of elevated railroads and depots is nearly 96.2% complete; and the package of locomotives, wagons, electric equipment, tracks and maintenance is about 83% complete.

There are three packages yet to start, namely the IT system for operations, the construction of operation and management offices, and the consulting package for the whole system’s safety.

The main reasons for further delays, according to the report, include more time needed for the HCMC administration to adjust the design, resolve contractor complaints, add additional costs and speed up site clearance work that has been very slow. Besides, the technologies used for Line 1 are completely new to Vietnam, and it is taking more time to learn.

"In addition, the work of making, appraising and approving the project's applications for more funding has taken a long time and but not been completed so far,” the ministry wrote in the report, citing another reason from the city administration.

The Line 2 project has seen even longer delays, according to the ministry. The project was originally approved for completion between 2010 and 2018, then adjusted to 2021-2026, and now to 2030.

The ministry report listed different reasons for the long delay, including site clearance problems. As of now, 85.15% of the site has been cleared, with the biggest remain obstacles lying in District 3, part of the central business district.

The consulting contract for the second metro line, signed in 2012 by the Management Authority for Urban Railways (MAUR) of HCMC and Implementation Consultant (IC), was terminated by an IC announcement this March.

The two-phase consulting contract expired in 2018 as stated in the agreement; and the consulting firm stopped supplying services for the first phase of the project. Then the MAUR had to end the second phase of the contract. In 2019, MAUR and IC held negotiations on Appendix 13 of the contract to complete the rest of the first phase. The negotiations lasted two years, but no consensus was reached.

In May 2021, the city decided to end Appendix No. 13 negotiations with IC. However, IC later proposed resuming negotiations to complete some main bidding packages. The city government assigned MAUR to get back to the negotiation table with IC. However, IC announced this March that it had ended the consulting contract.

The process of selecting a new consulting firm is ongoing, but the selection might last 12 to 18 months, according to city officials.

The Line 2 project, about 11 km long with 10 stations, is estimated to cost a total of VND47.89 trillion ($2.08 billion).

In all, HCMC has eight metro line projects planned with a combined length of 220 kilometers and estimated costs totaling almost $25 billion.

Comments (0)
  • Read More
Central Vietnam province plans to build $2.4 bln LNG power plant from 2031

Central Vietnam province plans to build $2.4 bln LNG power plant from 2031

The 4,800-MW Chan May LNG power plant, with an investment of $2.4 billion, can be deployed in 2031-2035, according to Thua Thien Hue authorities.

Energy - Thu, November 21, 2024 | 10:41 pm GMT+7

Indonesia, France step up cooperation in economy, defence

Indonesia, France step up cooperation in economy, defence

Indonesian President Prabowo Subianto discussed economic and defence cooperation during a bilateral meeting on Tuesday with French President Emmanuel Macron on the sidelines of the G20 Summit in Rio de Janeiro, Brazil, Antara reported.

Southeast Asia - Thu, November 21, 2024 | 10:25 pm GMT+7

Thai economy to maintain upward momentum in 2025

Thai economy to maintain upward momentum in 2025

The National Economic and Social Development Council of Thailand (NESDC) expects the Thai economy to sustain its upward momentum in 2025 with a growth of 2.3-3.3% despite growing risks.

Southeast Asia - Thu, November 21, 2024 | 10:24 pm GMT+7

Former parliament chairman Vuong Dinh Hue warned for violations

Former parliament chairman Vuong Dinh Hue warned for violations

The Politburo, Vietnam's supreme decision making body, on Wednesday issued warnings to Vuong Dinh Hue, former Chairman of the National Assembly, and Nguyen Van The, former Minister of Transport, for violations while on duties.

Politics - Thu, November 21, 2024 | 10:10 pm GMT+7

Sumitomo insists on building LNG power plant in central Vietnam

Sumitomo insists on building LNG power plant in central Vietnam

Japanese trading house Sumitomo has been pushing for a liquefied natural gas (LNG)-fed power plant investment in Vietnam’s central province of Khanh Hoa.

Energy - Thu, November 21, 2024 | 8:53 pm GMT+7

Vietnam’s Vinhomes fulfils 67% of record buyback plan

Vietnam’s Vinhomes fulfils 67% of record buyback plan

Vinhomes, the housing development arm of conglomerate Vingroup, has purchased back 246.98 million shares, meeting 66.75% of the plan and accounting for 5.7% of the outstanding volume.

Finance - Thu, November 21, 2024 | 8:43 pm GMT+7

Vietnam high-speed railway should run beyond Hanoi, HCMC on either side: lawmakers

Vietnam high-speed railway should run beyond Hanoi, HCMC on either side: lawmakers

Vietnam’s mega North-South high-speed railway project should be redesigned and extended beyond Hanoi and Ho Chi Minh City as currently planned, several lawmakers have suggested.

Infrastructure - Thu, November 21, 2024 | 6:11 pm GMT+7

Vietnam-Malaysia relationship upgraded to comprehensive strategic partnership

Vietnam-Malaysia relationship upgraded to comprehensive strategic partnership

Vietnam and Malaysia have upgraded their relationship to a comprehensive strategic partnership, the highest level in the former’s diplomatic hierarchy.

Politics - Thu, November 21, 2024 | 5:21 pm GMT+7

Petrovietnam units sign LNG supply deal for trial run of Vietnam’s first LNG power plants

Petrovietnam units sign LNG supply deal for trial run of Vietnam’s first LNG power plants

PV Power and PV Gas, two units of state-owned Petrovietnam, have signed an LNG supply deal for trial operation of Nhon Trach 3 and Nhon Trach 4, Vietnam’s first LNG-to-power plants.

Energy - Thu, November 21, 2024 | 4:40 pm GMT+7

Sufficient first phase funds ensured for Vietnam’s new mega airport: transport minister

Sufficient first phase funds ensured for Vietnam’s new mega airport: transport minister

Minister of Transport Nguyen Van Thang affirmed Wednesday that funding would be secured for building the Long Thanh International Airport, set to become Vietnam’s biggest.

Infrastructure - Thu, November 21, 2024 | 3:53 pm GMT+7

Bamboo Capital wins kudos for transparent reports, good governance

Bamboo Capital wins kudos for transparent reports, good governance

Vietnamese private conglomerate Bamboo Capital Group has been honored as a Top 20 business with the Best Annual Report and the Best AGM Organization at the 2024 Vietnam Listed Company Awards (VLCA).

Bamboo Capital - Thu, November 21, 2024 | 3:37 pm GMT+7

VAFIE to organize workshop on amendments to horse racing, football betting rules

VAFIE to organize workshop on amendments to horse racing, football betting rules

The Vietnam’s Association of Foreign Invested Enterprises (VAFIE) and The Investor will organize a workshop on suggestions to amend the government’s Decree 06 on horse racing, greyhound racing and international football betting services.

Economy - Thu, November 21, 2024 | 2:38 pm GMT+7

Vietnam Politburo okays international, regional financial centers in HCMC, Danang

Vietnam Politburo okays international, regional financial centers in HCMC, Danang

Vietnam’s highest decision-making body, the Politburo, has greenlighted the establishment of an international financial center in Ho Chi Minh City and a regional financial center in the central city of Danang.

Economy - Thu, November 21, 2024 | 1:50 pm GMT+7

Singapore's Platinum Victory seeks to gain veto at Vietnam’s REE

Singapore's Platinum Victory seeks to gain veto at Vietnam’s REE

Singaporean fund Platinum Victory Pte. Ltd. has registered to buy more shares of Ho Chi Minh City-based utility firm Refrigeration Electrical Engineering Corporation (REE) to achieve the vetoing power in the latter.

Finance - Thu, November 21, 2024 | 11:29 am GMT+7

Posco keen on investing in Vietnam's $2.2 bln LNG power project

Posco keen on investing in Vietnam's $2.2 bln LNG power project

South Korea’s steelmaker Posco is eyeing to invest in the $2.2 billion Quynh Lap LNG-fired power plant project in Vietnam’s central province of Nghe An.

Energy - Thu, November 21, 2024 | 10:42 am GMT+7

Vietnam firm Hoa Lam to build $212 mln Aeon Mall in Mekong Delta

Vietnam firm Hoa Lam to build $212 mln Aeon Mall in Mekong Delta

The Mekong Delta city of Can Tho has accepted a subsidiary of private multi-sector Hoa Lam Group as the investor of the Aeon Mall Can Tho commerce and service center.

Industries - Thu, November 21, 2024 | 10:31 am GMT+7