Long-delayed HCMC metro lines face even more delays
The prolonged delays to HCMC’s first and second metro lines are likely to extend even further, mired as they are in site clearance and funding problems, the transport ministry says.
In a new report to the government, the ministry (MoT) said the southern economic hub wants to complete Line 1 (Ben Thanh-Suoi Tien) in the fourth quarter of 2023 and Line 2 (Ben Thanh-Tham Luong) in 2030. The previous timeline for Line 1 was Q4/2021.
Line 1, estimated to cost over VND43.7 trillion ($1.89 billion), will run around 20 kilometers from the Ben Thanh area in District 1 to Long Binh Depot in Thu Duc city on HCMC’s outskirts.
Some railway wagons already in place for the unfinished Metro Line 1 project in HCMC. Photo courtesy of Legal newspaper.
According to the report, 92.2% of the construction of Line 1 has been completed and the ratio is expected to reach 93% by the end of this year, but site clearance is still not completed.
In terms of construction packages, the Ben Thanh-City Theater underground section is almost 97.2% complete; the City Theater-Bason Station underground section is almost 99.64% complete; the section of elevated railroads and depots is nearly 96.2% complete; and the package of locomotives, wagons, electric equipment, tracks and maintenance is about 83% complete.
There are three packages yet to start, namely the IT system for operations, the construction of operation and management offices, and the consulting package for the whole system’s safety.
The main reasons for further delays, according to the report, include more time needed for the HCMC administration to adjust the design, resolve contractor complaints, add additional costs and speed up site clearance work that has been very slow. Besides, the technologies used for Line 1 are completely new to Vietnam, and it is taking more time to learn.
"In addition, the work of making, appraising and approving the project's applications for more funding has taken a long time and but not been completed so far,” the ministry wrote in the report, citing another reason from the city administration.
The Line 2 project has seen even longer delays, according to the ministry. The project was originally approved for completion between 2010 and 2018, then adjusted to 2021-2026, and now to 2030.
The ministry report listed different reasons for the long delay, including site clearance problems. As of now, 85.15% of the site has been cleared, with the biggest remain obstacles lying in District 3, part of the central business district.
The consulting contract for the second metro line, signed in 2012 by the Management Authority for Urban Railways (MAUR) of HCMC and Implementation Consultant (IC), was terminated by an IC announcement this March.
The two-phase consulting contract expired in 2018 as stated in the agreement; and the consulting firm stopped supplying services for the first phase of the project. Then the MAUR had to end the second phase of the contract. In 2019, MAUR and IC held negotiations on Appendix 13 of the contract to complete the rest of the first phase. The negotiations lasted two years, but no consensus was reached.
In May 2021, the city decided to end Appendix No. 13 negotiations with IC. However, IC later proposed resuming negotiations to complete some main bidding packages. The city government assigned MAUR to get back to the negotiation table with IC. However, IC announced this March that it had ended the consulting contract.
The process of selecting a new consulting firm is ongoing, but the selection might last 12 to 18 months, according to city officials.
The Line 2 project, about 11 km long with 10 stations, is estimated to cost a total of VND47.89 trillion ($2.08 billion).
In all, HCMC has eight metro line projects planned with a combined length of 220 kilometers and estimated costs totaling almost $25 billion.
- Read More
Foxconn accelerates investment in Vietnam, moves toward humanoid robot manufacturing
Taiwan’s Hon Hai Precision Industry (Foxconn), a major Apple supplier, is signaling a deeper expansion in Vietnam as it pushes beyond traditional electronics manufacturing into higher-value automation, including industrial humanoid robots.
Industries - Fri, April 24, 2026 | 6:44 pm GMT+7
Century Synthetic Fiber Corp. targets 38% profit growth, bets on recycled fiber
Century Synthetic Fiber Corporation (HoSE: STK) aims for a 37.7% increase in 2026 pre-tax profit to VND128.5 billion ($4.88 million), driven primarily by its recycled fiber segment and a newly operational plant invested by its subsidiary Unitex.
Companies - Fri, April 24, 2026 | 5:31 pm GMT+7
Vietnam developer TTC Land eyes steady cash flow with sister firm acquisition
Saigon Thuong Tin Real Estate JSC (TTC Land), a subsidiary of multi-sector conglomerate TTC Group, is moving to secure stable, recurring revenue through the acquisition of Thanh Thanh Nam (TTN), another TTC Group member.
Companies - Fri, April 24, 2026 | 3:31 pm GMT+7
Vietnam, S Korea ink 12 deals, nuclear energy tie-up takes center stage
Vietnam and South Korea have signed 12 cooperation agreements spanning security, technology, energy and culture, with nuclear power collaboration a key highlight.
Economy - Fri, April 24, 2026 | 3:01 pm GMT+7
Thai SCG to halt Vietnam petrochemical plant in mid-May over Middle East conflict
Thai conglomerate Siam Cement Group (SCG) will suspend the operations of its Long Son Petrochemicals Complex in southern Vietnam, starting mid-May, as the Middle East conflict weighs on supply chain.
Energy - Fri, April 24, 2026 | 12:02 pm GMT+7
Vietnam licenses 10th wholly foreign bank after 9-year hiatus
Vietnam has allowed Industrial Bank of Korea (IBK) to establish a wholly foreign-owned, locally incorporated bank - the first such a license in nine years.
Banking - Fri, April 24, 2026 | 9:38 am GMT+7
Vissan falls short of public company criteria over concentrated ownership
Vietnam's leading meat producer Vissan has acknowledged that it fails to meet the requirements to qualify as a public company, citing its current shareholder structure and the absence of a divestment roadmap from state authorities.
Companies - Fri, April 24, 2026 | 8:17 am GMT+7
China's Su Shang seeks infras investment opportunities in northern Vietnam industrial hub
Su Shang Construction Group, a major Chinese infrastructure developer, is exploring investment opportunities in Bac Ninh as the northern Vietnam province steps up efforts to expand its transport and urban infrastructure network.
Infrastructure - Thu, April 23, 2026 | 9:09 pm GMT+7
Vietnam's leading broker SSI posts Q1 profit of $61 mln, trims equity exposure
SSI Securities Corporation reported a Q1 pre-tax profit of over VND1.59 trillion ($60.5 million), as the brokerage scaled back equity investments and margin lending amid volatile markets and rising interest rates.
Companies - Thu, April 23, 2026 | 5:33 pm GMT+7
Vietnam’s housing market posts 2.5-fold rise in new supply, enters selective recovery in Q1
Vietnam’s real estate market showed signs of recovery in the first quarter of 2026, with supply rebounding strongly and demand remaining resilient, even as high prices and cautious sentiment continued to shape buyer behavior.
Real Estate - Thu, April 23, 2026 | 4:30 pm GMT+7
Danang city approves Thaco Group unit to study urban railway project under PPP model
Central Vietnam hub Danang has approved a unit of Truong Hai Group (Thaco) to study investment in a proposed urban railway project under a public-private partnership (PPP) model, the city government said.
Infrastructure - Thu, April 23, 2026 | 3:01 pm GMT+7
VPBank CEO defends higher bad debt as trade-off for growth
Vietnam’s private lender VPBank is willing to tolerate a higher bad debt ratio as a trade-off for growth, reflecting its distinct business model and focus on higher-yield segments, its CEO said.
Banking - Thu, April 23, 2026 | 2:13 pm GMT+7
Diversifying export markets ‘golden key’ for Vietnamese firms: CEO
Expanding into alternative export markets such as India and the Middle East could prove a “golden key” for Vietnamese businesses, as demand in these regions remains strong and entry requirements are less stringent than in the U.S., according to Nguyen Tuan Viet, CEO of Vietgo, an im-export consultancy company.
Economy - Thu, April 23, 2026 | 11:39 am GMT+7
Vietnam banks face tightening margins, liquidity pressures in 2026
Vietnam’s banking sector is entering a period of heightened selectivity in 2026, with capital strength and liquidity management emerging as decisive factors separating lenders able to expand from those forced to scale back operations.
Banking - Thu, April 23, 2026 | 8:17 am GMT+7
Russia’s Novatek eyes LNG investment opportunities in central Vietnam
Novatek, Russia's leading natural gas producer, is exploring investment opportunities in Vietnam’s LNG sector, with a particular focus on Thanh Hoa province.
Energy - Wed, April 22, 2026 | 10:52 pm GMT+7
Vingroup’s VinDynamics partners Schaeffler to develop humanoid robot components
VinDynamics, a tech arm of Vietnam’s conglomerate Vingroup (HoSE: VIC), has signed an MoU with Germany’s motion technology firm Schaeffler to jointly develop key components for humanoid robots.
Companies - Wed, April 22, 2026 | 4:23 pm GMT+7




















