Long-delayed HCMC metro lines face even more delays
The prolonged delays to HCMC’s first and second metro lines are likely to extend even further, mired as they are in site clearance and funding problems, the transport ministry says.
In a new report to the government, the ministry (MoT) said the southern economic hub wants to complete Line 1 (Ben Thanh-Suoi Tien) in the fourth quarter of 2023 and Line 2 (Ben Thanh-Tham Luong) in 2030. The previous timeline for Line 1 was Q4/2021.
Line 1, estimated to cost over VND43.7 trillion ($1.89 billion), will run around 20 kilometers from the Ben Thanh area in District 1 to Long Binh Depot in Thu Duc city on HCMC’s outskirts.
According to the report, 92.2% of the construction of Line 1 has been completed and the ratio is expected to reach 93% by the end of this year, but site clearance is still not completed.
In terms of construction packages, the Ben Thanh-City Theater underground section is almost 97.2% complete; the City Theater-Bason Station underground section is almost 99.64% complete; the section of elevated railroads and depots is nearly 96.2% complete; and the package of locomotives, wagons, electric equipment, tracks and maintenance is about 83% complete.
There are three packages yet to start, namely the IT system for operations, the construction of operation and management offices, and the consulting package for the whole system’s safety.
The main reasons for further delays, according to the report, include more time needed for the HCMC administration to adjust the design, resolve contractor complaints, add additional costs and speed up site clearance work that has been very slow. Besides, the technologies used for Line 1 are completely new to Vietnam, and it is taking more time to learn.
"In addition, the work of making, appraising and approving the project's applications for more funding has taken a long time and but not been completed so far,” the ministry wrote in the report, citing another reason from the city administration.
The Line 2 project has seen even longer delays, according to the ministry. The project was originally approved for completion between 2010 and 2018, then adjusted to 2021-2026, and now to 2030.
The ministry report listed different reasons for the long delay, including site clearance problems. As of now, 85.15% of the site has been cleared, with the biggest remain obstacles lying in District 3, part of the central business district.
The consulting contract for the second metro line, signed in 2012 by the Management Authority for Urban Railways (MAUR) of HCMC and Implementation Consultant (IC), was terminated by an IC announcement this March.
The two-phase consulting contract expired in 2018 as stated in the agreement; and the consulting firm stopped supplying services for the first phase of the project. Then the MAUR had to end the second phase of the contract. In 2019, MAUR and IC held negotiations on Appendix 13 of the contract to complete the rest of the first phase. The negotiations lasted two years, but no consensus was reached.
In May 2021, the city decided to end Appendix No. 13 negotiations with IC. However, IC later proposed resuming negotiations to complete some main bidding packages. The city government assigned MAUR to get back to the negotiation table with IC. However, IC announced this March that it had ended the consulting contract.
The process of selecting a new consulting firm is ongoing, but the selection might last 12 to 18 months, according to city officials.
The Line 2 project, about 11 km long with 10 stations, is estimated to cost a total of VND47.89 trillion ($2.08 billion).
In all, HCMC has eight metro line projects planned with a combined length of 220 kilometers and estimated costs totaling almost $25 billion.
- Read More
Vietnam T&T Group, Qatar partner to build $3.2 bln Disneyland park in Hanoi
Vietnam’s conglomerate T&T Group and Qatar’s JTA International Investment Holding will jointly build a $4.5-billion sports and entertainment complex in Hanoi, featuring a Disneyland theme park worth $3.2 billion.
Infrastructure - Fri, November 1, 2024 | 12:08 pm GMT+7
AirAsia to collect mandatory carbon fee starting 2025
Malaysia-based carrier AirAsia will begin imposing a mandatory carbon fee on all passengers starting January 1, 2025, according to the country’s Transport Minister Anthony Loke.
Southeast Asia - Fri, November 1, 2024 | 12:05 pm GMT+7
At least seven killed in bridge collapse in Indonesia
At least seven people were killed and dozens of others were injured when a seaside bridge collapsed in the Maluku island region in eastern Indonesia on Thursday.
Southeast Asia - Fri, November 1, 2024 | 12:04 pm GMT+7
Thailand to raise retirement age to 65
Thailand's Labor Ministry plans to raise the retirement age for both private and government sectors to 65 years, the same as in Singapore and Switzerland, according to Labour Minister Phiphat Ratchakitprakarn.
Southeast Asia - Fri, November 1, 2024 | 12:03 pm GMT+7
A quarter of Singapore’s fish farms stop operations in past year
About a quarter of Singapore’s sea-based fish farms have exited the industry over the past year, figures from Singapore Food Agency (SFA) showed.
Southeast Asia - Fri, November 1, 2024 | 12:02 pm GMT+7
Malaysia plans to launch national AI office
The Malaysian Government plans to launch the National Artificial Intelligence Office (NAIO) in Kuala Lumpur on December 12, according to the country’s Digital Minister Gobind Singh Deo.
Southeast Asia - Fri, November 1, 2024 | 12:00 pm GMT+7
Vingroup posts Q3 earnings of $80 mln, highest in five years
Vingroup, the largest private multi-industry conglomerate in Vietnam by ecosystem, recorded a consolidated net profit of VND2,015 billion ($79.54 million) in Q3/2024, the heftiest quarterly earnings in the past five years.
Companies - Fri, November 1, 2024 | 11:54 am GMT+7
Thailand SCG to invest $700 mln more in $5 bln petrochemicals complex in Vietnam
Thailand’s Siam Cement Group (SCG) will invest an extra $700 million in the $5.2 billion Long Son Petrochemicals Complex (LSP) in Vietnam’s southern province of Ba Ria-Vung Tau to diversify its production.
Industries - Fri, November 1, 2024 | 10:20 am GMT+7
Vietnam manufacturing activity rebounds, recovering from typhoon Yagi
The Vietnamese manufacturing sector in October started to recover from the effects of September's super typhoon, recording renewed increases in both output and new orders.
Economy - Fri, November 1, 2024 | 8:34 am GMT+7
Vietnam private lender VietBank logs 96% profit growth in 9 months
Vietnam Thuong Tin Commercial Joint Stock Bank (VietBank) posted a 96% year-on-year surge in pre-tax profit in the first nine months of 2024 to reach VND820.4 billion ($32.46 million), or 78% of the year's target.
Banking - Fri, November 1, 2024 | 7:45 am GMT+7
Maersk opens its first bonded warehouse in Vietnam
Denmark's integrated transport and logistics giant A.P. Moller - Maersk (Maersk) on Thursday opened its first bonded warehouse in Vietnam at SLP Park, Nam Dinh Vu Industrial Park in Hai Phong city.
Industries - Thu, October 31, 2024 | 11:44 pm GMT+7
ABBank incurs $14 mln loss in Q3
Hanoi-headquartered An Binh Commercial Joint Stock Bank reported a pre-tax loss of VND343.5 billion ($13.59 million) in the third quarter of this year, while some other private Vietnamese banks posted strong profits.
Banking - Thu, October 31, 2024 | 9:29 pm GMT+7
Vietnam’s emergence as regional manufacturing hub a significant logistics opportunity: SuperPort exec
Southeast Asia’s rise as a vital logistics hub with Vietnam positioned as a key manufacturing center presents a significant business opportunity, says Yap Kwong Weng, CEO of Vietnam SuperPort.
Companies - Thu, October 31, 2024 | 9:01 pm GMT+7
Indonesia steps up support for textile industry
Indonesia’s President Prabowo Subianto held a close-door meeting with several ministers on Tuesday to discuss the current situation of Indonesia's textile industry, particularly focusing on textile giant Sri Rejeki Isman (Sritex).
Southeast Asia - Thu, October 31, 2024 | 6:01 pm GMT+7
Thailand speeds up plans to construct six new airports
Thailand’s Transport Ministry is accelerating development and construction projects on six airports with an aim to become the region's transportation hub.
Southeast Asia - Thu, October 31, 2024 | 6:00 pm GMT+7
Thailand develops eco-friendly seaport model
Thailand is striving to implement environmental protection and social sustainability solutions in developing the country’s major infrastructure projects, such as the development of Phase 3 of Laem Chabang Port, Thailand's only deep-sea port.
Southeast Asia - Thu, October 31, 2024 | 5:58 pm GMT+7