Long-delayed HCMC metro lines face even more delays

By Tuong Nguyen
Wed, October 12, 2022 | 8:22 am GMT+7

The prolonged delays to HCMC’s first and second metro lines are likely to extend even further, mired as they are in site clearance and funding problems, the transport ministry says.

In a new report to the government, the ministry (MoT) said the southern economic hub wants to complete Line 1 (Ben Thanh-Suoi Tien) in the fourth quarter of 2023 and Line 2 (Ben Thanh-Tham Luong) in 2030. The previous timeline for Line 1 was Q4/2021.

Line 1, estimated to cost over VND43.7 trillion ($1.89 billion), will run around 20 kilometers from the Ben Thanh area in District 1 to Long Binh Depot in Thu Duc city on HCMC’s outskirts.

Some railway wagons already in place for the unfinished Metro Line 1 project in HCMC. Photo courtesy of Legal newspaper.

Some railway wagons already in place for the unfinished Metro Line 1 project in HCMC. Photo courtesy of Legal newspaper.

According to the report, 92.2% of the construction of Line 1 has been completed and the ratio is expected to reach 93% by the end of this year, but site clearance is still not completed.

In terms of construction packages, the Ben Thanh-City Theater underground section is almost 97.2% complete; the City Theater-Bason Station underground section is almost 99.64% complete; the section of elevated railroads and depots is nearly 96.2% complete; and the package of locomotives, wagons, electric equipment, tracks and maintenance is about 83% complete.

There are three packages yet to start, namely the IT system for operations, the construction of operation and management offices, and the consulting package for the whole system’s safety.

The main reasons for further delays, according to the report, include more time needed for the HCMC administration to adjust the design, resolve contractor complaints, add additional costs and speed up site clearance work that has been very slow. Besides, the technologies used for Line 1 are completely new to Vietnam, and it is taking more time to learn.

"In addition, the work of making, appraising and approving the project's applications for more funding has taken a long time and but not been completed so far,” the ministry wrote in the report, citing another reason from the city administration.

The Line 2 project has seen even longer delays, according to the ministry. The project was originally approved for completion between 2010 and 2018, then adjusted to 2021-2026, and now to 2030.

The ministry report listed different reasons for the long delay, including site clearance problems. As of now, 85.15% of the site has been cleared, with the biggest remain obstacles lying in District 3, part of the central business district.

The consulting contract for the second metro line, signed in 2012 by the Management Authority for Urban Railways (MAUR) of HCMC and Implementation Consultant (IC), was terminated by an IC announcement this March.

The two-phase consulting contract expired in 2018 as stated in the agreement; and the consulting firm stopped supplying services for the first phase of the project. Then the MAUR had to end the second phase of the contract. In 2019, MAUR and IC held negotiations on Appendix 13 of the contract to complete the rest of the first phase. The negotiations lasted two years, but no consensus was reached.

In May 2021, the city decided to end Appendix No. 13 negotiations with IC. However, IC later proposed resuming negotiations to complete some main bidding packages. The city government assigned MAUR to get back to the negotiation table with IC. However, IC announced this March that it had ended the consulting contract.

The process of selecting a new consulting firm is ongoing, but the selection might last 12 to 18 months, according to city officials.

The Line 2 project, about 11 km long with 10 stations, is estimated to cost a total of VND47.89 trillion ($2.08 billion).

In all, HCMC has eight metro line projects planned with a combined length of 220 kilometers and estimated costs totaling almost $25 billion.

Comments (0)
  • Read More
Vietnam’s pepper exports surpass $1 bln in 8 months

Vietnam’s pepper exports surpass $1 bln in 8 months

Vietnam’s pepper industry recorded export revenue of more than $1 billion in the first eight months of 2025, the highest level for the period in seven years, according to the Vietnam Pepper and Spice Association (VPSA).

Companies - Tue, September 9, 2025 | 11:13 pm GMT+7

Indonesia, EU to sign CEPA after decade of negotiations

Indonesia, EU to sign CEPA after decade of negotiations

The Indonesia-European Union Comprehensive Economic Partnership Agreement (IEU-CEPA) is set to be signed on September 23 after a decade of negotiations, according to Indonesian Coordinating Minister for Economic Affairs Airlangga Hartarto.

Southeast Asia - Tue, September 9, 2025 | 10:07 pm GMT+7

Vietnam lifts asset freeze on ex-FLC chairman Trinh Van Quyet

Vietnam lifts asset freeze on ex-FLC chairman Trinh Van Quyet

Authorities in Vietnam’s central province of Khanh Hoa are moving to lift restrictions on asset transactions and transfers linked to Trinh Van Quyet, former chairman of property developer FLC Group, the provincial Department of Justice said on Tuesday.

Economy - Tue, September 9, 2025 | 9:26 pm GMT+7

Abbott-backed medical firm Domesco to pay 25% cash dividend

Abbott-backed medical firm Domesco to pay 25% cash dividend

Domesco Medical Import Export JSC (HoSE: DMC) will distribute a 25% cash dividend for 2024, equivalent to VND2,500 (9.5 U.S. cents) per share.

Companies - Tue, September 9, 2025 | 8:39 pm GMT+7

Vietnam’s finance ministry proposes raising personal deduction to $588 per month

Vietnam’s finance ministry proposes raising personal deduction to $588 per month

Vietnam’s Ministry of Finance has proposed raising the personal income tax deduction to VND15.5 million ($588) per month and the dependent deduction to VND6.2 million ($235).

Economy - Tue, September 9, 2025 | 4:09 pm GMT+7

PM requests prompt finalization of feasibility study for Lao Cai-Hanoi-Hai Phong railway project

PM requests prompt finalization of feasibility study for Lao Cai-Hanoi-Hai Phong railway project

Prime Minister Pham Minh Chinh on Sunday evening chaired a high-level meeting with key ministries and agencies to accelerate the implementation of the Lao Cai-Hanoi-Hai Phong railway project, during which he stressed the need for prompt completion of the project’s feasibility study.

Economy - Tue, September 9, 2025 | 3:06 pm GMT+7

WB, ADB to provide over $12 bln to green projects in ASEAN

WB, ADB to provide over $12 bln to green projects in ASEAN

The World Bank has allocated $2.5 billion, while the Asian Development Bank has set aside $10 billion to support green projects in ASEAN, said Malaysian Deputy Prime Minister Datuk Seri Fadillah Yusof.

Southeast Asia - Tue, September 9, 2025 | 3:01 pm GMT+7

Central Vietnam province seeks investors for $42 mln wind power project

Central Vietnam province seeks investors for $42 mln wind power project

Vietnam’s central province of Quang Tri is seeking investors for the Hung Bac wind power project, with total investment estimated at VND1.1 trillion ($41.69 million), according to the provincial People’s Committee.

Energy - Tue, September 9, 2025 | 2:56 pm GMT+7

Vietnam's leading conglomerate Vingroup sues 68 entities, individuals for false information

Vietnam's leading conglomerate Vingroup sues 68 entities, individuals for false information

Vingroup JSC (HoSE: VIC) on Monday reported to authorities, notified foreign embassies, and filed civil lawsuits against 68 organizations and individuals at home and abroad for spreading false information about the corporation online.

Companies - Tue, September 9, 2025 | 10:45 am GMT+7

Warburg Pincus unit, Masterise eye $739 mln expressway to Vietnam’s mega airport

Warburg Pincus unit, Masterise eye $739 mln expressway to Vietnam’s mega airport

A subsidiary of U.S. private equity firm Warburg Pincus and Vietnamese developer Masterise Group have separately proposed building an over VND19.52 trillion ($739 million) expressway connecting a major tourism area to the under-construction Long Thanh International Airport in the southern region.

Infrastructure - Tue, September 9, 2025 | 8:00 am GMT+7

Hoa Binh Construction wins $5 bln contract for mega urban project in southern Vietnam

Hoa Binh Construction wins $5 bln contract for mega urban project in southern Vietnam

Vietnam's leading contractor Hoa Binh Construction Group has secured a contract to build the first phase of a mega urban area project in Vietnam’s southern metropolis of Ho Chi Minh City.

Real Estate - Mon, September 8, 2025 | 9:22 pm GMT+7

Vietnam's monetary policy remains accommodative: WB

Vietnam's monetary policy remains accommodative: WB

Vietnam's monetary policy has remained accommodative, as State Bank of Vietnam (SBV) interventions contained foreign exchange pressures and increased credit growth, the World Bank Group said in its country economic update.

Economy - Mon, September 8, 2025 | 7:46 pm GMT+7

Property, technology, energy among sectors recording highest M&A activity in Vietnam

Property, technology, energy among sectors recording highest M&A activity in Vietnam

Vietnam’s M&A landscape in July recorded 34 completed transactions with the total disclosed and estimated deal value of $786 million, according to Grant Thornton Vietnam.

Economy - Mon, September 8, 2025 | 3:49 pm GMT+7

Vietnam's Van Thinh Phat-tied firm incurs $14 mln loss in H1 as legal woes persist

Vietnam's Van Thinh Phat-tied firm incurs $14 mln loss in H1 as legal woes persist

Bong Sen Corp, the hotel and property arm of troubled Van Thinh Phat Group, posted a net loss of nearly VND356 billion ($14 million) in the first half of 2025, its filing to the Hanoi Stock Exchange (HNX) showed.

Companies - Mon, September 8, 2025 | 3:24 pm GMT+7

Airport-centric urbanization - Vietnam’s new growth engine

Airport-centric urbanization - Vietnam’s new growth engine

In the past, cities in Vietnam would build airports to meet growing transportation needs, but today, airports themselves are becoming the nucleus around which new urban areas emerge.

Real Estate - Mon, September 8, 2025 | 1:36 pm GMT+7

Vietnam’s 8.3-8.5% growth target for 2025 ‘appropriate’: policy advisory council

Vietnam’s 8.3-8.5% growth target for 2025 ‘appropriate’: policy advisory council

The Vietnamese government’s GDP growth target of 8.3-8.5% for 2025 and double-digit expansion for 2026-2030 is "appropriate" in the context of favorable macroeconomic conditions and structural reforms, according to the Prime Minister’s Policy Advisory Council.

Economy - Mon, September 8, 2025 | 1:03 pm GMT+7